1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Installation Gregory Fries, Project Engineer 8 th ASAC meeting for NSLS-II Project May 10-11, 2011.

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Transition to Operations Erik D. Johnson, Deputy ALD for Programs Science Advisory Committee April 4, 2011.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beneficial Occupancy Readiness Evaluation Plan Update Brian Heneveld, P.E., CIH NSLS-II BORE Coordinator Conventional.
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Shielding Workshop S. Buda Personnel Protective Systems March 27, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring - Conventional Facilities Interfaces Erik Johnson, Accelerator Systems Interface Manager Accelerator Systems.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
1 BROOKHAVEN SCIENCE ASSOCIATES Commissioning Plans F. Willeke 9 th ASAC Meeting for NSLS-II Project February 1-2, 2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES Systems for Accelerator Operations Safety Erik Johnson ASD Deputy Director and Interface Manager NSLS-II ASAC Meeting October.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES Booster and Transport Lines F. Willeke for T. Shaftan 8 th ASAC meeting for NSLS-II Project May 10-11, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Role in NSLS-II Operations Marty Fallier Conventional Facilities Advisory Committee Review October 5-6, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting February 8-9, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Installation Erik Johnson ASD Deputy Director and Interface Manager NSLS-II CFAC Meeting November 9-10, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Status Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Accelerator.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Installation & Integrated Testing Status & Plans Gregory Fries, ASD Project Engineer 9 th ASAC meeting for NSLS-II Project.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
1 BROOKHAVEN SCIENCE ASSOCIATES ASAC Meeting NSLS-II Project July , 2008 G. Ganetis Power Supplies & Electrical Utilities ASAC Meeting National Synchrotron.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
1 BROOKHAVEN SCIENCE ASSOCIATES EFAC Review Conventional Facilities Update Marty Fallier Director for Conventional Facilities May 10, 2007.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting March 29-30, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Injector Status Timur Shaftan, Injector Group Leader 9 th ASAC meeting for NSLS-II Project February 1-2, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
MEF - Machines & Experimental Facilities March 2013 Project meeting Activities in Linac4 tunnel and building in 2013 March 2013 Project meeting 14/03/2013J.Coupard1.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Overview Scope & Schedule Marty Fallier Director for Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Getting the NSLS-II Accelerator ‘on-line’ Erik Johnson, Steve Hoey, Ferdinand Willeke NSLS-II PAC Meeting December 10-11,
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
Installation plans for RFQ and Superconducting linac Dave McGinnis Chief Engineer Eugene Tanke Systems Engineer March 20,
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Ferdinand Willeke Director, NSLS-II Accelerator Systems NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Accelerator Installation Plan: Graphical representation E. Sargsyan & L. Lari DRAFT - March March 2016.
ELENA installation progress F. Butin / ELENA collaboration.
Operation Status of the RF Systems and Taiwan Photon Source
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Report Technical Director Storage-Ring-Installation Completed
CBETA Technical Review
Installation Global System
IT-4189 Supply and installation of a cryogenic distribution system
Renovation of the 45-year old PS magnets
Advanced Research Electron Accelerator Laboratory
CF Scope, Management & Organization
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Installation Gregory Fries, Project Engineer 8 th ASAC meeting for NSLS-II Project May 10-11, 2011

2 BROOKHAVEN SCIENCE ASSOCIATES Outline Phasing of Installation Work Planning Site Access & Layout Rigging & Transport Storage Ring Installation Progress Schedule Injector Installation Challenges Summary

3 BROOKHAVEN SCIENCE ASSOCIATES Key Aspects of Production and Installation Accelerator Production – We procure injector sub-systems (Linac, Booster Ring) We build (integrate) Transfer Lines, B-RF and SR components Accelerator Installation – Storage Ring BNL Storage Ring RF BNL w/ vendor installing transmitter Booster RF BNL Transport Lines BNL Linac Vendor w/ BNL oversight Booster Ring Vendor using BNL technicians for all hands–on work w/ Vendor oversight

