August 12, 2013. Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.

Slides:



Advertisements
Similar presentations
Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
Advertisements

July 01, Shutdown Machine Status:  NTF Treatments and Dosimetry as scheduled  Proton Source Commissioning and Studies RFQ Injector.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
INTRODUCTION  RECYCLER BPM – Original system not adequate to measure beam position precisely. It is being upgraded to meet the required physics precision.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
Recycler Status and Plans Shekhar Mishra MID/Beams Division Fermilab AAC Review 2/4/03 Introduction to the Recycler Ring Recycler Improvements and status.
F Antiproton Source Apertures Steve Werkema DOE Tevatron Operations Review March 22, 2006.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Ff NO A Accelerator Upgrades: Status Phil Adamson Fermilab
Proton Study Meeting 4/19/05 Eric Prebys 1 Proton Plan Stage I Eric Prebys.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Main Injector Lambertson Aperture Scans David Johnson and Ming-Jen Yang March 17, 2006.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
S. Pordes - to part of CD 09/10/031 Introduction to some Beams Division jargon in some order…see how far we get:
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
AP2 Line & Debuncher Studies Status Keith Gollwitzer Antiproton Source January 9, 2006 Many people involved with providing the hardware and software that.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Accelerator Status and Plans
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
Recent Work Towards Increasing the AP2 & Debuncher Aperture – Keith Gollwitzer – May 9, Recent Work Towards Increasing the AP2 & Debuncher Aperture.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003.
Doug Michael Sep. 16, GeV protons 1.9 second cycle time 4x10 13 protons/pulse 0.4 MW! Single turn extraction (10  s) 4x10 20 protons/year 700.
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
Run II PMG 1/19/06 Pushpa Bhat 1 Run II Upgrades Status January 2006 Pushpa Bhat.
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
2/17/2016 Recycler -Gattuso Recycler Shut Down Status  Flying Wire Status  Wire Vacuum Certified  Tunnel Bake Prep status Disconnection of BPM, Correctors,
What we have now – the Pbar source 1 1/23/2013 J. Morgan.
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
All Experimenters’ Meeting September 23, Accelerator Operation Summary Calendar Week # 38 NuMI Weekly Integrated Intensity 4.57 E18 protons BNB.
F All Experimenters' Mtg - 6 Jan 03 Week in Review: 12/30/02 –1/05/03 Ron Moore – FNAL Store Summary – Best week! > 7 pb -1 Machine Studies/Maintenance.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
Run II Status Keith Gollwitzer Temple Review July 1, 2003.
All Experimenters’ Meeting November 25, 2013 Photo by Martin Murphy.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
All Experimenters’ Meeting November 4, Accelerator Operation Summary Calendar Week # 44 NuMI Weekly Integrated Intensity 5.97 E18 protons BNB.
July 29, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.
MI/RR Operation Status Ioanis Kourbanis August 21, 2014.
March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th :00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
Recycler Pbar Transfer -Gattuso 1 Recycler weekly Summary This presentation will probably involve audience discussion, which will create action items.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Maximum Credible Beam Loss in the Main Injector D. Capista January 26, 2012.
MI/RR Status January 3, 2014 D. Capista. MI Preformance.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Primary Design Parameters July 13,2001 S. Childress Page 1 NuMI Besides design specifications driven by physics and Main Injector beam parameters, significant.
Presentation transcript:

August 12, 2013

Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet moves  Main Injector Startup and Tuning ○ Extracted beam to NuMI beamline Low Intensity on hadron monitors ○ Recycler corrector ramp testing ○ First round of Quad moves complete Recycler lambertson installed MI30 vacuum ○ Work continues to resolve the high gas load at MI308

MI Startup Activities  Turn on power supplies and establish ramps  Establish 8 Gev beam  Match MI8 line lattice with IPM  Tune abort Gev  Establish 120 Gev beam  Smooth orbits up the ramp  Tune abort 120 Gev  High field Orbit smoothing (quad moves) (Have data for 1 st )  Requires tunnel access (2x8 hrs)  Calibrate tune table  MI8 line lattice matching (1 st of 2 passes complete)  Dedicated beam study  Extraction line tune up (NuMI) (Initial setup)  Tune up for operation  Deliver low intensity beam to NuMI beam line for target scans  Estimated to take an additional week after MI is tuned up for operations

Kautz Road SubStation  Status T87 and T85 have new surge arrestors MI backfed from Master SubStation ○ Using Feeder 45 for MI conventional power which is normally T85 on KRS We need to schedule a 20 minute MI conventional power outage to remove the backfeed from Master SubStation.

