MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.

Slides:



Advertisements
Similar presentations
EuCARD-HFM ESAC review of the high field dipole design, 20/01/2011, Maria Durante, 1/40 EuCARD-HFM ESAC Review of the high field dipole design Fabrication.
Advertisements

COIL & ASSEMBLY READINESS REVIEW, SEPT 2013 D. Smekens.
S. Caspi, LBNL HQS Progress Report High Field Nb 3 Sn Quadrupole Magnet Shlomo Caspi LBNL Collaboration Meeting – CM11 FNAL October 27-28, 2008.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
LARP QXF 150mm Structure Mike Anerella / John Cozzolino / Jesse Schmalzle November 15, nd Joint HiLumi LHC-LARP Annual Meeting.
MQXFS Assembly Procedure J.C Perez 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014 KEK, Tsukuba N. Bourcey, D. Cheng, B. Favrat, H. Felice,
SQXF Shell & Yoke Assembly Procedure
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
H. Felice - P. Ferracin – D. Cheng 09/19/2013 Update on structure CAD model.
H. Felice - P. Ferracin – D. Cheng 09/11/2013 Update on structure CAD model.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
Design Features: still to be determined and open questions P. Ferracin 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014 KEK, Tsukuba.
MQXF length P. Ferracin Video-meeting Structure WG September 18th, 2014.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
1m 3 SDHCAL Mechanic Structure M.C Fouz 8/10/2010 The 1m 3 prototype Mechanical Structure is financed by: Spanish HEP National Program by the project FPA
ELENA Support system 6/11/2014 Antti Kolehmainen on behalf of WP Support system
LARP Prototype Assembly Steps Towards Q1 and Q3 Production Dan Cheng MQXF Design Review December 10-12, 2014 CERN H. Felice, R. Hafalia, D. Horler, T.
LARP Prototype Assembly Steps Towards Q1 and Q3 Production Dan Cheng MQXF Design Review December 10-12, 2014 CERN.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
10/28/2015Pierre Moyret1 Production of SQXF Magnet Components: Return on experience P.MOYRET EN-MME-FS.
11 T Dipole Status at FNAL Fred Nobrega January 21, 2014.
Helene Felice, Dan Cheng Support structure modifications Update on discussion at CERN.
MQXF support structure An extension of LARP experience Helene Felice MQXF Design Review December 10 th to 12 th, 2014 CERN.
MQXFS Assembly Procedure J.C Perez N. Bourcey, B. Favrat, P. Ferracin, Ph. Grosclaude, M. Juchno, L. Lambert, P. Moyret, J. Parrilla Leal, N. Peray, T.
Hybrid Structure with Cooling John Cozzolino LARP Collaboration Meeting Port Jefferson, NY November 4-6, 2009.
HIGH RAMP RATE SUPERCONDUCTING MAGNETS AT BNL Peter Wanderer BNL Archamps Workshop, March 2003.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
LARP Collaboration Meeting Racetrack Coil Fabrication
MQXF Workshop on Structure, Alignment, and Electrical QA Feb 2-4, 2016 Dan Cheng J. De Ponte, H. Felice, S. Kincaid, T. Lipton, S. Myers, A. Pekadis, M.
Dan Cheng, Helene Felice 4/8/2015 MQXFS-D Build-up LBNL “Lessons Learned”
1 MQXF Workshop on Structure, Alignment, and Electrical QA Feb 2-4, 2016 Options for modifications to parts and procedures Options for modifications to.
MQXF Workshop on Structure, Alignment, and Electrical QA Feb 2-4, 2016 Dan Cheng J. DiMarco, C. Hernikl, D. Humphries, S. Myers, X. Wang MQXFA Magnet Fiducialization.
Overview short model design and structures P. Ferracin on behalf of the MQXF collaboration MQXF Workshop on Structure, Alignment, and Electrical QA CERN.
MQXFB Plan for mechanical alignment measurements J.C Perez On behalf of MQXF collaboration team Special thanks to Jose Ferradas for his contribution MQXF.
DESIGN STUDIES IR Magnet Design P. Wanderer LARP Collaboration Meeting April 27, 2006.
Cold Mass and Assembly Tooling Design, Procurement Status and Assembly Plan Igor Novitski Fermilab 15 T Dipole Design Review April 2016 April 28-29,
MQXFB Prototype structure and plans at CERN J.C Perez On behalf on MQXF collaboration team Joint HiLumi-LARP Meeting & 24 th LARP Collaboration Meeting.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
CONCEPTUAL DESIGN OF D2 MECHANICAL STRUCTURE (DOUBLE COLLARING OPTION) S. Farinon, P. Fabbricatore (INFN-Sezione di Genova) Sept. 24 th 2015.
QXF Reaction / Impregnation Fixtures J. Schmalzle 4/9/13.
B [OT - Mechanics & Cooling] Stefan Gruenendahl February 2, 2016 S.Grünendahl, 2016 February 2 Director's Review -- OT: Mechanics &
Cold mass procurement, status and plan, QA-QC H. Prin With contribution from S. Becle, O. Housiaux, R. Principe, J.-L. Rudeiros Fernandez, F. Savary 3.
MQXFSD3 laminated structure J.C Perez N. Bourcey, B. Favrat, P. Ferracin, P. Moyret.
Dan Cheng 8/27/2015 MQXFS1 Observations and Feedback from the Assembly Processes, Part II.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
3 rd ESAC Review, 27 th February to 1 st March 2013, CEA Saclay Fresca2 Dipole Structure Assembly J.C Perez on behalf of Fresca2 collaboration team.
QXF magnet integration Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
QXF Coil Fabrication & Tooling Reaction / Impregnation
MQXC Nb-Ti 120mm 120T/m 2m models
TQS Structure Design and Modeling
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
ERMC/RMM activities May 2017
J.C. Perez on behalf of SMC collaboration team J.C. Perez
Mechanical Modelling of the PSI CD1 Dipole
FRESCA2 Update on the dipole design and new calculations
Helene Felice 02/15/2013 HiLumi Meeting HQ Program
Discussion session on day 1
Glyn Kirby Magnet AssemblyTechniques.
the MDP High Field Dipole Demonstrator
Analytical Cost Model (16 T dipole)
MQXF updates P. Ferracin October 9th, 2014.
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
Bunker Wall Design Wall ESS
Helene Felice 02/15/2013 HiLumi Meeting HQ Program
SNS PPU Cryomodule Space Frame
Presentation transcript:

MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA CERN 2-4 February 2016

OUTLINE  MQXFB magnet design  MQXFB assembly plans and tooling at CERN  Conclusions February 2-4th 2016 J.C. Perez MQXF Workshop at CERN3 Special thanks to Bruno Favrat for his contribution to this presentation !

MQXFB magnet design February 2-4th 2016 J.C. Perez MQXF Workshop at CERN4 ≈7.5 meters long coils 50 mm thick aluminum collars Coil angular positioning w.r.t collars using radiation resistant G10 alignment keys Pads assembly : combining 5.8 mm and 28 mm pieces ≈ 3.8 m long masters & bladders Jokes assembly : using 5.8 mm and 46 mm thick pieces 10 long and 2 short aluminum shells ≈ 8.5 long rods for longitudinal loading ≈ 10 meters long ½ SS shells to be welded

¼ Yoke packs preparation February 2-4th 2016 J.C. Perez MQXF Workshop at CERN5 5 modules of yoke + shells per magnet pre-assembled using bladders and yoke keys ¼ yokes assembly operation will be performed on horizontal position using temporary tie-rods 2 & 3 shells configuration to be assembled 50 mm thick plates are required at shells junctions to bolt the supporting blocks for backing strip welding (strips tack- welded to the blocks) 3 Shells configuration 1 short & 2 long 1708 mm 2 Shells configuration 1368 mm

Yoke and Shell assembly February 2-4th 2016 J.C. Perez MQXF Workshop at CERN6 Assembly performed in vertical position and then pivoted Bolting yokes against the shell throw shell windows may be considered as an alternative solution for bladders operation (see Nicola’s presentation) Smaller yoke-keys will be used for safety Temporary rods will be removed after yoke-keys insertion Assembly procedure and comparative geometrical measurements to be validated during MQXFSD3 mechanical structure assembly (Feb-2016)

Yoke and Shell modules assembly February 2-4th 2016 J.C. Perez MQXF Workshop at CERN7 Each individual yoke pack will be measured during MQXFSD3 and prototypes assembly phase 2 mm gap to be guaranteed in between 2 adjacent yoke/shell sub-assembly (yoke longer by 1 mm at each extremity by design) Overall magnet length to be adapted? Can be done by machining the 2 SS end-plates

