Design-Build at CDOT Minnesota Design-Build Workshop November 30, 2000.

Similar presentations


Presentation on theme: "Design-Build at CDOT Minnesota Design-Build Workshop November 30, 2000."— Presentation transcript:

1 Design-Build at CDOT Minnesota Design-Build Workshop November 30, 2000

2 Design-Build at CDOT Overview CDOTs Definition CDOTs Progress to Date CDOTs Planned Use of Design-build

3 Design-Build at CDOT Definition of Design-Build Single-Point Responsibility Performance Standards and Specifications Warranty/Long Term Maintenance

4 Design-Build at CDOT Change from Tradition Selection Method Team Approach Owners Role

5 Design-Build at CDOT Benefits Reduced Time Reduced Cost Higher Quality/Innovation

6 Design-Build at CDOT Legislation 1999 Session Clear, Direct Authority Authorized Rules

7 Design-Build at CDOT Design-Build Rules Industry and Agency Involvement Process for Progress Effective December 31, 1999

8 Design-Build at CDOT Contract Documents Goals of Project Uniqueness of Projects Industry Involvement

9 Design-Build at CDOT Flexibility vs. Defined Multiple Award Methods Changes to Team Warranty/Long Term Maintenance

10 Design-Build at CDOT Two-Phase Selection Request for Qualifications Request for Proposals Best and Final Offer (BAFO)

11 Design-Build at CDOT Other Hot Issues Stipends Conflict of Interest Subcontracting

12 Design-Build at CDOT Controls on Process QC/QA Award Fees Chief Engineers Review Team

13 Design-Build at CDOT Southeast Corridor Project A Multi-Modal Transportation Project Estimated to cost 1.4 Billion Dollars

14 Design-Build at CDOT Highway Construction Reconstruct I 25 from Broadway to University Widen I 25 from University to Lincoln Avenue

15 Design-Build at CDOT Highway Construction (Cont.) Widen I 225 from I 25 to Parker Road

16 Design-Build at CDOT Light Rail Transit (LRT) Construction West Side of I 25, Construct LRT from existing Broadway station to Lincoln Avenue

17 Design-Build at CDOT LRT Construction (Cont.) In Median of I 225, Construct LRT from I 25 to Parker Road Construct 13 LRT Stations

18 Design-Build at CDOT Southeast Corridor Project expected to be complete during 2008

19 Design-Build at CDOT Summary Will happen! Thanks to Industry! Commitment to Cooperate!