The review held at CERN, 10 – 11 Nov. 2015

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

All experimenters meeting – July 7, 2014 LHC Crab Cavity Overview Tom Nicol – Fermilab All Experimenter’s Meeting July 7, It’s a group effort –
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
Stimulating a discussion on cavity performance metrics.
Cryomodule Concept for the ODU RF Dipole Crab Cavity Tom Nicol* - Fermilab December 10, 2013 * With lots of help from HyeKyoung, Tom J, Shrikant, Ofelia,
H IGH L UMINOSITY LHC WP1 - CERN S AFETY R EQUIREMENTS Stefan Roesler - Phillip Santos Silva – Ralf Trant EDMS# HSE Unit April 2011.
Ofelia Capatina on behalf of the CERN specification team
SPL cryo-module conceptual design review Cavity, helium vessel and tuner assembly N. Valverde, G. Arnau, S. Atieh, I. Aviles, O. Capatina, M. Esposito,
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
Ralph Assmann What Do We Want To Measure (in 2009) R. Assmann S. Redaelli, V. Previtali CERN/BE discussed with W. Scandale CERN/EN26/3/2009CC09  See also.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
ML Planning for ILC08 First Pass + SCRF agenda Chris Adolphsen Hitoshi Hayano.
8 th Meeting of the ATF TB/SGC 11 June Hardware Status Fast Kicker – FID pulsers have had a reliability problem: this appears to have been solved.
Workshop Objectives & Highlights from Daresbury Meeting Erk Jensen, CERN.
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
FNAL efforts on LHC Crab Cavity R&D (Proposals for R&D sub-tasks, resources and schedule) Nikolay Solyak.
Spoke test in vertical cryostat IPNO-UU Meeting on spoke test program, 2 nd -3 st October 2013 IPNO Team.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The integration of 420 m detectors into the LHC
Project Breakdown Structure Tracing changes to our different baselines I. Bejar Alonso and Project Office TCC – 14 th January 2016.
RF power couplers vacuum issues J.M. Jimenez Vacuum, Surfaces and Coatings Group (TE-VSC)
LHC Cryostat evaluation Nikolay Solyak Thanks Rama Calaga, Tom Peterson, Slava Yakovlev, Ivan Gonin C11 workshop. FNAL, Oct 27-28, 2008.
Summary of SCRF Meeting Fermilab, April 21-25, 2008 April 25, 2008 General Summary and Further Plan: 4/21: Cavity: Gradient R&D, performance, diagnostics.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
TE-CRG Activities D. Delikaris, TE-CRG.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
WP 4: Crab Cavity Ed Ciapala, Erk Jensen BE-RF, CERN HL-LHC Meeting, CERN, 20 Oct 2010.
CDR for the ESS Linac Magnets for LWUs (pulsed quadrupoles and DC correctors) Closeout May 4, 2016 J.G. Weisend II, Chairman CDR.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
Crab Cavities for the HL-LHC Project Definition and Design Study E. Ciapala, E. Jensen, J. Tuckmantel (CERN) R. Calaga (BNL) US-LARP CM15, November 2010,
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Global Collaborations Towards LHC Crab Cavity J. P. Koutchouk Thanks to Rama Calaga and Rogelio Tomas Crab Cavity Validity Requirement Workshop August.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
LARP Crab Cavities Cryomodule Integration Meeting Final Notes A.Ratti LBNL.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Crab Cavity Technical Coordination meeting:
CERN – Zanon discussions
Preparation of functional/engineering specifications for HL-LHC
Cold mass design, assembly plans and QA/QC at CERN
Plans towards CC in the LHC a US – centric perspective
SPS Crab Cavity Test Stand: Safety review summary
HL-LHC IT STRING and Series test of SC link
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
SPS cryogenic proximity equipment and SM18 validation
Update on HW commissioning
HL-LHC-UK: UK contribution to HL-LHC Crab Cavities and evolution
International Review of the Crab Cavity Performance for HL-LHC Close-out Executive Summary HL-LHC CC Review Panel Mark Champion (ORNL), Mike Kelly (ANL),
Hollow e- lens, Cryogenic aspects
International Review of the Conceptual Design of the Cold Powering system for the HL-LHC Superconducting Magnets J.Ph. Tock
ESS RF Development at Uppsala University
Superconducting RF Crab Cavities
UK RFD Pre-Series cryomodule
SRF Section Cuvée 2014.
LHC-CC09 workshop LHC Crab Cavity Workshop, jointly organized by CERN, EuCARD-ACCNET, US-LARP, KEK, & Daresbury Lab/Cockcroft Institute CERN, September.
Crab Crossing Named #1 common technical risk (p. 6 of the report)
Presentation transcript:

The review held at CERN, 10 – 11 Nov. 2015 Report of the HL-LHC WP4 (Crab Cavities): SPS Cryo-module Engineering Review Reviewers: Pierre Bosland, Philippe Lebrun, Vittorio Parma, Leonardo Ristori, and Akira Yamamoto (Chair) The review held at CERN, 10 – 11 Nov. 2015

Boundary Conditions The installation of Crab Cavities (CC) is planned during Long Shutdown 3 (LS3), scheduled for beginning 2024-25. Due to lack of experience of CC performance in hadron machines, a beam test of CCs is planned in the SPS before LS2 (by end of 2018) where one or more Cryomodules and as many different types of CC as possible will be installed in the SPS beam and tested for performance. A significant effort towards the SPS tests have resulted in a detailed design of the cryomodules for the double quarter wave (DQW) and the RF dipole (RFD).

Preparation & Installation General plans Courtesy: R. Calaga, O.Capatina 2 cryomodules for SPS tests - test 1 CM in 2018, the 2nd after LS2 1 CM w/ 2 identical cavities (type «vertical» - DQW) 1 CM w/ 2 identical cavities (type «horizontal» - RFD) 2 cryomodules pre-series for LHC (one of each type) 16 cryomodules for installation in LHC (8 of each type) + spares post C&S review: - all 32 dressed cavities to be produced - only 8 CMs foreseen for installation in LS3 with subsequent cryomodules in the following technical stops - this also allows schedule mitigation and flexibility to accommodate for crossing plane changes SPS test prototype preparation tests LHC pre-series Fabrication & tests Preparation & Installation LHC series production Run 2 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 LS2 LS3 EYETS Run 3 Run 4 YETS today

Courtesy: R. Calaga, O.Capatina ATLAS LHC Point 1 (vertical) 4 cavities / IP side/ beam to be installed during LS3 CMS LHC Point 5 (horizontal) SPS Test Prototype Module before LS2 SM18 Area Cavity cold testing, clean room facilities & cryomodule qualification HL-LHC WP4 (Crab Cavities): SPS Cryo-module Engineering Review, 10/11/2015

General Charges to the Review This review is charged to comprehensively review and address any outstanding issues related to the SPS cryomodules components design: vacuum vessel, thermal and magnetic shielding, thermal insulation, cryogenic distribution, internal support structure, RF internal lines, alignment adjustment and monitoring; as well as Physical and functional interfaces: to the RF cavities and helium vessels, cryogenic and vacuum systems. Some important elements of the cryomodule are being prototyped to understand the performance of the design choices (He-vessel, tuner etc..). The maturity of the technical status of the cryomodule and its readiness towards an installation in the technical stop of 2017-18 should be assessed

SPS Cryomodule: with 2 identical cavities installed 08.09.2011 Courtesy: R. Calaga, O.Capatina SPS Cryomodule: with 2 identical cavities installed Horizontal Crabbing RF Dipole (CMS) Vertical Crabbing Double Quarter Wave (ATLAS) Design per SPS, lo stesso concetto da tenere per LHC. DQW: vertical kick HL-LHC WP4 (Crab Cavities): SPS Cryo-module Engineering Review, 10/11/2015