Yoke & Shell modules assembly table February 2-4th 2016 J.C. Perez MQXF Workshop at CERN8 The horizontal alignment plane will be defined by the top surface of the pieces holding the 2 vertical ¼ yokes at each shell extremity 6 alignment fixtures equipped with cylindrical pins will ensure the lateral position of the yoke/shell sub-assemblies and guarantee the full assembly straightness over ≈7.5 m Horizontal reference plane Transversal alignment

Yoke & Shell modules assembly(1/4) February 2-4th 2016 J.C. Perez MQXF Workshop at CERN9 3 shells module will be placed on its support feet and blocked in longitudinal direction The next module will be placed on top of its corresponding feet with a distance between 2 adjacent shells of ≈10mm

Yoke & Shell modules assembly (2/4) February 2-4th 2016 J.C. Perez MQXF Workshop at CERN10 10 mm Contact See next slide

Yoke & Shell modules (3/4) February 2-4th 2016 J.C. Perez MQXF Workshop at CERN11 Hydraulic cylinders (if required) and intermediate tie-rods will be used to pull and temporary clamp 2 modules together The contact between 2 sub-assemblies will be located on the faces of the thick extremity lamination plates Temporary tie-rods will be removed after compressing the modules No alignment pins will be used in between 2 modules (final magnet alignment provided by bladders operation when loading the coil- pack: to be confirmed during first prototype assembly)

Yoke & Shell modules (4/4) February 2-4th 2016 J.C. Perez MQXF Workshop at CERN12 The same sequence will be repeated to assemble the 4 remaining modules using tie-rods adapted to the required length

Load pads and aluminum collars assembly February 2-4th 2016 J.C. Perez MQXF Workshop at CERN13 Stainless steel tube tack welded for thin laminations assembly The central part of load-pad packs will be assembled on top of a reference table using a SS tube (tack welded at the extremities) 50 mm SS pieces will be then assembled using 50 mm bushes Stainless steel rods will be used for longitudinal compression The aluminum collars will be assembled on top of the full length ¼ pad assembly using bushes Top part and pad indentation will be used as assembly reference plans for ¼ collar packs Stainless steel rods will compress the collar assembly

7.5 meters Coils assembly February 2-4th 2016 J.C. Perez MQXF Workshop at CERN14 4coils ≈7.5 meters long to be assembled (How to support them over the full length?)

Coil-pack assembly (1/2) February 2-4th 2016 J.C. Perez MQXF Workshop at CERN15 Assembly method as for MQXFS Upper ¼ pad & collars preparation

Coil-pack assembly (2/2) February 2-4th 2016 J.C. Perez MQXF Workshop at CERN16 Aluminum collars will not be bolted Bolting of the load-pads for coil pack assembly will be performed using screws spaced by ≈350 mm The new assembly procedure has been tested at CERN (using MQXFSD0 first structure: thick laminations ) during MQXFSD2 assembly (3 shells configuration). The same procedure will be applied on MQXFD3 mechanical structure assembly (new laminated structure using a 3 aluminum shell configuration: see Nicola’s talk)

Masters assembly February 2-4th 2016 J.C. Perez MQXF Workshop at CERN17 The masters will be bolted to the pivoting supports for assembly operation Temporary removable clamps will be placed around the coil-pack and masters to guarantee their correct positioning during insertion operation

Coil-pack insertion February 2-4th 2016 J.C. Perez MQXF Workshop at CERN18 The same insertion table concept used for MQXFS assembly will be scaled-up for MQXFB coil-pack insertion

Coil-pack insertion February 2-4th 2016 J.C. Perez MQXF Workshop at CERN19

Longitudinal compression and connection box February 2-4th 2016 J.C. Perez MQXF Workshop at CERN20 The connection box will be mounted after shell welding operation End-plate assembly and axial loading using the system validated on MQXFS

Conclusions MQXFS assembly procedure has been defined and is being tested during MQXFS model program The assembly procedure will be extrapolated for MQXFB construction and validated on the first prototype to be built at CERN from February 2016 on Most of the existing tooling can be scaled-up from models to 8 m long magnet Structure components detailed design to be completed by summer 2016 First MQXFB prototype (mirror configuration) assembly scheduled for Q Handling and assembly tooling to be designed and manufactured No show-stopper identified so far February 2-4th 2016 J.C. Perez MQXF Workshop at CERN21

February 2-4th 2016 J.C. Perez MQXF Workshop at CERN22 The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement Thank you for your attention