Celeris Systems Microsoft Project Association March 7, 2007.

Slides:



Advertisements
Similar presentations
Microsoft Project Tutorial for Chapters 6 & 7
Advertisements

©2012 Construction Science, LLC 1 Primavera P6 Settings Presented by Karen Reynolds, Partner Construction Science, LLC.
MS Project.
1 Earned Value Management (EVM) with SDSI Toolset Utilities Powerful tools for achieving true Cost/Schedule (C/S) Integration using Microsoft Project and.
OPSM 639, C. Akkan Before starting this section SAVE AS YOUR EXISTING MS PROJECT FILE AS -part3-1 -part3-1.
Microsoft Project.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Applied Software Project Management Andrew Stellman & Jennifer Greene Applied Software Project Management Applied Software.
Copyright © Software Process Group 1 Software Process Group Microsoft Project Tutorial Steve Meyers
Microsoft Office Project 2007: Managing Projects.
Project Management Software Tools Cheryl A. Wilhelmsen Lee Ostrom.
OPSM 639, C. Akkan SAVE your existing MS Project File at the end of PART3 as _PART4 _PART4 WITH BASELINE. Make sure you keep the original file without.
MS-Project tutorial Phongphan Danphitsanuphan CSSE – Computer Science Dept University of Southern California.
USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and.
Project Management Software Application PRM 705 Lecture 30.
Refining Your Project Plan Lesson 4. Skills Matrix SkillsMatrix Skill Apply a task calendar to an individual task Change task typesChange scheduling formula.
Project Management Methodology Project monitoring and control.
Evaluation#3 MS Project Objectived u In this lab you will learn: – how to add the resources into tasks. –How to review resource assignment information.
1 Managing Resource Utilization using Microsoft Project Leveling Presented by Larry Christofaro, PMP, MCITP February 29, 2008.
Ahmad Al-Ghoul. Learning Objectives Explain how to begin working in your project by Gathering Information, Determining detail tasks, Determining detail.
© 2002 ComputerPREP, Inc. All rights reserved. Project 2000: Module I.
Advanced Project Plan Formatting Lesson 14. Skills Matrix SkillsMatrix Skill Customize the calendar view Format bar styles for tasks in the Calendar view.
© 2002 ComputerPREP, Inc. All rights reserved. Project 2000: Module II.
Kevin Long Project Controls eCAM Notebook Training Manual.
This material is approved for public release. Distribution is limited by the Software Engineering Institute to attendees. Sponsored by the U.S. Department.
Microsoft Project – Tutorial 4 Assigning Resources to Tasks Switch to the Gantt Chart View Then click the Assign Resources button on the Standard toolbar.
Creating Effort Driven Schedules.  Objectives Understanding Your Job and the Tools Job Understanding Task Types Six Steps to an Effort Driven Project.
Ahmad Al-Ghoul. Learning Objectives Explain what a Microsoft Project environment and Project Server. Describe how to use the Ribbon, Quick Access Toolbar.
Project Management Software Application PRM 705 Lecture 32 1.
EARNED VALUE MANAGEMENT (EVM)
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Title of presentation goes here Name of presenter Location/date © 2005 MPA. All rights reserved. Task Management in MS Project Genea Mallow-Jensen President,
Project Management Software Application PRM 705 Lecture 15 Mian Wasim Irshad.
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
Loading data into the ETC and into the MPM Baseline.
MS Project Tips & Tricks Presenter: Natalie Wieland PMP, MCSD, MCDBA, OCPDBA, MCT.
© 2008 Sterling Commerce. Confidential and Proprietary. How to Get Along with Project Using Microsoft Project so that it actually works for you, not against.
Project Management– MilliKab Aïda Amrabt, Carole Decorps, Mark Kepeneghian, Lorianne Rollet.
Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.
How to keep Microsoft Project from being the Project 1/8/2003.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
1 Two Places to Enter Time My Tasks (Project Plans, Proposals and Activity Plans) My Timesheets (Periods and Administrative Time)
Project Setup and Execution For PMPlan Enterprise Presented by AlNik Solutions Copyright ©
Microsoft Project Tutorial for CSCI 577 Fall 2006 Jesal Bhuta
Microsoft Project 2010 ® Tutorial 4: Assigning Resources and Costs.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Parallon Business Solutions Microsoft Project Server 2010 Project Server 2010 Concepts of Working with Tasks.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
Microsoft Project Mastering Microsoft Project 2010 Instructor: Tom Vorves Dial In:1 (800)
Measuring Project Performance MS Project. Key Performance Indicators (KPIs) Quantifiable measurements – Reflect and measure achievements on critical success.
MS Project Tips and Tricks November 4, 2008 PMI-SVC Scheduling Forum.
Microsoft Project 2003 By: Mahmoud Saad El-Din. Topics  Creating a new project.  Working with workspace project.  Defining project information.  Working.
© 2008 Prentice HallAppendix A -1 Introduction to Project Management Appendix Microsoft Project Tutorial Information Systems Project Management: A Process.
Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering
Microsoft Project 101: How to Build a Project Plan
Earned Value Management
In this tutorial you will:
ENGINEERING MANAGEMENT (GE 404)
SSI Toolbox Status Workbook Overview
ELC 347 project management
Performance Tracking & Cost Schedule Integration
MS Project Add-on for Earned Value Analysis Reporting
ENGINEERING MANAGEMENT (GE 404)
Project Management © 2004 D. J. Foreman.
Project Management © 2004 D. J. Foreman.
Project Management © 2008 D. J. Foreman.
Presentation transcript:

Celeris Systems Microsoft Project Association March 7, 2007

Celeris Systems About Me Jim Aksel, PMP Director of Project Management Celeris Systems, Inc Telephone:

Celeris Systems You get Credit! You may claim 1 hour of CE (or PDUs) PMI References:

Celeris Systems Backward Compatibility to 2003

Celeris Systems Task Types Resource Issues & Leveling Custom Sorting Conclusion EVMS in Project

Celeris Systems Sorting Custom Sorts EVMS Tasks Leveling Resources

Celeris Systems Fixed Units Effort Driven Fixed Duration Effort Driven Fixed Duration Not Effort Driven Fixed Units Not Effort Driven Fixed Work Title TASKS

Celeris Systems Task Type Definitions Fixed Units –The allocations of resource units is held constant Fixed Work –Total of all work hours assigned to a task is held constant Fixed Duration –Task Duration is held constant

Celeris Systems Effort Driven Total task work remains at its current value, regardless of how many resources are assigned to the task. When new resources are assigned, remaining work is distributed amongst all assigned resources, proportionately.

Celeris Systems Basic Task

Celeris Systems Basic Task Work Hours Spread

Celeris Systems Added Resources Additional resources just increase total work with no change to duration

Celeris Systems Adding Resources After %Complete Status Date: 15 FEB 2007 On Schedule

Celeris Systems Progress Shown Status Date: 15 FEB 2007 On Schedule

Celeris Systems New Resources Create Remaining Work Status Date: 15 FEB 2007 On Schedule

Celeris Systems Adding Effort Driven Labor Adding Resources reduces duration while keeping total work and units constant No Work Change Added to Basic Task, after making it Effort Driven

Celeris Systems Effort Driven Labor Added after %Complete Adding Effort Driven Labor keeps finish date and work constant, creates split Status Date: 15 FEB 2007 On Schedule

Celeris Systems Adding Effort Driven Labor creates splits Status Date: 15 FEB 2007 On Schedule

Celeris Systems Effort Driven Add Resources Total Work Constant Duration Changes Add Work Changes Duration New resources Add work after Status Date Not Effort Driven Duration fixed Adding Resources adds remaining work Increasing Work increases Duration New resources add work after Status Date Fixed Units Tasks

Celeris Systems Fixed Duration Tasks Not Effort Driven behaves as before Adding resources divides remaining work among all resources

Celeris Systems Fixed Duration w/%Complete Additional Resources share the remaining work Status Date: 15 FEB 2007 On Schedule

Celeris Systems Fixed Work Task Always effort driven Additional Work alters duration while respecting finish date

Celeris Systems You Change UnitsUnits EDDurationDuration EDWork Units Duration Work Duration Work Duration Units Duration Work Units Task Type Fixed: What Project Recalculates ED: Effort Driven

Celeris Systems Sorting Custom Sorts EVMS Tasks Leveling Resources

Celeris Systems Resources Individual names Skill set grouping

Celeris Systems Named Person Unique Calendars Retains Grouping Skill Specific Skill Set List Department Wide Easier to Assign Interchangeable Resource Types

Celeris Systems Named Person Wage/Privacy Harder to swap Skill Specific Skill Set List Department Wide Homogeneous Calendaring Exact Costs TBD Resource Types

Celeris Systems Sorting Custom Sorts EVMS Tasks Leveling Resources

Celeris Systems

Leveling Order Standard Project looks at predecessor, slack (a task with more total slack time is delayed first), dates (a task with a later start date is delayed first), priorities, and constraints Priority, Standard Project looks first at priorities and then at predecessors, slack, dates, and constraints to determine whether and how tasks should be leveled

Celeris Systems Leveling Parameters: Day by Day Level resources when there is at least one day more work scheduled for a resource than can be completed within the resource's normal availability for that day. Week by Week Level resources when there is at least one week more work scheduled for a resource than can be completed within the resource's normal availability for that week. Month by Month Level resources when there is at least one month more work scheduled for a resource than can be completed within the resource's normal availability for that month. This is the default setting.

