CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES John Osborne GS/SE 16 May 2013.

Slides:



Advertisements
Similar presentations
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
Advertisements

Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
CFS challenges for a linear collider J.Osborne CERN ILC-GDE Dubna - 4 June 2008 OUTLINE : Introduction Civil Engineering -Geology (water, stability issues.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
Construction Industry Development Board development through partnership Construction Procurement documents 2c.
WELCOME TO THE PROCUREMENT SEMINAR Procurement and Contracts An Overview of Contract Administration.
CFS near term & Required ADI input CFS near term & Required ADI input 6-12 month activities, required ADI information 10. AUG 2014CFS-ADI Joint Meeting1.
John Osborne GS/SE March 2013
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
3 Dec 2003Market Operations Standing Committee1 Market Rule and Change Management Consultation Process John MacKenzie / Darren Finkbeiner / Ella Kokotsis,
EAST DON TRAIL ENVIRONMENTAL ASSESSMENT Project Overview Ward 31 Ravine Meeting November 4, :00 to 9:00 p.m. Presteign-Woodbine United Church.
Tim Watson ST-CE CE Experience with External Consultants for the LHC Project.
INVITATION TO TENDER PROCEDURE INVITATION TO TENDER PROCEDURE IT – 3972/EN PROVISION OF MAINTENANCE SERVICES ON INDUSTRIAL TRUCKS ON THE CERN SITE Insert.
PIT MANAGEMENT Why? Technical Standards Branch CEA PRESENTATION Revised Feb14 Bruce Blue.
Invitation To Tender Procedure IT – 4005/en Provision of engineering studies and drawings, the supply and installation of piping and its accessories.
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP Status and Overview.
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
Geotechnical & Civil Engineering Studies Future Circular Colliders (FCC)
CENF target facility civil engineering specifications – summary M. Calviani (EN/STI) for the CENF-SBWG team Neutrino Platform Meeting 30 th October 2014.
FCC Tunnel Civil Engineering and Geology John Osborne (CERN GS-SE) 4 April 2014.
CONSTRUCTION CONTRACTS PRIME CONTRACTS Format and Major Components CHAPTER - 4.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
Former DuPont Barksdale Works Project Update May 19, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center.
DESY_ILCW07 Global Design Effort-CF&S 1 Beam Delivery System & Interaction Region Fred Asiri CF&S Point of Contact.
ULCH Stormwater Fees An Equivalent Stormwater Unit (ESU) is calculated so 1 ESU covers the average impermeable surface in one normal city lot Given all.
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
Millbrook Dam Environmental Assessment Study Dan Marinigh CAO/Secretary-Treasurer Otonabee Region Conservation Authority October 20, 2015 Otonabee Conservation.
John Osborne : GS-SEM Civil Engineering 18 May 2009 CES 9 June News from ILC Japan CFS review 1-3 June 2010 :
15 January Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Conventional Facilities and Siting GG Global Design Effort BILCW 07 - Beijing1 Conventional Facilities and Siting Global Group Summary Report.
Former DuPont Barksdale Works Project Update July 14, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center.
T. KurtykaLinac4 meeting 12 March 2009 Guidelines from the sLHC Specification Committee 1). sLHC Specification Committee 2). Schedule of tenders for Linac4.
CENF CIVIL ENGINEERING : - DESIGN TENDER AND ESTIMATED COSTS John Osborne GS/SE 19 July 2013.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
HNSciCloud Pre-Commercial Procurement Project Procurement Framework and Schedule Dante Gregorio CERN 26 January
General Infrastructures Services Department Civil Engineering planning for LSS4 Option, presented at review workshop 30/7/ months Planning and Resources:
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
MDI 9 th Meeting - 22 nd January 2016 FCC Experimental Caverns - Feasibility and Excavation C. Cook (GS), J. Osborne (GS),
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
Survey Meeting John Osborne, CERN 8 February 2016
INVITATION TO TENDER PROCEDURE INVITATION TO TENDER PROCEDURE IT–4144/SMB/HL-LHC (Point 1) IT-4155/SMB/HL-LHC (Point 5)
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES - 3D VISUALS FOR SURFACE STRUCTURES.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
Work by contractors And Safety Coordination CONTRACTORS ’ ACTIVITIES What is the role of TSOs when contractors are working in their area? HSE Unit - Olivier.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Tuesday, May 3 rd, 2016.
The realisation of the projects: "sine qua non" condition for the absorption of the EU Funds.
PROCUREMENT RULES FOR EXPERIMENTS AT CERN Dante Gregorio CERN Procurement Service.
PRESENTED BY HENRY RUHNKE WALD, RUHNKE & DOST ARCHITECTS, LLP SIERRA HOUSE & DROP-IN CENTER.
FCC Underground Infrastructure
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
FCC Civil Engineering John Osborne & Jo Stanyard (SMB - Site Engineering - FAS Section) FCC week outline 10th May 2017.
Building 107 Update Introduction Project team Location Design status
Civil Engineering for FCC-eh IR
ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe – KICK OFF MEETING
CLIC Civil Engineering Update
National Conference of Regulatory Attorneys
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
WG GES: Decision review progress
MULTISPORTS CENTRE PRESENTATION
Review plan of the nature reporting – update 6
FCC Week 2019 Civil Engineering Summary
CV-SALTS Beneficial Use and Objective Study
Calendar Overview – Phase I – REVISED April 2019
East Hall under construction
FASER LS2 work coordination meeting
Presentation transcript:

CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES John Osborne GS/SE 16 May 2013

Site investigation for Near Detector and Target Area will be complete by end of May

Pumping tests have indicated that C12 (Near Detector) is in liaison with the ‘Lion’ Stream.

Tender documents : Updated list of firms from MS Instruction to Bidders Technical Spec including : Descriptive Deliverables for the phases Safety Rules Drawings Geology Risk Matrix Conditions of Contract Tender Form “Best Value for Money” Questions & Criteria (50%/50%) etc Call for tender for CE Design and Contract Administration

Phases of Services Phrase added top have a ’hold’ point after each phase to allow contract termination after any Phase Lump Sum

Key Dates (1) Specification Committee Monday 29 April. HSE & Legal Service consulted at the same time. Second meeting held Friday 3 May. Technical documents complete Documents will be send around for final comments this week Target date for Bidders Conference is Mon 10 June Target closing date for receiving bids is day 28 June Special FC Approval in July (Accelerated Procedure required including Peers Review)

Near and Far Buildings : Tender Design (Phase 1) complete by October 2013 (over summer months !) Construction Design (Phase 2) complete by end of 2013 CE construction works early 2014 – early 2015 Target area Tender Design (Phase 1) complete by March 2014 Construction Design (Phase 2) complete by July 2014 CE construction works mid 2014 – early 2016 *Junction cavern, extraction tunnel and service bld dates to be confirmed *Input from all CERN services needed to allow this firm to do detailed civil design (CV,EL, Access, Cranes etc) Key Dates (2) (+1 month ?) November

SPARES

CATIA CE model of North Hall nearly complete for Integration Bld 887 L.Faisandel GS/SE

CENF geological survey findings Completed borings up till 30 April 2013: C11-C14 (near detector area) Stratigraphy C11 and C12 0.2m-1.2m topsoil and backfill 1.2m to 8.0m Wurmian Moraine (clays, silts) Consolidated Intra-moraine units (marly, sandy, gravely), maximum thickness of 2.2m Partially saturated → excavation in wet conditions Between 6.0m and 13.0m gravels Compacted Aquifer → pumping tests will be carried out to determine the properties of the aquifer From13.0m up to 20m Rissien Moraine Stratigraphy C13 Entire borehole consists of Moraine, except for an intra-moraine marly and gravely unit at 5.0 – 7.2m depth Marly unit partially saturated → excavation in wet conditions Aquifer in gravels Stratigraphy C14 Entire borehole consists of Moraine, except for an intra-moraine marly and gravely unit at 5.0 – 7.2m depth Partially saturated → excavation in wet conditions No well defined aquifer, but some water inflow has been noted Initial conclusions Geology is very heterogeneous Groundwater levels are variable