ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration] Fidic 99
3
20.1 Contractor’s Claims If the contractor considers himself to be entitled to any extension of the time for completion and/or any additional payment, The The contractor shall give notice to the engineer, describing the event giving rise to the claim notice shall be given as soon as practicable, and not later than 28 days after the contractor became aware
4
20.1 Contractor’s Claims If the contractor fails to give notice of a claim within 28 days, The The time for completion shall not be extended, contractor shall not be entitled to additional payment employer shall be discharged from all liability in connection with the claim
5
20.1 Contractor’s Claims Otherwise, Otherwise, the following provisions shall apply The The contractor shall also submit any other notices required by the contract, and supporting particulars for the claim contractor shall keep such contemporary records as may be necessary to any claim
6
20.1 Contractor’s Claims The The engineer may, after receivng any notice, monitor the recored-keeping and instruct the contractor to keep further records contractor shall permit the engineer to inspect all these records and shall submit copies to the engineer
7
20.1 Contractor’s Claims Within Within 42 days after the contractor became aware of the event giving rise to the claim, the contractor shall send to the engineer a fully detailed claim including full supporting particulars of the basis of the claim and of the extension of time and/or additional payment claimed
8
20.1 Contractor’s Claims If the event giving rise to the claim has a continuous effect: This This fully detailed claim shall be considered as interim The The contractor shall send further interim claims at monthly intervals, giving the accumulated delay and amount claimed contractor shall send a final claim within 28 days after the end of the effects resulting from the event or within other period proposed by the contractor and approved by the engineer
9
20.1 Contractor’s Claims Within Within 42 days after receiving a claim, the engineer shall respond with approval or with disapproval and detailed comments He He may also request any necessary further particulars
10
20.1 Contractor’s Claims Each Each payment certificate shall include such amounts for any claim as have been reasonably substantiated as due under the relevant provision of the contract The The contractor shall only be entitled to payment for such part of the claim as he has been able to substantiate
11
20.1 Contractor’s Claims The engineer shall proceed to agree or determine The The extension of time for completion And/or And/or the additional payment to which the contractor is entitled under the contract
12
20.1 Contractor’s Claims The requirement of this sub clause are in addition to those of any other sub clause which may apply to a claim
13
20.2 Appointment of the Dispute Adjudication Board Dispute shall be adjudicated by a DAB. The parties shall jointly appoint a DAB by the date stated in the appendix to Tender
14
20.2 Appointment of the Dispute Adjudication Board The The DAB shall comprise, as stated in the Appendix to tender, either one or three suitably qualified persons If If the number is not so stated, the DAB shall comprise three persons
15
20.2 Appointment of the Dispute Adjudication Board If the DAB is to comprise three persons, each party shall nominate one member for the approval of the other party The parties shall consult both these members and shall agree upon the third member who shall be appointed to act as chairman
16
20.2 Appointment of the Dispute Adjudication Board However, if a list of potential members is included in the contract, the members shall be selected from those on the list
17
The The agreement between the parties and either the sole member or each of the three members, shall incorporate the general conditions to adjudicate dispute contained in the appendix of these general conditions
18
20.2 Appointment of the Dispute Adjudication Board The The terms of the remuneration of either the sole member or each of the three members including the remuneration of any expert whom the DAB consults, shall be agreed upon by the parties Each Each party shall be responsible for paying one half of this remuneration
19
20.2 Appointment of the Dispute Adjudication Board If If any time the parties so agree, they may jointly refer a matter to the DAB for it to give its opinion Neither Neither party shall consult the DAB on any matter without the agreement of the other party
20
20.2 Appointment of the Dispute Adjudication Board If If at any time the parties so agree, they may appoint a suitably qualified person or persons to replace any one or more members of the DAB
21
20.2 Appointment of the Dispute Adjudication Board The The appointment of any member may be terminated by mutual agreement of both parties, but not by the employer or the contractor acting alone.
22
20.3 Failure to Agree Dispute Adjudication Board If any of the following conditions apply: The The parties fail to agree upon the appointment of the sole member of the DAB by the date stated in the appendix to tender Either Either party fails to nominate a member for approval by the other party of a DAB by such date
23
20.3 Failure to Agree Dispute Adjudication Board The The parties fail to agree upon the appointment of the third member ( to act as chairman) parties fail to agree upon the appointment of a replacement person within 42 days after the date on which the sole member is unable to act ….
24
20.3 Failure to Agree Dispute Adjudication Board Then Then the appointing entity or official named in the particular conditions shall, upon the request of either or both of the parties, appoint this member of the DAB This This appointment shall be final and conclusive
25
20.4 Obtaining Dispute Adjudication Board’s Decision If If a dispute arises between the parties in connection with the contract or the execution of the works, either party may refer the dispute in writing to the DAB for its decision, with copies to the other party and the engineer
26
20.4 Obtaining Dispute Adjudication Board’s Decision For For a DAB of three persons, the DAB shall be deemed to have received such reference on the date when it is received by the chairman of the DAB
27
20.4 Obtaining Dispute Adjudication Board’s Decision Both Both parties shall promptly make available to the DAB all such additional information, further access to the site, and appropriate facilities ….
28
20.4 Obtaining Dispute Adjudication Board’s Decision Within Within 48 days after receiving such reference, the DAB shall give its decision, which shall be reasoned The The decision shall be binding on both parties, who shall promptly give effect to it unless and until it shall be revised in an amicable settlement or an arbitral award
29
20.4 Obtaining Dispute Adjudication Board’s Decision If If either party is dissatisfied with the DAB’s decision, then either party may within 28 days after receiving the decision, give notice to the other party of its dissatisfaction the DAB fails to give its decision within the period of 84 days, then either party may within 28 days after this period has expired, give notice to the other party of its dissatisfaction
30
20.4 Obtaining Dispute Adjudication Board’s Decision In either event, this notice of dissatisfaction shall state that it is given under this sub clause, and shall set out the matter in dispute and the reasons for dissatisfaction
31
If the DAB has given its decision as to a matter in dispute to both parties, and no notice of dissatisfaction has been given by either party within 28 days after it received the decision, then the decision shall become final and binding upon both parties
32
الحمد لله رب العالمين Thank You