Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.

Slides:



Advertisements
Similar presentations
Right of Way Acquisition Process Jesse W. Smith Right of Way Manager.
Advertisements

Metro Muncipal Agreement Program
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
Project Development Process (PDP) Structures. PDP – Three Project Levels Major Project ~ 14 Steps Major Project ~ 14 Steps Minor Project ~ 10 Steps Minor.
CMGC Contracting at UDOT Program, Projects & Lessons Learned
Phases of Plan Development – Leading to High Quality Plans ACEC/ODOT Conference April 15, 2008 Steve Cooley, PE, PLS ODOT Region 2 Technical Center Manager.
Charlottesville Residency Monthly Report 1 April 2004   Mission  Essential Tasks Assessment  Construction & Maintenance  Planning & Traffic Engineering.
FDOT R/W Guidelines Use of License Agreements
Project Prospectus and Design Acceptance Package ( and a little more) Alan Lively Project Delivery Specialist January 30, 2009.
Plans, Specifications and Estimate (PS&E) Kelli Sparkman Local Agency Liaison, Region 3 January 30, 2009.
State Aid Design-Build Project Delivery for Minnesota Cities and Counties.
Alternative Project Delivery
Northeast Corridor Greenway Acquisition – Mitigation Feasibility Study Results City Council Workshop June 24, 2014.
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
PROJECT AUTHORIZATIONS September 24, 2014 by Peter Anderson HQ Area Engineer – Districts 1 and 4 & Ephrem Meharena i- Team, Caltrans District 4 + VTA.
Overview of the Federal Aid Process for Transportation Projects.
Understanding Right of Way Process Dawn Haecker - Training & Technical Support Supervisor INDOT Trent Newport - VP, CrossRoad Engineers.
Managing Risk to Reduce Construction Claims (And Improve Project Success) Presented by Laurie Dennis, PE, CVS-Life, FSAVE.
SAFETY * MOBILITY * DELIVERY * STEWARDSHIP * SERVICE Timely Use of Federal and State Funds Stella Liao, P.E. District Local Assistance Engineer 1.
Brookwood/Helvetia Key #16842 Post-Bid Project Review PDT Feedback meeting 10/23/13.
Project Background STIP update - City requests cancellation of US101 at Logan Road EA and proposes new modernization project: US101 at 32nd Street.
W E L C O M E to the SB 1022 Real Estate Due Diligence Training SB 1022 Real Estate Due Diligence Training.
CALTRANS WIRELESS LICENSING PROGRAM Bimla G. Rhinehart Division of Right of Way and Land Surveys.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
Office of Traffic, Safety and Technology Module 6 Specifications and Special Provisions Traffic Control Plan Development Course.
Right of Way Section Dee Jones State Right of Way Manager Richard Dunlap Operations Manager Joe Gray Region 5 Right of Way Manager
Bridge Building Timelines Presented by The Richland County Engineers Office Thomas E. Beck, PE, PS 77 North Mulberry Street Mansfield, Ohio Jan.
Improving Understanding, Function and Procedural DBE Compliance ODOT OCR DBE Triage Training Office of Civil Rights DBE Program ODOT Training March 1,
Presented by Molly Skorpik at the 2011 Montana Association of Dam and Canal Systems Conference Presented by Molly Skorpik at the 2011 Montana Association.
Rural Intersection Conflict Warning System (RICWS) Design-Build Project.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
1 Developing Scope of Work, Budgets and Schedules for the OTIA III State Bridge Delivery Program Raymond Mabey, Deputy Program Manager, ODOT Lynn Iaquinta,
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
TH 2 – Wilton Bridge Replacement Design-Build Project S.P March 5, 2009 Todd Vonasek, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Transportation Enhancements Application Workshop Welcome!! October 3 & 4, 2012.
Transportation Management Plan Overview. TMP Overview2 Is that the impression people have?
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
RIGHT OF WAY BEST PRACTICES FOR LOCAL PUBLIC AGENCIES.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
New York State Department of Transportation Accelerated Bridge Program Phase 1B Design-Build Projects Request for Proposals Informational Meeting April.
Local Government Section Welcome Marty Andersen ODOT Local Government Section 355 Capitol Street NE, Rm. 326 Salem, Oregon Ph:
OREGON DEPARTMENT OF TRANSPORTATION Practical Design Decision Matrix.
PROJECT PHASES ACT Objective To provide an understanding of the design & construction process and the roles of the different participants in this.
Project Development Process. ODOT’ PDP A project management and transportation decision-making tool. Developing the detail to the level necessary to make.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
D.d. delivers district department of transportation d.d. delivers FAISAL HAMEED RONALDO T. NICHOLSON. P.E. Innovative Project Delivery Processes Innovative.
Project Scoping. Project Scoping – learning objective Who should complete the Project Initiation Package (PIP)? How is PDP Path used in scoping? Task.
Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
LPA Program Federal-aid Issues for Local Agencies Mike Morrow – December 10, 2010.
OTC Pres: Bid & Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office.
Orlando-Orange County Expressway Authority Project Development Process.
Winton Emmett, Chief Project Implementation North January, 2016 Division of Local Assistance John Hoole, Chief Project Implementation South.
The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects the current highway location in order to continue.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
Dave Adamson Design Network launched 2 years ago Had many good ideas Discipline tracks Activity ownership Milestone meetings Promised “Not Static”
Request For Proposals. Request for Proposals Book 1 Contract Book 2 Project Requirements Book 3 Applicable Standards Reference Information Documents (RID)
A New Paradigm for Utility Coordination Kenny Franklin VP of SUE Development Blood Hound.
Resident Engineer Training
LOCALLY ADMINISTERED PROJECTS
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
General comments: These projects are locally owned and the LPA should be involved and informed throughout the project. The project agreement is between.
A Paradigm for Utility Coordination
Construction Considerations
Right of Way Certification
Presentation transcript:

Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical Services, Right of Way October 21, 2008 Design (Design Acceptance Package (DAP) through Plans, Specifications & Estimates (PS&E)) PROJECT DEVELOPMENT – PHASE 3

OTC Pres: Design Phase 3 10/08 Page 2 Project Delivery Process

OTC Pres: Design Phase 3 10/08 Page 3 Design (Design Acceptance Package (DAP) through Plans, Specifications & Estimates (PS&E)) Environmental permitting Right of Way Construction (PS&E) documents Project Delivery methods Mobility Stakeholder involvement

OTC Pres: Design Phase 3 10/08 Page 4 Design Acceptance Package (DAP) Milestone Establishes the project “footprint” for:  “Pens down” (avoid rework)  Environmental permitting (if needed)  Right-of-way acquisition (if needed) Confirms readiness to develop construction contract documents Concurrence of project stakeholders

OTC Pres: Design Phase 3 10/08 Page 5 Design (DAP – PS&E) Processes—Overview Environmental (EIS/EA) complete, obtain permits  Critical Path (6-18 months) Right-of-Way  Critical path (1-2+ Years) Design Phase  Timeline 1-2 Years (Class 2, DAP-PS&E) Permits and Right of Way are now sequential, preliminary design is concurrent

OTC Pres: Design Phase 3 10/08 Page 6 Design (DAP – PS&E) RIGHT-OF-WAY Timeline (1-2 years) Finalize Right of Way Maps and Descriptions Right of Way Certification at PS&E FHWA Authorization for R/W Acquisitions Appraisals Negotiations with Property Owners Relocation Issues (if necessary) Condemnation (no agreement) to possession DAP PS&E

OTC Pres: Design Phase 3 10/08 Page 7 Design (DAP – PS&E) DESIGN Timeline (typically 1-2 yrs after DAP) Preliminary Plans 75% Complete Advanced Plans 95% Complete Final Plans 100% Complete Plans, Specifications, Estimates (PS&E) Documents PS&E Quality Control