Specific Charges Specific questions to be addressed by the review: Does the design meet all the functional requirements of such a cryomodule? Have all important issues been covered by the project team ? Have all the design aspects been studied sufficiently in detail in preparation for manufacturing? Are-there particular area where extra design effort is needed? Are there risks associated with the design that could or must be removed or mitigated at this stage? Is the proposed schedule related to SPS tests realistic? Are the general plans and criteria for cryomodule development past the SPS application and into the HL-LHC period (post-2024) correctly defined? Is there any particular area that should be studied in more detail at this stage

Reports given, 10 Nov. (1) a1 Introduction and overview of the CM Ofelia CAPATINA et al. a2 He vessel design, prototyping and tests Carlo ZANONI a3 Cold magnetic-shielding & Proposal for … Niklas TEMPLETON a4 Tuning system Kurt ARTOOS a5 HOM couplers Marco GARLASCHE a6 Fundamental power coupler and RF … Eric MONTESINOS a7 Support system of the dressed cavity Thomas JONES a8 Alignment and position monitoring system Mateusz SOSIN

Reports given, 10 Nov. (2/2) p1 Cryogenics and cryolines Krzysztof BRODZINSKI p2 Thermal and outer magnetic shields Niklas TEMPLETON P3 Thermal budget and heat loads Federico CARRA p4 Vacuum vessel Norbert KUDER et al. p5 Cryostating Pierre MINGINETTE p6 Integration in SM18 bunker tests Alick MACPHERSON p7 Integration in SPS Giovanna VANDONI

Reports given in addition, 11 Nov. Requirements/Goal for CC system at LHC Requirement/Goal for CC test at SPS Min. Success Criteria for CC test at SPS Rama Calaga A2 General Plan (schedule) to reach the SPS Test Ofelia CAPATINA et al.

Executive Summary (1/2) The review team wishes to thank all the participants for their well-prepared oral reports and comprehensive documents received soon after the review meeting. We have been impressed with the crab cavity (CC) and cryomodule (CCCM) team activities for their engineering design work and for the SPS test preparation.   We congratulate the team on the progress and current design achieved, and recognize the excellent work. The engineering design presented is sound and the current design concept should be kept. We have understood that the idea to accommodate two complementary CC designs of Double Quarter Wave (DQW) and RF Dipole (RFD) into those CCCMs so as to provide common interfaces to RF power and cryogenic system layout in the accelerator tunnel.

Executive Summary (2/2) On the other hand, we are concerned with that the general plan/schedule is very challenging to realize the SPS beam test within the LHC Run-2 period before the end of 2018. Installation of a new dedicated cryogenic system for the SPS test planned in the technical stop of 2016-17 (and CM in a year later) would be the most critical issue, and this must be well managed.   We recommend the basic CCCM design to be kept as achieved, and encourage to establish the preparation plan to be robust enough to ensure that the SPS test stay to be supported, and recommend to provide backup plans with the minimum goal to be clear enough to demonstrate the viability.

Recommendations (1/6) Charge 1: Does the design meet all the functional requirements of such a cryomodules? Clarify “the minimum functional requirement/goal” for the SPS CC test to be prepared in case of difficulties to be met in the course to the SPS test.

Documents given to the review team responding to its requests “Functional Specifications of the LHC Prototype Crab Cavity System” P. Baudrenghien et al., CERN-ACC-NOTE-2013-003, Feb., 2013 “Compact Crab Cavity Cryomodule” K. Srtoos et a., CERN-ACC-2015-0130, Oct. 2015. “Conceptual specification: Crab Cavities”, LHC-EQCOD-ES-xxxx, Draft. “Dressed bulk niobium radio-frequency crab cavities”, LHC-ACFDC-ES-0001, June 2014. “Conceptual specification: SPS Crab cavity validation run installation”, LHC-EQCOD-EX-xxxx, Draft June 2014. “Crab cavities prototype cryomodule, a proposal for compliance with CERN safety requirements”, EDMS No. 1494776, August 2015.     All information is online available: https://indico.cern.ch/event/435319/

Recommendations (2/6) Charge 2: Have all the important issues been covered by the project team? A decision on the implantation/location of the refrigerator cold box (at ground level or in tunnel) needs to be urgently taken. The critical components such as FPCs and tuners shall be individually reviewed in timely manner, if they have not already been done.

