D. Delikaris, TE-CRG, LSC 25th Meeting 18.10.2013 Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.

Slides:



Advertisements
Similar presentations
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Advertisements

O. Pirotte, A.Perin, TE/CRG, 4 th LHC Splice Review, Page 2 4 th LHC Splice Review, July 22-24, 2013 O. Pirotte (TE-CRG), A. Perin (TE-CRG)
Going towards LHC Run2 CRYOGENICS 5 th Evian Workshop 2-4 June 2014 SESSION 4 - Systems 2 - Status and commissioning plans (HW perspective) Krzysztof Brodzinski.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
STATUS OF THE MEG CRYOSTAT Construction status Schedule ____________________________________________________________ 04/Agust/06 F. Raffaelli, L. Delfrate.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
TE-CRG Activities D. Delikaris, TE-CRG.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
A. Perin, TE/CRG, DFBA LSC Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation.
MPE Workshop for LS1 / 22 & 23 Nov  DFB Instrumentation Upgrade  Cabling Issues  R2E Consolidation  Current Lead Insulation Project  DFB Instrumentation.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Spectrometer Solenoid Prep Work at RAL and LBNL Steve Virostek Lawrence Berkeley National Lab Steve Virostek Lawrence Berkeley National Lab MICE VC May.
LHC CRYOGENICS – new experience of run with increased beam energy and intensity Krzysztof Brodzinski CERN, Geneva, Switzerland With contribution from:
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
Workshop on Appraisal of Disassembled Magnets: Lessons learned March 17 th, 2005 Boundary Conditions-Technical Specification Jos Vlogaert.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
TE-CRG Activities A. Perin, on behalf on the Cryogenics Group.
LHC Performance Workshop LS1 Session Cryogenic system: strategy to achieve nominal performance and reliable operation J. Bremer, K. Brodzinski, J. Casas,
OMP: Major maintenance policy of the LHC Accelerator and Detectors Motors & Compressor for the EYETS, YETS & LS2 period.
K. Foraz on behalf of OSS members
SMACC Tenth report [15 min] 13/09/2013
Update of cryogenic activities
LS1 Committee January 24th, 2014
CRYOGENICS – strategy, unavailability root causes and limitations
Nikolaos TRIKOUPIS on behalf of TE-CRG-CI CRG-TM for LS2 preparation Preliminary activities of the CI section 25/09/2017
Preparation of the activities for the LHC Long Shutdown 2
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
Activities of the ME section during LS2 ( )
Overview & baseline of LS2 and roadmap for CRG
Status of the cryogenic system for B180
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
K. Foraz on behalf of OSS members
SNS Cryoplant Commissioning Past Experiences
Presentation transcript:

D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities report

D. Delikaris, TE-CRG, LSC 25th Meeting Page 3 Agenda Update on Cryogenic Activities: Preventive Maintenance - Major overhauling Helium Cold Boxes repairs in LHC P2-P8-P6 cryoplants QRL compensator bellows (Headers C & D) DFBA splice consolidation DFBA gimbal bellows

D. Delikaris, TE-CRG, LSC 25th Meeting Page 4 Preventive maintenance C199 contract for Preventive & Corrective maintenance activities Investigation launched to understand the “baseline vs work orders vs work progress” issue: Work progress on schedule wrt to LS1 planning; shifted with respect to the original CRG baseline (non-adapted to real work progress tracking) Discrepancy between work progress & work orders (WO) completion: due to open WO that can only be closed at a later stage & dates Remaining actions: Work order line to be completed wrt expected milestones for closure A new version of the baseline will be defined

D. Delikaris, TE-CRG, LSC 25th Meeting Page 5 Major overhauling; Dashboards Helium screw compressors 3.3 kV electrical motors Everything on track Delayed delivery of Kaeser compressors caused by additional corrective maintenance task (rotors replacement)

D. Delikaris, TE-CRG, LSC 25th Meeting Page 6

D. Delikaris, TE-CRG, LSC 25th Meeting Page 7 Major overhauling (compressors & 3.3 kV motors) Reception from manufacturer and… …installation, coupling and alignment at LHC P6

D. Delikaris, TE-CRG, LSC 25th Meeting Page 8 P2 18 kW LHC cold box repair Leak repaired on medium pressure He circuit to insulation vacuum (heat exchanger) First tightness testing: done Reinstallation of MLI: underway Closing of the vacuum jacket: w Vacuum pumping: w 46 Final testing: w Matter removal for two stage welding Intermediate stage Final stage Excellent work from Fives Cryogenie (FR)