OTC Pres: Design Phase 3 10/08 Page 8 Design (DAP – PS&E) Plans for Construction Roadway Plans Bridge Plans Traffic Structures Plans Retaining Wall Plans Soundwall Plans Material Source and Disposal Site Plans Roadside Development Plans Geotechnical Plans Hazardous Materials Plans Wetland Mitigation Plans Erosion Control Plans Hydraulic Plans Water Quality and Detention Plans Traffic Control Plans Sign Plans Striping Plans Signal Plans Illumination Plans Construction Cost Estimate Construction Schedule Special Provisions Utility Conflict List Constructability Review Value Engineering Study Insurance Risk Assessment Access Management PS&E Submittal Plan Review Assemble and Submit Final PS&E to Office of Pre-Letting Bidding Package

OTC Pres: Design Phase 3 10/08 Page 9 Design (DAP – PS&E) Project Team Approach Before project development teams, design was more sequential, requiring considerable rework Now project teams include all engineering and other disciplines working concurrently Construction and maintenance included in project teams

OTC Pres: Design Phase 3 10/08 Page 10  ‘Critical path’ (can take 1-2+ years)  Sensitive relationships with property owners & public  Property owner rights Design (DAP – PS&E) Right of Way Complexities

OTC Pres: Design Phase 3 10/08 Page 11  20+ Environmental disciplines  10+ Regulatory & local agencies  Continual stakeholder involvement Design (DAP – PS&E) Environmental Permitting Complexities

OTC Pres: Design Phase 3 10/08 Page 12 Costs PhaseModernizationBridgePreservation Safety/ Ops Planning9.1%5.2%0.4%3.0% Design9.1%5.4%6.7%13.0% RoW / Utility Relocation3.4%1.3%1.6%4.5% Bid & Award Construction Engineering Construction Total (%)21.6%11.9%8.7%20.5% * State projects only * Only primary work types included * Based on projects 2nd noted between 1/1/2005 and 12/31/2007 (completed projects) * 3 Design/Build projects excluded * Projects with unusual expenditure patterns excluded (17 projects) * Right of way expenditures uncommonly low due to specific projects included in this report (largest projects completed were in rural areas or areas that did not involve significant right of way expenses.

OTC Pres: Design Phase 3 10/08 Page 13 Success for Project Delivery is: Minimize contract addenda Plans that are –Permittable –Biddable –Buildable –Maintainable –Supported by the community

OTC Pres: Design Phase 3 10/08 Page 14 Continuous Improvements Completed Mobility is always considered at the project and corridor level, process is working well ROW ADR program RWDMS – acquisition process streamlining (phase 1)

OTC Pres: Design Phase 3 10/08 Page 15 Continuous Improvements Completed DAP – Reduce need for design changes DAP (established footprint) vs preliminary plans Established Liaison Program Alternative contracting methods and incentives are used frequently to save time –CMGC, D/B, incentive/disincentive specification

OTC Pres: Design Phase 3 10/08 Page 16 Continuous Improvements Completed New roles and responsibilities –Leadership Teams –Better, timelier communications: Operational notices, technical bulletins, documented procedures –Decentralization (SASC) –Cradle-to-grave management –Focus on performance measures –OTIA III –Alternative Delivery business models –Judicious selection of technology improvements.

OTC Pres: Design Phase 3 10/08 Page 17 Continuous Improvements Future RWDMS acquisition process streamlining (Phase II) 9 State Peer Exchange - ROW acquisition & relocation incentive payments Public involvement: Systematic Development of Informed Consent, ACTs

OTC Pres: Design Phase 3 10/08 Page 18 Process Challenges Unforeseen issues, scope changes, new information resulting in design modification DAP “completeness” issues FHWA now requires Environmental Approval prior to ROW and Final Design for Class 2 projects Regulatory expectations are subject to change

OTC Pres: Design Phase 3 10/08 Page 19 Discussion