SPHENIX MECHANICAL D. Lynch September 11, 2014. AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.

Slides:



Advertisements
Similar presentations
4/11/20131 PHENIX WEEKLY PLANNING 4/11/2013 Don Lynch.
Advertisements

7/28/03P. Kroon AEROGEL Assembly of Cells into 80-cell Array: –8 cells wide by 10 cells high mm high (Y) by 2077 mm wide (Z) by about 335 mm deep.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 4/20/06 Don Lynch. Safety We have lost a whole week of running because of a violation of procedure and not because of the accident.
6/6/ PHENIX WEEKLY PLANNING 6/6/2013 Don Lynch Note: No PHENIX planning meeting this week due to end of run party. Feel free to discuss safety and.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
5/9/ PHENIX WEEKLY PLANNING 5/9/2013 Don Lynch.
11/7/ PHENIX WEEKLY PLANNING Nov. 7, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 10/05/06 Don Lynch. 10/05/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
12/5/ PHENIX WEEKLY PLANNING Dec. 5, 2013 Don Lynch.
3/14/20131 PHENIX WEEKLY PLANNING 3/14/2013 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
7/31/2014 PHENIX WEEKLY PLANNING July 31, 2014 Don Lynch 1.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
3/6/ PHENIX WEEKLY PLANNING March 6, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
Robert Pak, FVTX Annual Review Nov Mechanical Integration WBS Robert Pak Brookhaven National Laboratory.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
1 PHENIX WEEKLY PLANNING January 21, 2016 Carter Biggs.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
2/14/20131 PHENIX WEEKLY PLANNING 2/14/2013 Don Lynch.
4/24/ PHENIX WEEKLY PLANNING April 24, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 10/20/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
5/16/ PHENIX WEEKLY PLANNING 5/16/2013 Don Lynch.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
4/17/ PHENIX WEEKLY PLANNING April 17, 2014 Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
Robert Pak VTX Meeting Sept. 7, 2004 VTX. Robert Pak VTX Meeting Sept. 7, 2004 PHENIX Central Region From VTX Proposal (dims in mm) HBD is standalone.
PHENIX WEEKLY PLANNING 10/12/06 Don Lynch. 10/12/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
5/8/ PHENIX WEEKLY PLANNING May 8, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
12/20/20121 PHENIX WEEKLY PLANNING 12/20/12 Don Lynch.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
DON LYNCH OCTOBER 28, October 28, 2014 sPHENIX Detector Integration & Assembly Concept.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
SPHENIX MECHANICAL D. Lynch, R. Ruggiero June 12, /12/2014sPHENIX Mechanical Design.
SPHENIX MECHANICAL D. Lynch & R. Ruggiero July 31, /29/2014sPHENIX Mechanical Design.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
DON LYNCH DECEMBER 4, AGENDA December 4, BABAR Magnet Update Outer HCal Structural Analysis (Assembly and Support) sPHENIX Project Management.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
2/27/ PHENIX WEEKLY PLANNING Feb. 27, 2014 Don Lynch.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
12/6/20121 PHENIX WEEKLY PLANNING 12/13/12 Don Lynch.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
PHENIX WEEKLY PLANNING 3/30/06 Don Lynch. This Week MPC air flow started BLM source test HBD transparency monitor hutch work and cable tray 1 st MPC Card.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
QXF magnet integration Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
PHENIX WEEKLY PLANNING 2/16/06 Don Lynch. Prep for Run 6 Completed.
Integration issues at IHEP
Polarized 3He target installation
Presentation transcript:

SPHENIX MECHANICAL D. Lynch September 11, 2014

AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept (new, Anatoli) sPHENIX management, progress and schedule 9/11/2014sPHENIX Mechanical Design 2

9/11/2014sPHENIX Mechanical Design sPHENIX Global Design Concept General Constraints IR dimensions Shield wall existing configuration Existing tracks MuID steel (assume all will remain) Cooling Water HVAC Power Access & Work platforms Cryo Supply Electronics Support Vacuum/beampipe 3

9/11/2014sPHENIX Mechanical Design sPHENIX Global Design Concept: Key dimensional constraints (Updated) 4

9/11/2014sPHENIX Mechanical Design sPHENIX Global Design Concept: Key dimensional constraints 5

9/11/2014sPHENIX Mechanical Design sPHENIX Global Design Concept SPHENIX Overall Detector Envelope sPHENIX Detector Individual Design Envelopes Magnet HCal Outer HCal Inner EMCal Tracking (VTX) Future Upgrades Support Structure Envelope IR Services Envelope 6

9/4/20147 EMCal Magnet Overall Detector Detector Support Structure

9/11/2014sPHENIX Mechanical Design sPHENIX Global Design Concept: Detector Structural Support External and Internal Support Structures EC ?, WC ?, CP: ¼, ½, ¼ Outer HCAL ?? CP lower supports ¼ Outer HCAL lower and Magnet HCal Inner supported by HCal Outer EMCal supported by HCal Inner Tracking (VTX) supported by Load transfer from CP to HCal Outer/Upper Bridge Platform above HCal Outer Upper supported from CP lower 8

9/11/2014sPHENIX Mechanical Design Internal Support Concept 9

9/11/2014sPHENIX Mechanical Design 10

9/11/2014sPHENIX Mechanical Design Internal Support Concept 11

9/11/2014sPHENIX Mechanical Design 12

9/11/2014sPHENIX Mechanical Design 13

9/11/2014sPHENIX Mechanical Design Internal Support Concept: Tracking Tracking support concept is not yet illustrated. 2 – 4 light rails to support 2 “clamshell” half detectors. Detectors will separate transversely from tight around beampipe then each ½ will be extracted longitudinally. 14

