Rooftop Solar Systems Rooftop Solar System (Off-Grid) Reliance Solar Energy™, Ratnagiri
2
Overview
3
Rooftop Solar Systems are the best off-grid solution for rural electrification. It constitutes of PV solar panels, charge controller (optional), storage batteries and inverter systems. Generators could be installed optionally to maintain reliability. PV panels convert solar radiations to electricity, which is then stored in a battery. In order that most of the loads are in AC, stored charge is converted into AC through an inverter and provided to the load.
4
Highlights of Our System Immediate replacement to the existing supply It can be implemented completely off grid i.e. No need of any supply from other electricity provider and state electricity All the appliances such as AC, TV, Refrigerator, Fan, Lamp, Computers etc can be powered No need of any change in existing wiring
5
Design Determining the load Selecting Panels Selecting Battery Size Selecting Inverter
6
Determining the load List all the electrical requirements of the load which are to be used in a day. For example: If you have a 15 watt bulb and you use it for 4 hours a day, than list down the particular Watt-Hour, i.e. in this case 15 Watts x 4 hours = 60 Watt-hours (Wh). Sum all the Wh at the end and the resulting total will be the required system capacity to be built.
7
Selecting Panels PV panels are rated in Watts. So say a PV panel of 100 Watt receiving sunlight for 4 hours would generate 400 Wh. The total load required which was calculated in previous step, say 2000 Wh would require 5 PV panels if it receives 4 hours of sunlight.
8
Selecting Battery Batteries are rated in Ampere- Hours (Ah). Now convert the Wh into Ah by dividing it the battery voltage i.e. 12V. So in our case 2000Wh / 12V, will be 166.67 Ah. Concerning conversion losses and battery safety parameters select rating of battery above 166.67 Ah i.e. say 250 Ah.
9
Selecting Inverter Earlier we calculated the connected load for selecting the battery and PV panels, but in the case of inverter we should consider maximum demand, i.e. the amount of load which are simultaneously ON. This would be lesser than the connected load, since all the connected load are unlikely to be simultaneously ON at a same time.
10
Installation Mounting Solar panels Wiring
11
Mounting Solar panels It must be based on the geographical conditions i.e. based on the latitude of the site. While mounting solar panels; shadows of trees, nearby by buildings must be avoided.
12
Wiring
13
Thank You Reliance Solar Energy™, Ratnagiri