Power Failures  Feeder 46B Wednesday, July Impact – Possible F0 ventilation system Fault located between P71 & F4 Further isolation and repairs necessary

Power Outages  PS3 Power Outage Oil Switch Replacement Impacts PS3, PW5, & PC3 Run on generator for ~1 week Connect generator Monday, July – 1000 Disconnect generator Friday, August COMPLETE

August 2013

Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations ScheduleOperations Schedule Direct link to schedule -

MI Startup Activities  Turn on power supplies and establish ramps  Establish 8 Gev beam  Match MI8 line lattice with IPM  Tune abort Gev  Establish 120 Gev beam  Smooth orbits up the ramp  Tune abort 120 Gev  High field Orbit smoothing (quad moves) (Have data for 1 st )  Requires tunnel access (2x8 hrs)  Calibrate tune table  MI8 line lattice matching (1 st of 2 passes complete)  Dedicated beam study  Extraction line tune up (NuMI) (Initial setup)  Tune up for operation  Deliver low intensity beam to NuMI beam line for target scans  Estimated to take an additional week after MI is tuned up for operations

 We have removed all of the antiproton equipment, which comes to over 1,400 feet of beamline components. o Electron cooling removal o Stochastic Cooling tanks removal from the 200 and 100 tunnel locations o Decommissioned the two Recycler Pbar injection and extraction lines (~1,000 ft. of beam line components). o The A150 Beam line was decommissioned (~800 ft. of beam line)  More than ~1.3 Million feet of cable have been pulled to support the new transfer lines and instrumentation upgrades. o ~500,000 feet was a complete replacement of the Recycler BPM system o ~700,000 feet of new cabling for instrument cabling o IPM’s, Toroid's, DCCT’s, Multiwires, Schottkies, o ~10,000 ft. of RF cabling o ~10,000 ft. of 500 MCM cable o ~12,000 ft. of 350 MCM cable o ~25,000 ft. of correction element cables o ~6,000 ft. of radiation damage cable o ~ 25,000 ft. of kicker system cables  We have installed a new transfer lines; a new Injection line into the Recycler and a new transfer line out of the Recycler Ring into the Main Injector o New injection line spans from the MI-8 line Q848 location to the Recycler Q104 location o New extraction line spans from Recycler Q230 to Q308 in the MI

 Approximately 590 tons of material has been moved o ~ 40 Tons of lead blankets were installed to reduce the radiation levels to reasonable levels such that work can be completed (~25 tons in the MI30 straight section, ~5 tons in the new injection line and ~10 tons in various other locations around the ring. o Installed 3 shielding walls ( 2 for MI-31 stub and 1 at the 304 tunnel location ~ 20 tons each) o ~490 Tons of magnets moved o 3 ILAM we moved/relocated o 6 3Q120 magnets were removed from the A150 line reworked and reinstalled in the NuMI beam line to replace existing magnets o 1 MI wide aperture Quad was relocated o 1 new Wide aperture C Magnet was installed in the MI abort line o ~40 20 inch Quads were removed from the RR30 Cooling insert o 3 ADCW were installed ( main vertical bend Magnets) o Entire Ecool Cooling section and return line were removed o inch Quads were installed in the RR 30 section o inch Quads were installed in the new RR extraction line o inch Quads were relocated/installed in the RR injection line o Removed/installed/relocated a total of 14 cavities o 2 old RR RF cavities/6 MI coalescing cavity/ 2 MI studies cavities/ 2 new MI RF cavities and 2 new RR cavities o ~30 tons of stands and misc. parts/components were removed and or installed

 Keeping true the Recycler name, we are reusing ~70 percent of the instrumentation, ~30 percent of the vacuum components ~85 percent of the magnets  A completely new 53 MHz RF cavity system was installed into the Recycler o 2 New RF cavities were installed a place holder for a third o Relocated and repurposed the 3 existing Recycler wideband RF cavities into a damper system.  A complete rework of the Recycler Abort system to allow full turn proton abort along with gap clearing.  5 Gap clearing kicker and 2 new Full turn kickers were relocated from the Main Injector to the Recycler  The RR30 straight section was rework from a cooling lattice back to a standard FODO lattice  ~45 Recycler 20 inch quads were removed  ~900 feet of beam pipe was removed and reworked for the new Lattice configuration  New insert was prepped for 2.5 MHz RF cavity system to be installed in the Recycler region.  Relocated radiation sensitive equipment from the MI/RR 30 straight section to minimize future radiation dose to equipment and Technicians.  MI and RR Coasting Beam safety system  MI and RR DCCT’s  RR schotkies  Installed 2 new 53 MHz in the MI  Relocated 4 RF cavities to make room