Generator Interconnection Studies & Agreements Charles Hendrix.

Slides:



Advertisements
Similar presentations
Parallel Flow Visualization and Flowgate Allocations Equity Concerns of Non-Market Transmission Owners Equity Concerns of Non-Market Transmission Owners.
Advertisements

GEORGIA POWERS SMALL POWER PRODUCERS FUNDAMENTALS.
Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore.
Excelsior Energy’s Mesaba Energy Project Update for the NM-SPG August 16, 2006.
Al McBride MANAGER, AREA TRANSMISSION PLANNING Existing Import Interfaces: Transmission Transfer Capabilities and The Calculation of Tie Benefits DECEMBER.
PER
Federal Energy Regulatory Commission Large Generator Interconnection Order on Rehearing (Order No A) RM March 3, 2004.
Updated 1/28/2011. Technical Requirements & Regulatory Issues In Interconnection Agreements March 9, 2011 Jay Caspary ·
Public Service Company of New Mexico
1 RTWG Tariff update to the BOD, MOPC, SPC, and RSC January 4, 2005.
WELCOME Western Area Power Administration1. Where did the journey begin? Western Area Power Administration2.
SPP’s 2013 Energy Consumption and Capacity 2 12% annual capacity margin requirement CapacityConsumption Total Capacity 66 GW Total Peak Demand 49 GW.
Transmission Corridor Zone Designation Process Terrence O'Brien, CEC December 11, 2007 Energy Action Plan.
Queue Reform at the Midwest ISO NARUC February, 2008.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Federal Energy Regulatory Commission Proposed Rule on Small Generator Interconnection RM July 23, 2003.
Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM July 23, 2003.
Topics to Cover Interconnection Process Overview
SPP.org 1. 2 Aggregate Transmission Service Study (ATSS)
Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP.
Despite Order No Planning Gaps for (Certain) Merchants OPSI Annual Meeting 2013.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 Network Operating Committee (NOC) June 12 th, 2014.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
Montana Ambassadors Helena, Montana February 25, 2011.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Eagle Crest Energy Company February Page 2 New Hydro: Making it Happen Background on the Eagle Mountain Pumped Storage Project Need for Eagle.
Peak RCCo Performance Metrics Draft –November 2013.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC 10/09/2003 KENNETH A. DONOHOO, P.E. Manager of System Planning Transmission Services
WestConnect Activities Charles Reinhold WestConnect Project Manager 2008 ACC BTA Workshop Phoenix, AZ May 22, 2008.
Energy Gateway Update for Wyoming Infrastructure Authority January 27, 2009 Darrell Gerrard Vice President Transmission System Planning.
OASIS Insights & Observations Transmission Customer Forum September 21-22, 2006 Jim Viikinsalo September 21-22, 2006 Jim Viikinsalo.
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
RPG Meeting Five Year Plan Extension Brad Schwarz.
OSC Meeting April 27, Transmission Cost Allocation Overview.
ATC/TTC Basics Transmission Customer Forum Doug McLaughlin 9/22/06 Transmission Customer Forum Doug McLaughlin 9/22/06.
1 Interconnection Update Jay Zimmerman Manager, Transmission Policy Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
AFC METHODOLOGY EMS USER GROUP SEP 12, 2004 AFC – New Developments EMS USER GROUP Sep
Large Generator Interconnection Procedures Reform 2 nd Stakeholder Meeting May 5, 2009.
October 6, 2006 Public Stakeholder Review Portland, Oregon Conditional Firm.
March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers.
Transmission Issues & Renewables Perspectives of a Wind Developer.
Dale Osborn Midwest ISO October 13, 2008 EE 590 Transmission Planning with Significant Energy Resources.
IWWG Annual Conference Wind Management at MISO July 22, 2011.
© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest.
2013 Wind Conference. Transmission Service Study Process Steve Purdy.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
2006 SPP RTO Expansion Plan Carl A. Monroe July 30, 2006.
Order 1000 Implementation in PJM – Challenges and Opportunities Jodi L. Moskowitz Senior Director – Transmission Development & Strategy October 13, 2015.
Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
SPP.org 1. ICT Working Groups Current Activities Jody Holland Dowell Hudson Antoine Lucas Tim Phillips.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
Rate Design Proposal for SPP: Integrated Transmission Plan and Priority Projects Mike Proctor CAWG May 27, 2009.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
October 15, 2012 PV & Storage Workshop ERCOT’s Interconnection Process John Adams Principal Engineer.
Northern Tier Transmission Group Report to Columbia Grid Planning Committee February 9, 2012 “To ensure efficient, effective, coordinated use & expansion.
Study Plan Development & Approach May 5, 2010 Conference Call & Webinar “To ensure efficient, effective, coordinated use & expansion of the members’
Status Update for Reliability/Market Power Mitigation Assessment
Location, Location, Location
Excelsior Energy’s Mesaba Energy Project
Excelsior Energy’s Mesaba Energy Project
Interconnection Practice, Policies, Procedures ComEd Illinois
Pseudo-tie business procedure
Proposal for Distribution Group Studies
Excelsior Energy’s Mesaba Energy Project
Pseudo-tie business procedure
Offshore Wind Transmission:
Presentation transcript:

Generator Interconnection Studies & Agreements Charles Hendrix

Generator Interconnection Service Energy Resource Interconnection Service – allows a generator to be eligible to use the existing firm or non-firm capacity of the Transmission System on an “as available” basis –Customer must still request Transmission Service Network Resource Interconnection Service – allows the Transmission Owner to construct the necessary upgrades to integrate the generator into the Transmission System in a manner comparable with other Network Resources –Customer must still request Transmission Service 2

Generator Interconnection Service Neither Energy Resource Interconnection Service or Network Resource Interconnection Service gives the generator any right to deliver energy to any customer or point of delivery 3

Generator Interconnection Studies Process Definitive Interconnection System Impact Study (DISIS) – Studied in Clusters Facility Study Limited Operation Study Interconnection Agreement 4

DISIS – Powerflow Analysis Models built from the Integrated Transmission Planning Models Includes all upgrades with NTC Includes a look over the 10 year planning horizon so no short term outages accounted for SPP Footprint divided into 12 sub-regions (groups) for interconnection study purposes 5

DISIS – Powerflow Analysis Distinct dispatch for each interconnection request in the cluster study for each season All Energy studied to be sunk in SPP footprint 6

DISIS – Powerflow Analysis AC Contingency Analysis Constraints Identified and transmission reinforcements required for –ERIS – overloads with 20% sensitivity factor –NRIS – overloads with 3% sensitivity factor Neither ERIS nor NRIS conveys right to deliver Upgrade Costs shared on a MW impact basis 7

DISIS – Transmission Upgrades If long lead time upgrades with NTC are found to mitigate the constraints identified in the DISIS Study, this is documented in the study as a required upgrade for the Generator This requirement also documented in the Generator Interconnection Agreement (GIA) 8

Facility Studies Performed by the transmission owner +/- 20% estimate of interconnection facilities and network upgrades Short Circuit Analysis – verify circuit breaker duty ratings 9

Limited Operation Impact Study (LOIS) Customer may request to interconnect before the completion of long lead time upgrades identified in the DISIS An additional study (LOIS) is evaluated taking the following into consideration –Customer’s requested COD –Higher-queued generation in service  Neglecting generators that haven’t built –Existing transmission infrastructure 10

Limited Operation Impact Study (LOIS) AC Contingency Analysis Constraints Identified – LOIS may be denied (or temporary cap identified) for –Overloads with 20% sensitivity factor Otherwise Generator can interconnect on ‘as available’ basis until higher queued generator comes into service Conditions documented in GIA 11

Interconnection Agreement Draft GIA presented to Customer after completion of Facility Study Customer given 60 days to negotiate with transmission owner for construction milestones GIA is finalized, executed, and filed at FERC if necessary 12

Questions 13