4 BROOKHAVEN SCIENCE ASSOCIATES Phasing of Construction and Installation Temp walls constructed separating BOD segments Installation and testing within these segments Components will be staged on experimental floor 1 2 B RF L Beneficial Occupancy AreaOriginal Date Actual/New Date Pentant 1 1-Feb-1114-Mar-11 RF Building 23-Mar-1120-May-11 Injector Building 18-May-1126-Jul-11 Pentant 2 2-Jun-1123-Jun-11 Pentant 3 27-Sep-11 Pentant 4 28-Nov-11 Pentant 5 9-Feb-122-Feb-12

5 BROOKHAVEN SCIENCE ASSOCIATES Work Planning Installation schedule complete, including resource loading Schedule is reviewed, updated & disseminated weekly Emergency plan & operations plan in place Site specific training for phase 1 complete One work permit will be created for each phase on installation Detailed work plans will be attached to each work permit Installation WCC for each ASD group identified Daily morning meeting on site with WCCs taking place Weekly installation meetings taking place MonthPeople Mar ’1135 Apr ‘11 – May ‘1150 June ‘11 – Sep ‘1175 Oct ‘11 – May ’12100 June ’12 – Nov ‘1275 Dec ‘12 – March ‘1350 ASD Install Labor Profile

6 BROOKHAVEN SCIENCE ASSOCIATES Site Access Sketch Access via Brookhaven Ave Dedicated parking lot “Safe zone” identified via fence to provide separation from construction site Enter at column 102 Hard hats, safety shoes & safety glasses required Signage in place No personal vehicles on site Storage Containers Loading Dock

7 BROOKHAVEN SCIENCE ASSOCIATES Experimental Floor Layout During P1 Install (8) 20’x30’ Cages for technician space on experimental floor. Will move from pentant to pentant through installation process.

8 BROOKHAVEN SCIENCE ASSOCIATES Pictures of Experimental Floor

9 BROOKHAVEN SCIENCE ASSOCIATES Rigging, Forklifts & Vehicles (2) 3-person rigging teams assigned full- time to project ASD Forklift 10,000 lbs. capacity 208” max lift to reach mezzanine from experimental floor Rigging services to provide add’l forklifts Vehicles For transport of small & fragile components 3 vehicles assigned in Feb add’l vehicles in 2-3 months

10 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Systems Installation Per Pentant Mech. & Elec. Utilities Personnel Protection System Magnet/Girder Assemblies Vacuum System Power Supplies Beam Instrumentation Controls Where Applicable RF Systems Beam Line FEs, DWs, IDs Injection Straight

11 BROOKHAVEN SCIENCE ASSOCIATES P1 Electrical & Mechanical Utilities and PPS Electrical Utilities Cable tray installation complete (3) Cells of equipment racks in place UPSs in place Starting to pull cables in mid-May Mechanical Utilities DI water piping complete in mid-May Pump skids installed in July Magnet/Girder floor plates in process PPS P1 racks installed Human interlock interfaces installed

12 BROOKHAVEN SCIENCE ASSOCIATES Magnet/Girder Floor Plate Installation Installation of magnet/girder floor plate work has begun (2 cells complete) Process includes: Survey Drilling Scarifying Plate Installation Grouting Preparation for the installation of the first magnet/girder at end-May 2011

13 BROOKHAVEN SCIENCE ASSOCIATES Magnet/Girder Transport Magnet/Girders will be transported to tunnel via experimental floor Will be transported to site and unloaded via forklift Will be pulled across experimental floor using standard dollies Will use short & tall dolly system to transition from experimental floor to tunnel (8” difference in height) Moved to final location using air casters

14 BROOKHAVEN SCIENCE ASSOCIATES Short & Tall Dolly System Courtesy of Lewis Doom Experimental Floor Tunnel

15 BROOKHAVEN SCIENCE ASSOCIATES High-Level Installation Schedule Does not include subsystem testing, integrated testing and commissioning Hatched section of SR RF schedule indicates 2 nd RF Cavity Taken from P6 on May 3, 2011 Accelerator Installation JFMAMJJASONDJFMAMJJASONDJFMAM Phase 1 - Pentant 1 Current Baseline Phase 2 - SR RF Phase 3 - Injector Phase 4 - Pentant 2 Phase 5 - Pentant 3 Phase 6 - Pentant 4 Phase 7 - Pentant 5