D. Delikaris, TE-CRG, LSC 25th Meeting Page 9 P8 18 kW LHC cold box repair Leak repaired on N2 circuit of to insulation vacuum (pre-cooling heat exchanger) First tightness testing: done Reinstallation of MLI: underway Closing of the vacuum jacket: w Vacuum pumping: w 46 Final test: w 47 Leak observed Matter removal Final welding

D. Delikaris, TE-CRG, LSC 25th Meeting Page 10 P6 18 kW LHC cold box repair - Leak to be repaired on SS/AL transition, He to insulation vacuum - Spare ordered (Japan), expected mid Nov. - Order done; repair to be done by Linde end of Nov. Aluminium to Stainless Steel transition DN400 HP LP MP

D. Delikaris, TE-CRG, LSC 25th Meeting Page 11 QRL Headers C & D compensator x-rays status

D. Delikaris, TE-CRG, LSC 25th Meeting Page 12 QRL Headers C & D compensator repair status Header D in the LS1 planning Additional information: - Header D in 14L2: external envelope was open, dedicated spare testing is underway - Header D: 4 additional spares available - Header E: 31/64 (LHC all sectors) compensators checked and OK (partially visible on line C x-ray) - Headers C & E new spares: 3 offers requested mid August, only one feedback from Witzenmann received, order will be sent next week with 12 weeks of delivery time for 30 DN100 and 15 DN80

D. Delikaris, TE-CRG, LSC 25th Meeting Page 13 DFBA 13 kA splices consolidation Schedule shift caused by: - Extra time for repair of non conformities (quality checks, geometrical) for DFBAN & DFBAO - Discovery of damaged bellows in DFBAO - Personnel illness (one) Forecast: - Disturbance due to disconnection (same team as splices) of DFBAK (for repairing the bellows) will add 1-2 weeks - Training of additional personnel (existing) for recovery

D. Delikaris, TE-CRG, LSC 25th Meeting Page 14 DFBA gimbal bellows Following the discovery of a damaged bellow in the DFBAO by using a double endoscope inspection technique, a global inspection of the bellows is being carried out: to be completed by end of the w 43 on all DFBAs Current status (4/32; 12.5 %): 2 DFBAs with upper bellows damaged (DFBAK collapsed & probably leaking, DFBAO damaged but not leaking) 2 DFBAs with lower gimbal damaged; not leaking (DFBAI & DFBAF) First inspection of DFBAO Double endoscope inspection of DFBAO upper bellows Lower bellows

D. Delikaris, TE-CRG, LSC 25th Meeting Page 15 DFBA gimbal bellows: repair strategy - Lower bellows: in-situ repair, 3 weeks each for DFBAI and DFBAF respectively (patching solution) - Upper bellow DFBAK: workshop repair, bellows replacement, learning form opening - Develop local internal solution for DFBAO by drilling the inner layer of the 2-layer bellow thus eliminating the helium accumulation issue and reinforce the mechanical resistance of the bellow by encapsulating it in an epoxy shell. Decision for DFBAO in 6 weeks. DFBAK closed 24/02/2014 DFBAO closed, if local repair, 17/01/2014 DFBAO closed, if workshop repair, 09/04/2014

D. Delikaris, TE-CRG, LSC 25th Meeting Page 16 Conclusions Preventive Maintenance - Major overhauling C199: Discrepancy on baseline/work progress/work orders clarified and to be closely followed; major overhauling of helium compressors and 3.3 kV electrical motors on schedule Helium Cold Boxes repairs in LHC P2-P8-P6 cryoplants Very good progress; P2-P8 completed; P6 on schedule QRL compensator bellows Damaged bellow on header D in the repair planning compliant to LS1; Header C bellows repair work ahead of schedule; spares procurement for all bellow’s type on going DFBA splice consolidation Despite additional resources work progress remains constantly shifted from the baseline (originally expected to recover by end of 2013) due to geometrical non-conformities, personnel illness and the discovery of a 4 th damaged gimbal interfering with teams load. Training of additional personnel scheduled DFBA gimbal bellows On going cross-check by double endoscopy of all DFBAs bellows; DFBAI, DFBAF: in-situ repair (patching) DFBAK: workshop repair (bellows replacement) DFBAO: development of dedicated local technical approach for in-situ repair prioritized; final decision in 6 weeks, if negative, workshop repair (bellows replacement)