Contract Management: Claim Avoidance and Handling District Engineer Panel Discussion Lowell Fleenor, P.E. District 2 Engineer, Casper John Eddins, P.E.

Slides:



Advertisements
Similar presentations
Project Cycle Management
Advertisements

Management of Engineers and Technology Project Management Risk Management.
Bob Smith, P.E. Region 1 Benjamin Acimovic, P.E., Region 1
Construction Contracting
Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
ABC Change Orders College of Environmental Design
Presentation by: Tshewang Gyeltshen. The SBD is prepared in line with the PRR 2009 & SBD Large Works General principals of procurement to be applied prescribed.
Tabular Format (TF!/SeeSOR) Lifecycle Approach to Services Procurement
Acquisition Process Step 1 - Requirements Definition
U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration Damage Prevention PHMSA Update Annmarie Robertson PHMSA/Office.
Fachgebiet Projektmanagement 3. Kasseler PM-Symposium 2007 K. Spang: Partnerschaft zwischen AG und AN – die Zukunft des Bauens Chair of Project Management.
Major Incident Process
Ensure Vendor/Engineer of Choice Product Quality
UNDERSTANDING PREQUALIFICATION IN NORTH CAROLINA Ted Edwards, Esq Emperor Boulevard, Suite 225 Durham, North Carolina (P)
4/28/20151 PRESENTED BY NAKABAGO JOHN CONTRACT MANAGEMENT AND ADMINISTRATION IPPU PRESENTATION JOHN NAKABAGO.
Ohio Department of Transportation Dispute Review Boards (DRB) Megan Blackford, P.E., Esq. Construction Claims Administrator.
Presentation for Thesis of Master Degree Done by Ali Abdullah Al Salman CEM – 520 Term Project (Paper Presentation) Assessments of Risk Management Perception&
Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January.
Performance Monitoring All All Contracts require basic monitoring once awarded. The Goal of contract monitoring is to ensure that the contract is satisfactorily.
Construction Industry Development Board development through partnership Construction Procurement documents 2c.
Claim Tracking System. Why was the Claim Tracking System Built? Mandated by the 2002 Legislature Automated Monthly Summary Reports Track and Ensure Construction.
INTRODUCTION TO PUBLIC PROCUREMENT
Large Public Works Projects and the General Contractor/ Construction Manager (GC/CM) Procedure: A New Way to Save Money, Time and Aggravation.
Contract Administration Stacy Sassman Purchasing Agent Iowa State University Cory Harms Associate Director of Purchasing Iowa State University.
Compensation events and claims Presented by Prof. Khem Dallakoti.
TH 2 – Wilton Bridge Replacement Design-Build Project S.P March 5, 2009 Todd Vonasek, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING.
EXAMPLE – Quality Control Plan For Consultants
Job Order Contracting Process Bob Bourg, Claims & Disputes Manager Marlene Anglemyer, Cost Engineer.
CVE 4070 Construction Engineering Test-2 & Review Prof. Ralph V. Locurcio, PE.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Construction Process Public- statutory control of process Private- market control of process Traditional system: Owner Arch/EngrContractor Non-contractual.
District Operations Contracts Office / Final Estimates Jennifer Taylor Steve Lange John Burnette.
Managing The Work Of Paraprofessionals TEACHERS DIRECTING THE WORK OF PARAPROFESSIONALS.
Project Management By: Dr Madhu Fernando Project Procurement Management.
Contractor / Engineer Conference 2010 Dispute Resolution Process Dispute Resolution Process.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
GLOBAL SCHOOL OF PROJECT MANAGEMENT UNIVERSITY FOR INTERNATIONAL COOPERATION Ing. Osvaldo A. Martínez Gómez, MAP, MSc. Essential Topics - Project Management.
Agency Construction Management :CM NOT AT-RISK
Click on Next to continue Next Introductio n Inputs Tools and Techniques Outputs The process of managing procurement relationships, monitoring contract.
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
CHANGES AND WHAT THEY MEAN FOR YOU 2013 EJCDC CONSTRUCTION DOCUMENT SERIES Matthew Skidmore, P.E. NC AWWA-WEA 95 TH ANNUAL CONFERENCE.
Project Scoping. Project Scoping – learning objective Who should complete the Project Initiation Package (PIP)? How is PDP Path used in scoping? Task.
CONTRACTOR’S CLAIM PERSPECTIVE My Disclaimer: This perspective is per Lloyd Wulf! Other contractors will disagree! What is a claim?  Types of claims and.
Resident Engineer Panel Discussion Jack Stone, P.E. District 2 Engineer, Casper Chad Aagard, P.E. District 2 Engineer, Casper Pete Hallsten, P.E. District.
CVE 4070 Construction Engineering Course Review Prof. Ralph V. Locurcio, PE.
Resident Engineer Panel Discussion Jack Stone, P.E. District 2 Engineer, Casper Chad Aagard, P.E. District 2 Engineer, Casper Pete Hallsten, P.E. District.
Elementary School Administration and Management GADS 671 Section 55 and 56.
 Section Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days.
E-61 / CLAIM AVOIDANCE. Construction Claim Avoidance Communicate - Communicate - Communicate We probably spend to much time talking and not enough listening.
DISTRICT CONSTRUCTION ENGINEER PANEL DISCUSSION Contract Management: Claim Avoidance and Handling Keith Compton, P.E. District 5 Construction Engineer.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Middle Fork Project Relicensing Process Plan April 25, 2006.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Introduction to ITSM processes. CONFIDENTIAL Agenda Problem Management  Overview  High Level process Change Management  Overview  High Level process.
CVE 4070 Construction Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
CVE 4070 Construction Engineering HW #6 review Test-2 & Review Prof. Ralph V. Locurcio, PE.
The Contract Management Process Post Award Activities.
The Contract Management Process Contract Formation.
Successfully Managing Customer Expectations Change is expected to occur during the life of any project, but this change must be controlled and managed.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Pre-Construction Services
Ex Ante Review Overview
ARRA Reporting – Upcoming Initiatives
Traditional Steps Leading To A Bid Document
2006 Central Region Post Mortem Review
Chapter 2 – Review ‘construction management’
Presentation transcript:

Contract Management: Claim Avoidance and Handling District Engineer Panel Discussion Lowell Fleenor, P.E. District 2 Engineer, Casper John Eddins, P.E. District 3 Engineer, Rock Springs April 22, 2014

Discussion Topics zGeneral Principles zClaim Avoidance zProject Documentation General z , Contractor-Engineer Notification z , Appeal to District Engineer zSupporting Documentation, zEvaluation of claim, entitlement, impact, dollars zQuestions and Discussion

General Principles zBe proactive zPractice Effective Communication (including listening) zBe honest and forthright zBe open minded zTry to anticipate problems zBe solution oriented and cooperative zBe consistent zHigh expectation of WYDOT during contract administration zDocument

Claim Avoidance zQuality plans and specifications minimize the risk of a contract claim zPlans, summaries and specifications, must clearly describe the work being bid zContradictory notes/statements within the plans and specifications zIncorrect quantities zConstructability zAssignment of Risk, contractor, owner

Project Documentation zSchedules in accordance with zSchedules updated in accordance with zA good schedule may avoid dispute or assist in resolution zAccurate and complete diary entries zWritten work directives zLetters, avoid s zBe proactive when quality of work is poor or does not meet specification. Force the issue and get the work corrected. Document

, Contractor – Engineer Notification Critical that process as set forth in is followed zA claim is a contractor requested change that WYDOT does not agree with zDiffering site conditions zSignificant change in the character of the work zWYDOT requested change order, time? zCommunication to truly understand the request for the change order zDocumentation, detailed request for needed information zMake sure all needed information is provided

Supporting Documentation, zLast chance to get all needed information for the claim zCritical that RE’s response includes documentation used to make decision zCombine contactors submitted information with RE information to make a complete, understandable claim package zInformation needed for a good claim package starts well before the claim begins

, Appeal to District Engineer z Additional information added to the claim package is not allowed after the Resident Engineers decision zCritical that the claim package is complete and understandable zDE decisions are based on the information in the claim package and how well the DCE and RE present the basis for their decision zContract administration correctly performed and specifications enforced correctly

Evaluation of the Claim zStrength of RE decision based on documentation zEntitlement, based on the contract is the contractor due compensation zImpact, to what degree was the contractor operations and schedule effected zDollars, how much is the contractor owed zTo determine or decide the above, it is critical that all pertinent information was included in the claim package and evaluated by the Resident Engineer

Thank You and Questions/Discussion