Miguel GIL COSTA CIEMAT CERN TE-VSC EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015.

Slides:



Advertisements
Similar presentations
Method of beam extraction from a synchrotron by the instrumentality of multilayer Cu-Fe shield Bondarenko Alexey.
Advertisements

XFEL Undulator Efforts at DESY and Thoughts on LCLS-II H.-D. Nuhn June 30, 2010.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
SPSU Progress on coatings and grooves M.Taborelli -Progress on C based coatings -Progress on rough coatings -Progress on SEY instrument -Grooves.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
Compressor status AWAKE Technical Board meeting 19 May 2015.
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Erhard Huttel ISS/ANKA 1 CLIC damping wiggler CERN Vacuum Requirements etc. for ANKA General Requirements for UHV Vacuum: Pressure without.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
CLASSE prototype: mechanical concepts G. De Michele, EPFL-PSI-CERN on behalf of CERN team SLAC, 16 th April, 2012.
Hyperbolas 9.3. Definition of a Hyperbola A hyperbola is the set of all points (x, y) in a plane, the difference of whose distances from two distinct.
Vacuum Controls Status MACS week December 2010 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
ASTeC Report for CLIC-UK Jim Clarke on behalf of all ASTeC & Technology Department staff contributing to CLIC-UK STFC Daresbury Laboratory, UK CERN-UK.
BEPCII Prealignment Installation Survey and Alignment Accelerator Center of IHEP Xiaolong Wang
1 Francis Perez WP4 Cryogenic Beam Vacuum System Conception EuroCirCol WP4 – Cryogenic Beam Vacuum Concept Cryo Beam Vacuum Objectives,
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Compressor status AWAKE Technical Board meeting 19 August 2015.
ALBA Vacuum System, E. Al-Dmour Vacuum Systems for Synchrotron Light Sources 12 th -13 th Sep ALBA Vacuum System ALBA VACUUM SYSTEM E. Al-Dmour On.
Status of the activities on vacuum system C. Garion TBMWG, 20/06/2012.
Heat load of the radiation cooled Ti target of the undulator based e+ source Felix Dietrich (DESY, TH-Wildau),Sabine Riemann(DESY), Andriy Ushakov(U- Hamburg),
Preliminary calculations for the vacuum system of ELENA R. Kersevan TE/VSC-IVM – 21/6/2012 The vacuum sectors, the position of vacuum pumps, flanges, and.
CEA DSM Dapnia DIRAC-Phase-1 Annual Report meeting Status of the R3B-GLAD Magnet DIRAC-Phase-1 Annual Report Meeting 26 September 2006 Bernard Gastineau.
CLIC08 workshop CLIC module layout and main requirements G. Riddone, on behalf of the CMWG Home page of the TBM WG:
Status of Vacuum Control System MACS week June 2011 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
IFS prototype – PM3 LAM, 13/06/2003 Prototype testing at CRAL Tests at room temperature in the visible.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
CARE SC meeting, CERN, 13th September, Report on SRF Work-packages WP7Power Couplers WP8Tuners WP9 Low level RF WP10Horizontal Cryostat Integration.
Outline Injection septum SMH42 Injection bumper Resources Conclusion LIU-ABT review 20/11/2015 Status PS injection septa2.
An electron/positron energy monitor based on synchrotron radiation. I.Meshkov, T. Mamedov, E. Syresin, An electron/positron energy monitor based on synchrotron.
CLIC requirements on Warm Magnets (for CLIC Modules mainly) 1 M. Modena, CERN TE-MSC 13 April 2011 CERN-UK Collaboration Kick-off Meeting.
BPM for Spectromety development status A. Lyapin.
PSB H 0 -H - Injection: Sectorisation Analysis C.Pasquino, J. Hansen, P.Chiggiato 1LIU - PSB Ho-H- Injection Meeting.
1 COBRA Magnet Status W.Ootani MEG Experiment Review Meeting, Jul W.Ootani MEG Experiment Review Meeting, Jul
Krzysztof Radwan, PJAS, TE/VSC/ICM Interlocks, Controls and Monitoring Section HIE-ISOLDE Vacuum Controls INSTALLATION.
ANKA Synchrotron Radiation Facility 1 S.Casalbuoni, E. Huttel, WP4 Coordination Meeting , CERN, Geneva, Switzerland EuroCirCol Kickoff Meeting,
Carles Colldelram EuroCirCol Kick of meeting, CERN 03/06/2015 CERN March’15 EuroCirCol Kick of meeting Study Beam Induced Vacuum Effects.
1 Francis Perez WP4 Cryogenic Beam Vacuum System Conception EuroCirCol WP4 – Cryogenic Beam Vacuum Concept Cryo Beam Vacuum Summary.
1 BROOKHAVEN SCIENCE ASSOCIATES 12th International Workshop on Accelerator Alignment September 10-14, 2012 Fermilab, Batavia, Illinois, U.S.A NSLS-II Girder.
Mitglied der Helmholtz-Gemeinschaft Status of day-one experiment commissioning at COSY Huagen Xu Goa, Mar
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
First evaluation of Dynamic Aperture at injection for FCC-hh
WP4 Cryogenic Beam Vacuum System Conception: Activity LNF (task 4.4, 4.6) R. Cimino LNF-INFN, Frascati (Italy) 1.
M. Sullivan Apr 27, 2017 MDI meeting
on behalf of the CLIC active pre-alignment team
Same Day Access to Mental Health
Installation of an Instrument on a CERN machine
Francis Perez (ALBA) and Paolo Chiggiato (CERN)
Manufacturing of the first FCC-hh beam screen prototype for ANKA
Status of Vacuum Control System
Some Thoughts About Possible Measurements with SR at DaFne
Structural Fire Engineering, October 2015, Dubrovnik, Croatia
Components for the Machine-Interface Regions
R. Kersevan, TE-VSC-VSM 30/06/2016
List of changes and improvements for the next generation CLIC module
Status and needs of dynamic aperture calculations
IDEA Detector Simulation Status
Operation and Safety ART Review Harald Sinn.
Challenges for FCC-ee MDI mechanical design
XFEL Bunch Compressor BC1 and BC2 Vacuum Issues
X-Ray Transport, Optics, and Diagnostics WBS Alan J
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Two-beam Test-stand Design and Construction Status
SR Background Update for JLEIC
Presentation transcript:

Miguel GIL COSTA CIEMAT CERN TE-VSC EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015 M. GIL COSTA 2 Test Set-Up at ANKA Outline: ANKA Facility Current Status/Next Steps FCC Beam Screen Prototype Test Bench Next Steps ANKA Test Line full definition Schedule Conclusion

Vacuum, Surfaces & Coatings Group Technology Department 3 M. GIL COSTA position ANKA Facility ANKA FacilityCurrent StatusNext StepsScheduleConclusion ANKA Facility EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department Existing Beam Line slit Valve Absorber Pump Distance source to set up center: 5.5 m Set up 4 M. GIL COSTA Information summary: Free space Length from the source to the wall: ~ 7 m “Useful” length? (~ up to 2-3 m ?) Beam height: 1.4 m Incidence angle: 6.4 mrad Operating ANKA at 2.2 GeV Horizontal slit opening at 4m: 6.2 mrad SR load : ~ 110 W Flux: ~ ph/s ANKA Facility ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 5 M. GIL COSTA Some components are available on site Proposition Sketch beam line + set up (thanks to E. Huttel) Vertical scrapper with fixed horizontal mask ANKA Facility ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 6 Information to be defined: Design of absorbers needed or they are existent elements? Dimensions of existent elements to integrate on CATIA model? Alignment and survey system? Control and acquisition system ? Definition of the set up functionalities Finalisation of the instrumentation needs M. GIL COSTA ANKA Facility ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 7 Current Status / Next Steps Beam Screen Prototype ANKA FCC Test Bench ANKA FCC Test Line M. GIL COSTA Current StatusNext Steps ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 8 Beam Screen (15m long) Beam Screen Prototype (≈2m) M. GIL COSTA Current Status ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 9 ANKA FCC Test Bench Supports adaptation from an existent design Vacuum Chamber FCC Beam Screen Prototype Centring System M. GIL COSTA Current Status ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 10 M. GIL COSTA FCC Beam Screen Prototype Centring System Supports adaptation from an existent design ANKA FCC Test Bench Current Status ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 11 Next Steps ANKA FCC Test Line Complete definition of the line with the inputs taken in the last days Check integration with ANKA Listing components and costs Start of production and material orders M. GIL COSTA Next Steps ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 12 Schedule Design phase end expected by end of November 2015 Fully definition of the line is not yet defined M. GIL COSTA Schedule ANKA FacilityCurrent StatusNext StepsScheduleConclusion Seems difficult to be finished in one week EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 13 Conclusions Beam Screen prototype production definition and 3D model is well advanced. Test Bench design proposition is presented and need to be discussed for further development and future design versions. ANKA Test Line for FCC prototypes has to be defined on the following weeks with priority based on the gathered information after discussion during Orsay meeting. Design Schedule might have to be reconsidered, trying to maintain the same deadline for the next step (procurement/tests in lab) M. GIL COSTA Conclusion ANKA FacilityCurrent StatusNext StepsScheduleConclusion EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 14 M. GIL COSTA EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 15 M. GIL COSTA Thanks for your attention EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015

Vacuum, Surfaces & Coatings Group Technology Department 16 M. GIL COSTA EuroCirCol WP4, Annual meeting 3 Orsay, 19 November 2015