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. COMPLETE ASSEMLY AND INSTALLATION SCENE 15BNL, A. Gordeev, Long I-beam Inner H-cal assembly area Short I-beam Inner H-cal Assembly MAGNET H-cal I-beam supports Modules Installation

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. Assembly Cage Assembly cage 16BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. Assembly Cage Assembly Cage 2 Flanges with Outer R = 1400mm; Inner R = 1135mm: Separated by 3850mm Connected together by 16 removable rods. 17BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. Assembly Cage + I-beam 18BNL, A. Gordeev, COMMERCIAL STEEL I – beam #21 USED FOR ASSEMBLY SUPPORT

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. I-beam position inside of assembly cage 19BNL, A. Gordeev, R = 1400mm R = 1135 mm

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. Transportation cart 20BNL, A. Gordeev, GAP for LINEAR ROLLER SYSTEM I-beam ROLLERS for ASSEMBLY CAGE ROTATION

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. CAGE, Transportation cart and support beam 21BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. Transportation cart. MODULE INSTALLATION PROCEDURE 22BNL, A. Gordeev, ROTATE CAGE FOR RIGHT POSITION Modules ALWAYS loaded From top. REMOVE CAGE TMPORARY ROD, THEN NEEDED

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. Transportation cart. MODULE INSTALLATION PROCEDURE 23BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. Transportation cart. MODULE INSTALLATION PROCEDURE 24BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. COMPLETE ASSEMLY AND INSTALLATION SCHEME 25BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. CASE WITH EM-cal INSTALLATION Inner H-cal Assembly I-beam supports Short I-beam MAGNET Inner H-cal assembly area H-cal Long I-beam 26BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. ISO View CASE WITH EM-cal INSTALLATION BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. SUPPORT BEAM STRUCTURAL ANALYSES BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. SUPPORT BEAM STRUCTURAL ANALYSES. SETTING 29BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. SUPPORT BEAM STRUCTURAL ANALYSES. DEFORMATION 30BNL, A. Gordeev,

sPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. SUPPORT BEAM STRUCTURAL ANALYSES. STRESS 31BNL, A. Gordeev,

xPHENIX INNER H-cal ASSEMBLY AND INSTALLATION PROPOSAL. Tooling. SUPPORT BEAM STRUCTURAL ANALYSES. STRESS 32BNL, A. Gordeev,

The west carriage assembled at 1008 with platforms for racks Global assembly Plan

West carriage moved into IR NOTE: The west carriage needs to be moved 5ft to the North after it is moved to the West wall. It is desirable to make this move easier than its current process. Global assembly Plan

¼ of Outer HCAL moved into 1008 AH NOTE: The 4 modules shown are not the current design, they are being used for illustration purposes only Global assembly Plan

Central Pedestal assembled in 1008 AH Global assembly Plan

¼ of Outer HCAL assembled onto CP Global assembly Plan

sPHENIX magnet mounted to Central Pedestal Global assembly Plan

Inner HCAL modules transported to 1008 AH Global assembly Plan

Inner HCAL modules mounted and being installed NOTE: Installation fixture is conceptual at present time Global assembly Plan

Inner HCAL Installed Global assembly Plan

Outer HCAL support structure installed NOTE: Support structure is conceptual at this time Global assembly Plan

Central Pedestal moved to IR

Outer HCAL modules for WC and CP moved to 1008

Outer HCAL modules for WC moved into IR NOTE: North MUID has been removed for visual purposes CP has been moved North to make room for HCAL modules Global assembly Plan

HCAL modules installed onto WC Global assembly Plan

HCAL modules moved into IR for CP Global assembly Plan

HCAL modules installed onto CP Global assembly Plan

Platform installed on CP Global assembly Plan

Racks and cable installed and routed for Inner and Outer HCAL NOTE: The number of racks on the CP does not necessarily represent the number of racks we will have Global assembly Plan

EMCAL modules brought to 1008 AH Global assembly Plan

EMCAL modules brought into IR for installation NOTE: EMCAL is being shown as individual modules that will slide inside inner HCAL using a rail system (not shown) Global assembly Plan

EMCAL installed onto CP Global assembly Plan

The East carriage assembled in 1008 AH with platforms for racks Global assembly Plan

HCAL brought to 1008 AH Global assembly Plan

HCAL installed onto EC Global assembly Plan

Racks and cable routed on EC NOTE: The number of racks on the EC does not necessarily represent the number of racks we will have Global assembly Plan

EC moved into IR Global assembly Plan

9/11/2014sPHENIX Mechanical Design 59 sPHENIX Management & Progress Magnet – revised shipping fixtures in Central Shops WBS Tasks for subsystem Managers – sample (HCal) for input info by next week Subsystem areas: Management Decommissioning Magnet Tracking (Inner & Outer) EMCal HCal (Inner & Outer) Calorimeter Electronics DAQ & Trigger Infrastructure Installation & Integration WBS/Task #WBS Item/Task Duration (Days)Materials needed & Costs Scientist (m/d) Engineer (m/d) Designer (m/d) Technician (m/d) BNL Trades (m/d)Task DescriptionNotes (caveates, Potential Problems), Etc 1.06HCAL Schedule starts from 6/1/14 Ready for 1st Run 12/31/ Inner HCAL Inner HCal Design 1SubSystem Design Includes Assembly, sub-assembly, outline, cable routing drawings, and mechanical interface drawings 2Detail -SS Plates Includes detail drawings of inner plates outer

9/11/2014sPHENIX Mechanical Design 60 Global Schedule to be derived from WBS Task Info

sPHENIX schedule 9/11/2014sPHENIX Mechanical Design 61