16 BROOKHAVEN SCIENCE ASSOCIATES SR RF Installation RF Cavities moving toward critical path 2 nd Cavity may be installed during ID installation RF Transmitter w/ klystron installed by vendor Remaining RF systems installed by BNL Taken from P6 on May 3, 2011 SR RF Installation JFMAMJJASONDJFMAMJJASONDJFMA Mech & Elect Utilities Cabling, Wiring, Piping RF Transmitters Low Level RF Liquid Nitrogen System Refrigeration System RF Cavities

17 BROOKHAVEN SCIENCE ASSOCIATES Injector Installation Phases Mechanical & Electrical Utilities Booster RF LtB Transport Line Part 1 Through wall, up to vac valve in booster vault, needed to commission linac Linac Booster LtB Transport Line Part 2 TL complete, need to commission booster BtS Transport line Part 1 Up to beam dump, needed to commission booster

18 BROOKHAVEN SCIENCE ASSOCIATES Injector Installation Phases Layout BtS TL Part 1 Booster LtB TL Part 2 Linac LtB TL Part 1 Phase Separation Booster RF Phase Separation (end of injector install)

19 BROOKHAVEN SCIENCE ASSOCIATES Linac Installation Vendor responsible for installation Installation plan & HASP being created Linac to be delivered Sep BNL will run AC power to their racks to expedite BNL will install shielding BNL will need to complete LtB TL Part 1 for commissioning Vendor will work with BNL on ARR Ready for commissioning Dec Linac commissioning will overlap with booster & SR installation

20 BROOKHAVEN SCIENCE ASSOCIATES Booster Installation Vendor responsible for installation using BNL technicians for all hands–on work Technicians will perform tasks assigned by vendor BNL will supervise technicians Technician labor requirements & install plan being finalized Booster to be delivered Feb Magnet/Girders will arrive assembled BNL will need to complete BR RF, LtB TL and BtS TL Part 1 for commissioning Vendor will work with BNL on ARR Ready for commissioning Dec. 2012

21 BROOKHAVEN SCIENCE ASSOCIATES Injector Installation Schedule Taken from P6 on May 3, 2011 Installation of Linac is approx. 3 months early Hatched section of LtB TL Part 1 indicates diagnostics that are not needed for Linac commissioning BtS Part 2 is not needed for Booster commissioning Injector Installation JFMAMJJASONDJFMAMJJASOND Utilities - Mech & Elec Phase 1 - Booster RF Phase 2 - LtB TL Part 1 Phase 3 - Linac Phase 4 - Booster Phase 5 - LtB TL Part 2 ` Phase 6 - BtS Part 1 Phase 7 - BtS Part 2

22 BROOKHAVEN SCIENCE ASSOCIATES Challenges Coordinating multiple activities & teams during installation Beneficial occupancy dates close to pushing installation schedule Maintaining component delivery schedules (i.e. magnets, RF cavity) Adapting to delivery delays Cleanroom in 902 for precision alignment of magnets may become bottleneck Tight coordination with XFD installation needed to avoid conflicts with required flexibility of ASD installation schedule (hand-over delays)

23 BROOKHAVEN SCIENCE ASSOCIATES Summary Accelerator installation fully underway in pentant 1 Currently approx. 6 weeks behind schedule in pentant 1 Planning in process for installation in RF & Injector buildings Focus on flexibility in installation schedule based on availability of building and components Rigging, storage & logistics plans in place Required installation staff in place Good communication established with CFD & XFD Conclusion: Installation progressing very well

24 BROOKHAVEN SCIENCE ASSOCIATES Acknowledgements A. Boerner, M. Bromfield, A. Byon, S. Buda, R. Chmiel, L. Dalesio, L. Doom, O. Dyling, M. Fallier, R. Fliller, G. Ganetis, E. Golnar, D. Hatton, H. Hseuh, S. Hoey, E. Johnson, F. Lincoln, T. Mendez, J. O’Malley, S. Ozaki, P. Ribaudo, J. Rose, S. Sawch, T. Shaftan, W. Scheuerer, S. Sharma, R. Sikora, O. Singh, J. Skaritka, T. Tanabe, F. Willeke, P. Zoccoli & many others