Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.

Slides:



Advertisements
Similar presentations
ISTISNA’.
Advertisements

Contracts – important issues
CONTRACT TERMS AND CONDITIONS--COMMERCIAL ITEMS ( ) (FEB 2007)
COMMENCEMENT OF ARBITRATION PROFESSOR JOSEPH MBADUGHA.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
Arbitration in Poland Practical issues Monika Hartung Legal Adviser, Partner Warsaw 16 June 2011.
Dr. Lic. Herfried Wöss, LL.M. (Exeter), MCIArb. © The relationship between Arbitration and the Dispute Adjudication Board under the FIDIC Silver Book (EPCT)
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
17 th Contracting Squadron I n t e g r i t y - S e r v i c e - E x c e l l e n c e LETTER CONTRACTS 2k7 01 Dec 05 Train and deploy the world’s foremost.
Blueprint of a Bid Protest. …well, more of a thumbnail of a bid protest.
 Mediation is a dispute resolution process in which, as an alternative to judicial or administrative decision-making process, the parties are assisted.
WIPO ARBITRATION AND MEDIATION CENTER 1 Ignacio de Castro WIPO Arbitration and Mediation Center February, 2008 Arbitration of Intellectual.
Learn. Perform. Succeed. Protest, Claims, Disputes and Appeals Chapter 7.
Time for a new standard - AS General Conditions of Contract
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
The Islamic University of Gaza Engineering Faculty
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
Workers Compensation Commission Sian Leathem Registrar 29 September 2008.
Performance of Contractor Agreements: Practical Issues Kyiv, September 2012 Kristina ARTEMENKO EU Project "Harmonisation of Competition and Public Procurement.
December 8, Changes to Patent Fees Under the Consolidated Appropriations Act, 2005 (H.R. 4818)(upon enactment) and 35 U.S.C. 103(c) as Amended by.
Contract Review.  1. The final step in the vendor contracting process should be getting the vendor’s standard written contract and signing the contract.
TAX ADMINISTRATION ACT, 2011 By Johan Kotze Head of Tax Dispute Resolution.
Revenue Enforcement Legal Strategies Lawrence K. Nodine Ballard Spahr December 16, 2009.
Center of Islamic Finance COMSATS Institute of Information Technology Lahore Campus 1 Adopted from open source lecture of Meezan Bank. Customized for best.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Pre-action Procedure for Financial Cases. Pre-action Procedure- Financial Cases  Rule 1.05(1)- each prospective party to the case must comply with the.
Local Assessment of Code of Conduct Complaints. 2 Background  On 08 May 2008 – the local assessment of Code of Conduct complaints was implemented due.
Third Party Alternative Dispute Resolution. Alternative Dispute Resolution (ADR)?  It involves the application of theories, procedures, and skills designed.
1 Ⅴ. General Articles Ⅵ. Transfer Article 29 Extension of Expiry Date or Last Day for Presentation Article 30 Tolerance in Credit Amount, Quantity and.
Procedural Safeguards. Purpose Guarantee parents both an opportunity for meaningful input into all decisions affecting their child’s education and the.
Doc.: IEEE /1129r1 Submission July 2006 Harry Worstell, AT&TSlide 1 Appeal Tutorial Notice: This document has been prepared to assist IEEE
1 Expenditure Documentation Review. 2 The Purpose of the Expenditure Documentation Review Beginning with Fiscal Year , the Office of Family Planning.
Rabbanai T. Morgan Current as of 26 January 2006 Protests.
1 WIPO Arbitration and Mediation Center Rome Conference, December 11, 2009 Theme 6: Dispute Settlement and Enforcement of IP Rights by MSMEs WIPO Arbitration.
1 A decade of revisions at UNCITRAL Special Course 6 – James Castello Lecture 3 Arbitration Academy PA R I S SUMMER COURSES
1 DISPUTE SETTLEMENT THROUGH ADJUDICATION N D Sharma.
1 A decade of revisions at UNCITRAL Special Course 6 – James Castello Lecture 5 Arbitration Academy PA R I S SUMMER COURSES
Local Assessment of Code of Conduct Complaints. Background  On 08 May 2008 – the local assessment of Code of Conduct complaints was implemented due to.
Mediation with the Information Commissioner’s Office Cory Martinson Appeals and Policy Analyst 25 November 2009.
Change Orders. CO Proposals Initiated by owner or GC –Owner requests estimate for work proposed –GC CO results from changed site condition or response.
Notes on the drafting of arbitration agreements in shipping and transport related contracts Fredrik Andersson 16 June 2014.
Legalwise Seminar : 27 November 2015 Review of Strata Title Reforms: Impact and Vision for the Future ____________________________________________________________________________________________.
Office of the Disability Appeals Officer Oifig an Oifigigh Achomhairc um Míchumas National Information Sharing Day February2009.
ODAO Information Sharing Day Presentation February/March Office of the Disability Appeals Officer Oifig an Oifigigh Achomhairc um Míchumas National.
SESSION SEVEN THE HEARING (UNCITRAL 2010) Immanuel Kant Baltic Federal University Kaliningrad, Russia John B. Tieder, Jr., Esq. McLean, Virginia USA
ADVOCATE S The Arbitration and Conciliation Act, The Arbitration and Conciliation (Amendment) Ordinance, 2015 C-17, II Floor, LSC I Paschimi Marg.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
Equal Employment Opportunity (EEO) Division of Immigration Health Services FY 2010.
By Khalil T. Hasan Construction Solutions ( Joint Operation/Administration of multiple FIDIC Forms – A Case Study.
What is the court’s expectation of doctors? British Medical Association 17 November 2006.
ARBITRATION ACT. Challenge of arbitrator The appointment of an arbitrator may be challenged on the issues of – (i) impartiality, – (ii) independence,
CCA Adjudication Cashflow, or fair dispute resolution, or both? Opportunities for Improvement in the Act and adjudication procedure Peter Degerholm AMINZ.
Step Advancement Based on Satisfactory Performance Departmental Human Resources Group Meeting July 28, 2006.
Article 4 [Obligations of Applicant] 4.1. As a sole and exclusive owner of the Application, Applicant warrants that.
CONTRACT ADMINISTRATION
Dispute Resolution Between ICT Service Providers in Saudi Arabia
Administration of a FIDIC Contract - Project Control
Resolving IP Disputes outside the Courts through WIPO ADR
Civil Pre-Trial Procedures
Civil Pre-Trial Procedures
Extension of time and how it is granted to a contractor (Referencing JCT 2005)
First Collective Agreements
ARBITRATION AWARD.
Marcus Claridge Director Energy and Water October 2017
Education Employment Procedures Law of 2001
SIMAD UNIVERSITY Keyd abdirahman salaad.
EEO MODULE 3: DISCRIMINATION COMPLAINT PROCESSING
Appeal Tutorial Date: Authors: July 2006 Month Year
Grant Implementation Agreement (GIA)
Stakeholders sensitization PRESENTED BY ANTHONY GACHAI PTA
Presentation transcript:

Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa

2 Outline Contract Administrator’s Authority Extension of Contract Time Changes in the Work Claims, Negotiations, Mediation Rights to Correct a Default

3 Contract Administrator’s Authority l Section GC 3.01 (01) The Owner’s representative (02) All claims, disputes etc. shall be referred to CA in writing by Contractor (06) CA will investigate all allegations of a change in the character of the work made by the Contractor and issue appropriate Instructions

4 CA’s Authority continued (09) The CA will be, in first instance, the interpreter of the Contract Documents and the judge of the performance thereunder by both parties to the Contract. Interpretations and decisions of the CA shall be consistent with the intent of the Contract Documents and in making these decisions the CA will not show partiality to either party.

5 Extension of Contract Time l Section GC 3.06 (01) An application for an extension of Contact Time shall be made in writing by the Contractor to the CA as soon as the need for such an extension becomes evident and at least 15 days prior to the expiration of the Contract Time. The application for an extension of Contract Time shall enumerate the reasons, and state the length of extension required..…continued

6 Extension of Contract Time …continued (03) The CA will, in considering an application for an extension to the Contract Time, take into account whether the delays, Changes in the Work, Extra Work or Additional Work involve a Controlling Operation. (04) The Contract Time shall be extended for such an additional time as may be recommended by the Contract Administrator and deemed fair and reasonable by the Owner.

7 Extension of Contract Time … continued (05) The terms and conditions of the Contract shall continue for such extension of the Contract Time. (06) All the provisions of subsection GC.3.07 shall also apply to an extension of the Completion Date.

8 Delays l Section GC 3.07 (01)If the Contractor is delayed in the performance of the Work by, a) an act or omission of the Owner or CA; or… d) Then the Contractor shall be reimbursed by the Owner for reasonable direct costs incurred by the Contractor…( continued)

9 Delays … continued …as the result of such delay, provided that the Contractor presents a written notice of calm for delay to the CA not later than (10) days after the commencement of the delay. In the case of a continuing cause of delay, only one notice of claim shall be necessary.

10 Delays … continued (01) e) Notwithstanding the agreed upon direct costs in (c) above, the Contractor shall not be reimbursed by the Owner for other lost profits, administrative costs, impact costs, indirect costs or damages relate to other works not included in the contract. Extension of Contact Time will be considered in accordance with subsection GC 3.06, Extension of Contract Time.

11 Delays … continued (03) The Contractor shall not be entitled to payment for the cost of delays incurred as a result of a dispute between the Contractor and the Owner. The Contractor shall execute the Work and may pursue resolution of the dispute in accordance with subsection GC 3.13, Claims, Negotiations, Mediations.

12 Changes l Section GC Changes in the Work 01) The Owner, or the CA where so authorized, may, by order in writing, make Changes in the Work without invalidating the Contract. The Contractor shall not be required to proceed with a Change in the Work until in the receipt of a Change Directive. Upon receipt of such Change Directive the Contractor shall proceed with the Change of Work.

