LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A.

Slides:



Advertisements
Similar presentations
MICE Target Report Video Conference 15/03/07 Chris Booth Sheffield 15 th March 2007.
Advertisements

Final Commissioning Plan and Schedule Cheng-Ju Lin Fermilab Installation Readiness Review 09/27/2004 Outline: - Work to be done during shutdown - Work.
MICE Target Electronics, DAQ and BPS MICE/ISIS Target Meeting 17 th September 2010 P J Smith – University of Sheffield.
BEPCII RF POWER SYSTEM RF group, IHEP Sep ~ April 1.The 1 st transmitter had finished installing,commissioning and SAT (Site Acceptance Test).
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Tom Kubicki.  Booster HLRF System to be upgraded using 1kW Solid State Driver (SSD) Amplifiers.  Used to drive the 200kW Power Amplifier  Eliminates.
Ion source RF system Andy Butterworth BE/RF Mauro Paoluzzi BE/RF 14/11/2013Linac4 ion source review.
A.Blas AB/RF/FB APC meeting 20/4/ Status of the PS TFB Upgrade launched in July 2005 L. Arnaudon, A. Blas, F. Caspers, D. Glenat, R. Louwerse, V.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
PSB DSP Based Low Level RF Operational Experience. April 2015 M.E. Angoletta, A. Blas, A. Butterworth, A. Findlay, S. Hancock, M. Jaussi, J.Molendijk,
SPS re-commissioning with beam K. Cornelis PS-SPS days.
PSB RF bypasses + PSB TFB electronics A. Blas PSB-LIU meeting04 Jun Executive summary: Components for the PSB rf-bypasses will be installed (Joao.
ADT re-commissioning after LS1 A. Butterworth, W. Höfle, F. Killing, G. Kotzian, T. Levens, D. Valuch with many thanks to BE/OP LBOC, ADT re-commissioning.
W. Hofle LIU-SPS Meeting SPS BA2 Damper LS1 Progress and plans reported by W. Hofle LIU-SPS Meeting G. Kotzian T. Levens D. Valuch.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
High Bandwidth damper Input from W.Hölfe Acknowledgement to all collaborators at SLAC, INFN, LBNL and CERNL Presentation of recent MD results (J.Cesaratto):
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
Beam Instruments PSB + Transfer Lines B. Mikulec, J-F. Comblin.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting August 3, 2004.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
Feedback and Beam Control Section (FB) Activities and Highlights 2013 Outlook presented by Wolfgang Hofle FB Section at 2013 RF Group Meeting - December.
Session 7: I-LHC Organization: Chamonix Summary Session7; Oliver Brüning 1 -session organized in collaboration with D. Manglunki and all speakers.
Commissioning of the ALBA IOT-Transmitters Paco Sanchez - 14th ESLS RF - ELETTRA, September Paco Sanchez, RF Group, CELLS (Consortium for.
PASI OsC meeting 12th July 2012
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
Injector RF and Synchrotron RF Present Status, Activities, Plans PP a-GKO_MACS_RfStatus G. Kotzian WP RF - Present Status 1.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Nikolaos TRIKOUPIS, TE-CRG-CI LS1 projects review: feedback on projects and lessons learnt 01/JUN/2015, Indico
Programme for “Target 3” – test of alternative bearing materials (from Jason Tarrant) –Drawing updates by 11 th November –Bearings: Material approval –
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
INJECTORS BLM SYSTEM: PROGRESS REPORT Christos Zamantzas on behalf of the BLM team. MSWG 28/08/2015.
Radio-Frequency (RF) & Schottky diagnostics WP for ELENA Maria Elena Angoletta, BE/RF on behalf of the CERN RF group First ELENA construction meeting CERN,
A new RF system for the PSB. LIU-PSB Working Group Meeting, 10th December 2015 M. Paoluzzi December 10 th Wide working group involved including.
Digital LLRF: achievements and LS1 plans M. E. Angoletta, A. Blas, A. Butterworth, A. Findlay, M. Jaussi, P. Leinonen, T. Levens, J. Molendijk, J. Sanchez.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
Reminder of upcoming milestones For all machines: Nov. 2012:Table of performance parameters Jan. 2013: Baseline activities defined Feb. 2013: Update APT/EVM.
CS section activities Industrial controls Luca Arnaudon David Glenat David Landre Slawomir Totos Ruben Lorenzo-Ortega Digital hardware John Molendijk.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Radio Frequency Andy Butterworth AB/RF Accelerator Controls Renovation WS 3 Dec 2008.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
ELENA installation progress F. Butin / ELENA collaboration.
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
PSB and PS test systems status. M. Haase September 14 th Finemet Review.
Linac4-PSB 160 MeV connection readiness review Tuesday 30 August August 2016 Linac4-PSB 160 MeV connection readiness review 2.
01/09/ KTAG 5/8 sectors equipped DCS system in pogress DAQ commissioning in progress Test pressure scan this week (t.b.c) 01/09/20142.
RF acceleration and transverse damper systems
LIU – SPS Low level RF Updates and schedule G. Hagmann,
Jorge Sánchez-Quesada BE-RF-FB
BI-day 2014, The SEM-grid renovation project Michel Duraffourg
LIU – EVM status and next steps
Injectors BLM system: PS Ring installation at EYETS
EC Activities Status for the LIU
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
The ELENA BPM System. Status and Plans.
Status of the BI Work Package in the LIU-PSB frame
LLRF: M. E. Angoletta, A. Findlay, M. Jaussi, J. Molendijk, J
ThomX – Commissioning Meeting – 25/01/2018
Status of the BI Work Package in the LIU-PSB frame
Presentation transcript:

LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A. Butterworth, A. Findlay, M. Haase, W. Hofle, M. Jaussi, T. Levens, R. Louwerse, J. Molendijk, D. Perrelet, M. Paoluzzi, J. Sanchez Quesada, J. Simonin, S. Zorzetti. 24/10/2013

Introduction The status of the Low Level RF The status of the LL RF Controls The status of the Transverse Feedback The status of the High Level RF Summary

Status of the Low Level RF Development & Production of Hardware: Pre-series production of the Carrier, Rear Transition, VXS Switches, ADC, DAC & DDS boards tested and validated. Tests went well with no problems to report that will hold back series production. Series production underway, all hardware expected to be delivered late Autumn as planned. Hardware also being used for other projects including MedAustron, with Finemet cavity servo loop tests on test bench presently underway. Hardware may be used with beam at MedAustron before end of LS1, offering a good opportunity to gain operational experience. Integration of new HW advancing well now that PSB cabling campaign paused in BOR. As no radial pick-ups were re-cabled, having to rethink how to supply beam control with sigma and delta signals.

Status of the Low Level RF Development of Software & Firmware: Good progress for the 3 Carrier Board system required for the PSB. Development Scripts & Tools previously written now paying dividends. FPGA & DSP code can be loaded remotely. Firmware and software progressing according to plans.

Status of the Low Level RF Controls LL hardware can supply OASIS & “sampler” digital data. Reference functions & soft timings integrated into LL hardware. Integrated functions compatible with standard function editor application. OASIS requirements defined and confirmed with CO. OASIS hardware ordered and installation planned for Autumn Digital & analogue OASIS signals will be available with same time base. OASIS for Finemet prototype also defined and ordered. OASIS integration yet to be done, a few weeks of work. Sampler implementation looks to be reasonably straight forward, with FESA class to be run in a crate outside of the RF LL crates(simple crate may need to be purchased) CO HW order: Crates+CPUs delivery Oct 2013, CTRVs order Oct 2013 & delivery Dec FESA classes for timings done Work underway for LL systems 3 rd Carrier board (Cavity gap returns & drives) Synoptics to control LL system yet to be done. Initial measurements indicate fully compatible with delaying/advancing cycle (<100ms) RF-CS manpower yet to be confirmed for this work.

Status of the Transverse Feedback Existing TFB System Modifications: PLC control of power amplifier power supplies and cooling water installed and ready for testing. The PLC control & water cooling fully compatible with existing & future systems. Existing TFB HW has been moved to make space for future system. Electricity and plumbing complete, system tests started. All 100W power amplifiers need to be checked and repaired where necessary, as several found broken during MD at end of run. ( start Nov 2013, ~4 weeks total) Beam testing with modified TFB estimated 4 days.

Status of the Transverse Feedback New TFB System: New 800W power amplifier prototype under test and on track. Once tests completed (end Oct 2013) 20 units will be prepared for installation April New power amps fully compatible with existing system, hence after testing with beam, will replace old power amps (expected by August 2014). A study to decide upon which HW to base the new TFB system electronics resulted in the decision to update the existing PS 1 Turn Feedback board developed by D.Perrelet. The initial analogue bandwidth is 13MHz to match the existing system, but later beam tests will investigate increasing this to 20-30MHz. The plan remains to have a complete system installed in parallel on all rings for end May The above HW is outside of the ring and will be tested with beam in PPM by switching with existing system on R4. Testing with beam estimated at 2 months, planned to start mid-August After successful beam tests, all 4 rings will be brought into operation by end November Upgrade to 100MHz BW option to be studied late 2014 once new system in operation.