Celeris Systems Leveling Example: Ringo assigned to two 8 hour tasks in 1 day. Leveling: –Day By Day: Problem –Week By Week: No Problem, work <40 –Month By Month: No Problem, work<160

Celeris Systems Other Leveling Settings Level only within available slack –Finish Dates are respected. Leveling can adjust individual assignments on a task –Adjusts when a resource works on a task independent of the other resources working on the same task. Leveling can create splits in remaining work –Any remaining work can be split for leveling. Unchecked will not delay a task with an Actual Start Date.

Celeris Systems General Guidance IMHO –Project does a pretty good job of leveling since it takes a methodical approach –However, it does level in resource order

Celeris Systems Sorting Custom Sorts EVMS Tasks Leveling Resources

Celeris Systems Standard Sorting Obvious Just Like Excel

Celeris Systems Sorting Custom Sorts EVMS Tasks Leveling Resources

Celeris Systems Custom Grouping (Sorting)

Celeris Systems Custom Grouping Dialog

Celeris Systems Custom Grouping

Celeris Systems More Powerful Options

Celeris Systems Some Grouping Ideas Place custom text field in Resource Usage View –Group by CLIN, Job Number, other accounting information –Assign Control Account Managers –Supplier ID’s WBS Field –Sort by defined code (such as first three levels)

Celeris Systems Sorting Custom Sorts EVMS Tasks Leveling Resources EVMS is my personal opinion

Celeris Systems EVMS in MS Project Cost BCWS = Budgeted Cost of Work Scheduled Cost BCWP = Budgeted Cost of Work Performed Cost ACWP = Actual Cost of Work Performed

Celeris Systems EVMS Comments BCWS & BCWP only register in the Baseline Date Period If you start/finish on different dates you must enter an Actual Date in the [Actual Start] or [Actual Finish] columns

Celeris Systems MS Project uses %Complete Method Think about it – Milestones, Incremental, 80/20, Formula, Apportionment are all subsets of %Complete The trick is accurate definition of %Complete

Celeris Systems Example: Concert 6 Roadies take 2 days to setup Fab Four sing some songs for 1 day 3 Roadies tear down for 1 day

Celeris Systems Resources Singers make $500/hr Roadies make $25/hr Let’s assume everyone is paid cash at the end of each phase (setup, sing, teardown)

Celeris Systems Baseline Schedule and Costs We have a $19K EAC and 4 Days

Celeris Systems %Complete Example After Setup is complete, we claim 50% EV = $9,500 We pay the roadies $2400

Celeris Systems End of Day 3 We claim 75% Complete 0.75 x $19,000 = $14,250

Celeris Systems % Complete Earned Value Parameters ItemMonTuesWedThur BCWS $ 1, $ 16, $ ACWP $ - $ 2, $ 16, $ cBCWS $ 1, $ 2, $ 18, $ 19, cBCWP $ - $ 9, $ 14, $ 19, cACWP $ - $ 2, $ 18, $ 19,000.00

Celeris Systems %Complete EV This is a duration weighted method %Complete =

Celeris Systems %Work Complete This is an Effort weighted method

Celeris Systems %Work Complete At the end of the 2 nd day, 63% of the labor is complete EV= 0.63 x $19,000 = $ 12,000

Celeris Systems %Work Complete End of Day 3 we are 84% Labor Complete 0.84 x $19,000 = $16,000

Celeris Systems Physical%Complete Allows you more flexibility –EV Method Physical%Complete –Each Task Physical%Complete

Celeris Systems Physical % Complete EV for Tasks

Celeris Systems Physical % Complete EV

Celeris Systems Physcial%Complete Day 2 At the end of Setup we are 13% Complete 0.13 x $19,000 = $2400 Note: Project displays only 2 significant digits

Celeris Systems Physical % Complete Day 3 At end of “Hey Jude…” we are 97% Complete 0.97 x $19,000 = $18,400

Celeris Systems Which one does your boss expect?

Celeris Systems