13 Changes… continued 02)The Contractor may apply for an extension of Contract Time according to the terms of subsection GC 3.06, Extension of Contract Time. 03)If the Changes in the Work relate solely to quantities, payment for the Work will be made according to the conditions specified in clause GC , Variations in Tender Quantities. …continued

14 Changes… continued 03) If the Changes in the Work do not solely relate to quantities, payment may be negotiated pursuant to subsection GC 3.13, Claims, Negotiations, Mediation or payment may be made according to the conditions contained in clause GC , Payment on a Time and Material Basis.

15 Extra Work l Section ) The Owner, or the CA where so authorized, may, by order in writing, make Changes in the Work without invalidating the Contract. The Contractor shall not be required to proceed with Extra Work until in receipt of a Change Directive. Upon receipt of such Change Directive the Contractor shall proceed with the Extra Work.

16 Extra Work… continued (02) and (03) essentially the same as GC provisions for Changes in the Work.

17 Additional Work l Section GC All 3 sections essentially the same as for Changes in the Work andExtra Work.

18 Claims, Negotiations, Mediation l Section GC Continuance of the Work l GC (01)- Unless the Contract has been terminated or completed, the Contractor shall in every case, after serving or receiving any notification of a claim or dispute, verbal or written, continue to proceed with the Work with due diligence and expedition. It is understood by the parties that such action will not jeopardize any claim it may have.

19 Claims, Negotiations, Mediation… continued l GC Record Keeping (01) Immediately upon commencing work which may result in a claim, the Contractor shall keep Daily Work Records, during the course of the Work, sufficient to substantiate the Contractor’s claim, and the Contract Administrator will keep Daily Work Records to be used in assessing the Contractor’s claim, all in accordance with clause GC , Records.

20 Claims Procedure l Section ) The Contractor shall give verbal notice of any situation which may lead to a claim for additional payment immediately upon becoming aware of the situation. 02) The Contractor shall provide written notice in the standard form “Notice of Intent to Claim” within (7) days… …continued

21 Claims Procedure… continued …of the commencement of any Work which may be affected by the situation. 03) The Contractor shall submit detailed claims as soon as reasonably possible and in any event no later than 30 days after completion of the work affected by the situation.

22 Claims Procedure… continued 04) Within 30 days of the receipt of the Contractor’s detailed claim, the CA may request further and other particulars which the Contractor must submit within 30 days of receipt of such request. 05) Within 90 days of receipt of the detailed claim, CA will advise the Contractor, in writing, of the CA’s opinion with regard to the validity of the claim.

23 Negotiations l Section GC (01) The parties shall make all reasonable efforts to resolve their dispute by amicable negotiations and agree to provide, without prejudice, open and timely disclosure of relevant facts, information, and documents to facilitate these negotiations.

24 Negotiations … continued (02) Should the Contractor disagree with the opinion given in paragraph GC , with respect to any part of the claim, the CA shall enter into negotiations with the Contractor to resolve the matters in dispute. Where a negotiated settlement cannot be reached and it is agreed that payment cannot be made on Time and Material basis in accordance with clause GC , …

25 Negotiations … continued …, the parties shall proceed in accordance with clause GC , Mediation, or subsection GC 3.14, Arbitration.

26 Mediation l Section GC (01) If the claim is not resolved satisfactorily through the negotiation stage noted in clause GC , Negotiations, within a period of 30 days following the opinion given in paragraph GC , and the Contractor wishes to pursue the issue further, the parties may, upon mutual agreement, utilize the services of an independent third party mediator.

27 Mediation… continued (4) The review by the Mediator shall be completed within 90 days following the opinion given in paragraph GC (05) Each party is responsible for its own costs related to the use of the third party mediator process. The cost of the third party mediator shall be equally shared by the Owner and Contractor.

28 Arbitration l Section GC (01) If a claim is not resolved through negotiation or mediation, either party may initiate an arbitration by giving written notice to the other party. (03) The parties shall be bound by the decision of the arbitrator. … continued

29 Arbitration … continued (04) the rules and procedures of the Arbitration Act 1991, S.O. 1991, c.17, as amended, shall apply to the arbitration.

30 Costs l Section GC (01)The arbitrator’s fee shall be equally shared by the Owner and the Contractor. (04) The arbitrator may, at his or her discretion, award reasonable costs, related to the arbitration.

31 Decision l Section GC (01) Decision to be made in writing within 90 days of the conclusion of the hearing. An extension of time to make a decision may be granted with consent of both parties.

32 Contractor’s Right to Correct a Default l Section GC 4.06 (01) The Contractor shall have the right within the 5 full Working Days following the receipt of a notice of default to correct the default and provide the Owner with satisfactory proof that appropriate corrective measures have been taken.

33 Contractor’s Right to Correct a Default… continued (02) If the correction cannot be completed within the 5 full Working Days following receipt of the notice, the Contractor shall not be in default if the Contractor, (a) commences the correction of the default within the 5 full Working Days following receipt of the notice; (b)provides the Owner with an acceptable schedule for the progress of such correction; and …continued

34 Contractor’s Right to Correct a Default… continued (c) completes the correction in accordance with such schedule.

35 Thank you