Status of the Transverse Feedback New TFB Head Amplifier: New Head amplifier study underway, prototype being built and tested. This is advancing but delayed by ~ 2 months w.r.t. to planning. Delay will probably not allow prototype HW to be ready for installation before end LS1, but R4 will be equipped to welcome the new amplifier during a suitable technical stop. R4 will be used as the test ring for the new amplifier, and it’ll be designed in such a way to use the same connections/cables as we use presently to the surface equipment. As this will have to be swapped with the existing head amplifier, tests will be carried out once the new TFB system is stable. This is not essential for the new system at this stage.

Status of the Transverse Feedback New TFB System Cables: The existing cables between the machine & surface were recently measured and the required extensions to connect to the new HW ordered. A. Blas is presently investigating if the cables from the TFB surface equipment to the machine need to be changed in LS1.5 or 2. The existing cables are presently believed to be fully compatible with the new HW.

Status of the High Level RF Existing C02, C04 & C16 Systems: Several relay gaps for the C04 & C16 must be replaced after a measurement campaign showed several were broken. A relay gap must be installed on the Ring 4 C02 cavity ahead of the Finemet ® cavity tests. The above is planned, along with the regular cavity maintenance, before the HW cold-check in May 2013.

Status of the High Level RF Finemet ® Prototype Cavity: Despite short delays in the delivery of the vacuum tube, the cavity is 80% ready and is expected to be finished ready for installation December Power amplifiers already delivered and being tested, next 5 delivered by end October to be tested by end November Spare power amplifiers will follow and be ready soon after. Dedicated Digital LL RF: This will be the Ring 0 LL beam control that will be switched with the R4 Digital Low Level. This is included in the New Digital Low Level planning and on track.

Status of the High Level RF Interlocks: These are finished and being installed, so will be ready for PSB HW cold check out. Power Convertors: Installation underway and on track to be finished by end November Cabling: Power cables being replaced for power convertors, on track for delivery end November Initial cable order completed for connections to machine and surface equipment during PSB cabling campaign. A new request for further cables has been approved for the 2 nd phase of the PSB cable campaign with delivery by February 2014.

Status of the High Level RF Cooling: Slight delay in program but remains on track for delivery by end Jan Beam Tests: Position of prototype cavity means it experiences ~200 times the radiation of the existing cavity positions, hence the power amplifiers require a means of compensating this. This has been introduced for the power amplifiers that will be installed for 2014, but has yet to be tested. As a precaution, it will be necessary to remove the power amplifiers after the HW cold check and before the beam is injected, to save the critical components. Before the beam tests start the amplifiers will need to be re-installed during a technical stop, which will take approx. 6 hours including cool down and testing. Due to workload of RF specialists, the earliest possible date for beam tests would be September 2014.

Summary Low Level RF: HW & SW on track for delivery April Start up after LS1 with commissioning of new Digital Beam Control with beam. Big challenge to get system operational, but must be done while all experts are available at start of run. Existing Low Level system remains in parallel in case of major problems. Low Level RF Controls: OASIS & “samplers” work underway, HW ordered or being installed, integration to be done early Synoptics to program/control low level and OASIS+”samplers” essential before commissioning can start. Heavy work load for RF-CS section means waiting for confirmation that manpower will be available.

Summary TFB: Existing system will be available after a few days of re-commissioning. The new TFB system installation is progressing as planned, the HW choices have been made or are towards the end of the prototyping stage and all 4 rings are expected to be equipped with new system by May 2014, ready for beam tests in August. New 800W power amplifiers expected to be operational with existing system by mid-August months beam tests required with new system on R4 only, meaning HW validated for 13MHz BW with increased power by mid-October. All 4 rings to be brought into operation by end November New head amplifier expected to be installed on R4 once new system is stable, ~ December MHz system upgrade will be studied once new HW fully operational, but present planning for delivery stands at April 2016.

Summary High Level RF: Existing system will be ready for cold check after maintenance. Finemet ® Cells and their associated power amplifiers are expected to be ready for installation in December The dedicated Low Level RF is expected to be installed and ready for tests May Power convertors & interlocks ready for testing by end November Initial cabling complete, second request approved for January To protect the power amplifiers, they will be removed after cold check and re-installed before the beam tests. Beam tests will not start before September 2014.

Acknowledgments With thanks to all the project team members for their essential input.