Report on the Western Cape outages for the period November 2005 to February 2006.

Slides:



Advertisements
Similar presentations
Museum Presentation Intermuseum Conservation Association.
Advertisements

WECC Board of Directors April 21-23, 2004 Seattle, Washington WECC Procedure for Reporting of System Events Disturbance Reports Rod Maslowski OC Vice Chairperson.
Incident took place at OPP substation at 9. 31
1. Four LLs were published in February Transmission Relaying – Undesired Blocking 2.Lack of Separation for Critical Control Power Supply Leads.
Submitted by: Name:Rajendra Kumar Choudhury Branch:Electrical Engg.
Transmission Operator Protection System Misoperations 2014 ERCOT Transmission Protections System Misoperations Data – 138kV and 345kV Combined (Not including.
PER
Accident Investigation for Supervisors
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
De-energization and Lockout
Project 1.4 Operational Strategies and Storage Technologies to Address Barriers for Very High Penetration of DG Units in Intelligent.
EAS Lessons Learned Summary Lessons Learned Published in May 2014.
Crane Operations Objective
System Operator Conference NERC Standards Review for: Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS.
Proposed Design and the Operation of a Disconnecting Device for Small EG Installations Prepared by Hendri Geldenhuys.
Computer Security: Principles and Practice
September 2014 Lesson Learned Summary. September 2014 LLs 2 Three NERC lessons learned (LL) were published in September 2014 LL Redundant Network.
RiversidePublicUtilities.com Arts & Innovation RiversidePublicUtilities.com Challenges and Solutions for Large-Scale PV Integration on RPU’s Distribution.
Responsible CarE® Employee health and Safety Code David Sandidge Director, Responsible Care American Chemistry Council June 2010.
Excavation Instructional Goal: through class participation and discussion, the participant will identify the issues and hazards related to trenching and.
ERCOT Compliance Audits Robert Potts Sr. Reliability Analyst March 23, 2005.
Health and Safety. The Health and Safety at Work Act 1974 An Act to make further provision for securing the health, safety and welfare of persons at work,
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
BLACKOUT POWER OUTAGE By Masih Madayeni Class 3/6 English Presentation.
Adaptive Protection of Distribution Feeders Alexander Apostolov, Benton Vandiver.
Guidance Notes on the Investigation of Marine Incidents
POWER SYSTEM PROTECTION
Frankfurt (Germany), 6-9 June 2011  PV in Spain: Basically Large plants connected to MV or HV Mainly in rural areas (generation exceeds consumption) 3,000.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
February 26, 2013 Board of Directors Meeting 2012 ERCOT Region Reliability Update.
Lesson 9-Information Security Best Practices. Overview Understanding administrative security. Security project plans. Understanding technical security.
Electrical Fire in Terminal Room at Collider-Accelerator Department Relay-Fire Investigation Committee
Programme Performance Criteria. Regulatory Authority Objectives To identify criteria against which the status of each element of the regulatory programme.
© Property of ERCOT /06/20041 Overview of SPS in ERCOT February 5, 2004.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
QUALITY MANAGEMENT STATEMENT
EAS Lessons Learned Summary Lessons Learned Published in June 2014.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Fire Risk In Power Facilities. Introduction Fires in Power Plants or Distribution Facilities have occurred World Wide Many have resulted in Plant Shutdowns.
AUDIT OF INTERNAL CONTROL Day V Sessions I & II. Session Overview Periodical audit of existence of internal control in order to examine its effectiveness.
Alain Schenk, Switzerland, ALPHA 3, Block 3.1, Selected paper Barcelona May ASSESSMENT OF PROTECTION SCHEMES: A KEY FACTOR FOR RELIABILITY.
Introduction to switchgears
NERC Lessons Learned Summary LLs Published in September 2015.
A Presentation On 132 KV GSS BEHROR
CONTENTS: 1.Abstract. 2.Objective. 3.Block diagram. 4.Methodology. 5.Advantages and Disadvantages. 6.Applications. 7.Conclusion.
Checking and Corrective Action EPA Regions 9 & 10 and The Federal Network for Sustainability 2005.
132KV GSS PIPAR CITY JODHPUR
OSHA’s Top 10 Violations of Electrical Safety Policies …. Number 10.
Impacts and Actions Resulting from the August 14, 2003 Blackout Minnesota Power Systems Conference November 2, 2003.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
Role of Account Management at ERCOT 2006 TAC Subcommittee Review ERCOT Board February 21, 2006.
WORKSHOP ON ACCREDITATION OF BODIES CERTIFYING MEDICAL DEVICES INT MARKET TOPIC 9 CH 8 ISO MEASUREMENT, ANALYSIS AND IMPROVEMENT INTERNAL AUDITS.
EFFECTIVE ACCIDENT/INCIDENT INVESTIGATION 15 FEBRUARY 2013 PHILIPPINE ASSOCIATION OF SAFETY ENGINEERS -QATAR- -QATAR- COMMITTEE ON SAFETY EDUCATION 2013.
Organization and Implementation of a National Regulatory Program for the Control of Radiation Sources Program Performance Criteria.
EE 2353 HIGH VOLTAGE ENGINEERING
Failure Modes, Effects and Criticality Analysis
April 7, 2015 Washington, D.C. Area Low-Voltage Event Operations Training Seminar 2016 Erik Johnson System Operations Training (ERCOT)
Computer Security: Principles and Practice First Edition by William Stallings and Lawrie Brown Lecture slides by Lawrie Brown Chapter 17 – IT Security.
Power System Protective Relaying-Part One
STUDY OF ELEMENTS OF A 220/132/33KV SUBSTATION
Chapter 8. Electrical Systems
NERC Lessons Learned Summary
Subteam 1a Competitive Solicitations Framework Working Group Meeting
Leading transport safety
ACCIDENT INVESTIGATION PRESENTATION
Impacts and Actions Resulting from the August 14, 2003 Blackout
Reporting Incidents and Hazards Accident Prevention
Regulatory Oversight of HOF in Finland
Hazard Identification & HAZOP (HAZard and OPerability studies)
Parker domnick hunter. Safety of Electrical and
Presentation transcript:

Report on the Western Cape outages for the period November 2005 to February 2006

2 Event Analysis method Evaluated conformance to planning and operating procedures and/or instructions Evaluated licence conditions and adherence thereto Analyzed report and documents for root and direct causes Analyzed the protection system operations to confirm sequence and cause of events Evaluated maintenance practices and policies for the affected equipment and units (e.g. transmission lines) Evaluated feasibility of the recovery plans Established trends in the events analyzed.

3 Incident of 11 November 2005 Switching operations at Koeberg substations resulted in the tripping of several lines and Koeberg Unit 2 Root cause - Latent defect open circuit on the isolator Findings –Negligence resulting from set procedures and instructions that were not carried out on the day –Inadequate maintenance procedures that cannot detect visible defects –Breach of the licence condition - failure to island of Koeberg Unit 2 (incorrect configuration of the relay) –Incorrect protection system operation, resulting in unnecessary loss of load

4 Incident of 12 November 2006 A piece of wire that was dropped by a crow whilst building its nest resulted in the tripping of the Beta-Hydra line and associated transformer as well as the auxiliary power supply to the Koeberg Unit 2 Root cause – protection malfunctioning due to incorrect configuration of the measurement transformers Findings –Maintenance and/or commissioning procedures are inadequate –Protection co-ordination incorrect

5 Incident of 16 November 2006 Fire under the Droerivier-Muldersvlei 2 line tripped the line causing a voltage depression that tripped Koeberg Unit 2. Direct cause – malfunctioning of the protection system and failure of the tele-protection equipment. Findings –Breach of the licence condition - failure to island of Koeberg Unit 2 (incorrect configuration of the relay) –Implementation of corrective measures inadequate (correction recommended in 2002 but not implemented)

6 Incident of November Controlled shutdown of Koeberg Unit 2 due to out of specification chemical concentration in the safety injection accumulator Direct cause – failure to notify the authorities that the adverse boron concentration went below the chemistry specific target value Findings –Negligence in not notifying the authorities and allowing the acid concentration to go out of specification –Inadequate operating risk assessment processes

7 Incident on February 2006 On the 18 th February the Kendal power station unit 6 tripped causing a severe frequency drop that resulted in the sympathy tripping of the Koeberg Unit 2. On the 19 th February various lines and substations experienced insulation flashovers that resulted in the tripping of numerous transmission lines and substations Direct cause – The Koeberg Unit 2 tripped due to loss of excitation and the insulation failures were induced by excessively dense and highly conductive mist Findings –Inadequate maintenance procedures and policies for transmission lines and substations –Negligence in not coating and/or washing of the insulators in time. –Licence conditions breached with regard to frequency limits

8 Incident of 28 February 2006 The Bacchus-Droerivier line tripped resulting in the isolation of the Western Cape Network. Koeberg Unit 2 successfully islanded and tripped as it was being reconnected to the main network Direct cause – Insulation flashover on the Bacchus-Droerivier line due to heavy mist resulting in the breaking of the insulator and subsequent falling to ground of the line. Findings –The corrective measures on the protection configuration were correctly implemented resulting in the correct islanding of the Koeberg Unit 2 –Co-ordinatio of protection & tele-protection was inadequate –Maintenance procedures & policies inadequate for prevailing conditions –Negligence in not washing the lines in time, given the warnings

9 Future plans & supply security Western Cape Recovery Plan –Additional generation of 1050MW by 2007 for the Western Cape –Demand Side Management initiatives –Koeberg Unit 1 restoration –Demand Market Participation and co-generation –Additional mobile generators where required Findings –Plans and initiatives adequate for the short to medium term

10 Summary of Events & Conclusion Events of 11, 12 & 16 November 2005 mainly resulted from incorrect protection systems operation and configuration causing transgressions of the licence conditions. Events of 19 & 28 February resulted from inadequate transmission lines and substation maintenance practices and policies Events of 23 – 26 November resulted from the negligence and ill discipline of the responsible personnel. The implemented corrective measures are adequate as well as effective and have resulted in the correct operation of the relevant protection systems and hence conformance to breached licence conditions. The measures taken to ensure the security and continuity of supply are adequate and sufficient for the short to medium term.

11 THANK YOU