SPS: operation Courtesy: R. Calaga, O.Capatina this is illustration only as the location recently changed and integration in the new location is underway – see Giovanna’s talk this after-noon

Recommendations (3/6) Charge 3: Have all the design aspects been studied sufficiently in detail in preparation for manufacturing? Are there particular area where extra design effort is needed? The system integration workflow, including efficient tooling, fixtures, and intermediate tests must be studied in greater detail, especially with regard to preventing contamination of the CC and degrading its performance. Cryogenic-safety and the extreme failure-mode analyses should be performed, considering the specific SPS test environment to be well prepared.,

Recommendations (4/6) Charge 4: Are there risks associate with the design that could or must be removed or mitigated at this stage? We advise the project team to consider reinforcing the stiffness of the supporting system while, at the same time, limiting forces on the FPCs.

Cryomodule Assembly Courtesy: R. Calaga, O.Capatina SPS crab cavity cryomodules components design : vacuum vessel, thermal and magnetic shielding, thermal insulation, cryogenic distribution, internal support structure, RF internal lines, alignment adjustment and monitoring; the physical and functional interfaces to the: RF cavities, HOM couplers and helium vessel, cryogenic and vacuum systems. HL-LHC WP4 (Crab Cavities): SPS Cryo-module Engineering Review, 10/11/2015

Dressed Cavities Courtesy: R. Calaga, O.Capatina Vertocal Crossing 08.09.2011 Courtesy: R. Calaga, O.Capatina Dressed Cavities Vertocal Crossing Double Quarter Wave (ATLAS) Horizontal Crabbing RF Dipole (CMS)

Recommendations (5/6) Charge 5: Is the proposed schedule related to SPS tests realistic? Take fast action, such as ordering cryogenic refrigerator, as well as tracking closely the milestones of the project schedule and working out mitigation paths in case these milestones are not met. Prepare for various scenarios, at least to reach the minimum requirements for the SPS test.

Preparation & Installation General plans Courtesy: R. Calaga, O.Capatina 2 cryomodules for SPS tests - test 1 CM in 2018, the 2nd after LS2 1 CM w/ 2 identical cavities (type «vertical» - DQW) 1 CM w/ 2 identical cavities (type «horizontal» - RFD) 2 cryomodules pre-series for LHC (one of each type) 16 cryomodules for installation in LHC (8 of each type) + spares post C&S review: - all 32 dressed cavities to be produced - only 8 CMs foreseen for installation in LS3 with subsequent cryomodules in the following technical stops - this also allows schedule mitigation and flexibility to accommodate for crossing plane changes Cryogenics installation required,  Challenging CM installation required, SPS test prototype preparation tests LHC pre-series Fabrication & tests Preparation & Installation LHC series production Run 2 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 LS2 LS3 EYETS Run 3 Run 4 YETS today

Recommendations (6/6) Charge 6: Are the general plans and criteria for cryomodule development past the SPS application and into the HL-LHC period (post-2024) correctly defined? Is there any particular area that should be studied in more detail at this stage? Provide clear documents for the general plan, at least for the goal of the CC-CM test at SPS with various scenarios including the minimum requirement to be achieved. Further scope for the HL-LHC period shall be re-visited after certain progress in the SPS test preparation.

Test Program Summary (discussed in the 2nd day) Provided by R. Calaga, Test Program Summary (discussed in the 2nd day) In-situ cryomodule testing in out-of-beam position RF commissioning with low-intensity beam, 1-12 bunches Establish proper RF parameters (operating frequency, amplitude, and phase) Verify that CCs are transparent (cavity counter-phasing and detuning) High intensity single bunch up to 4x72 trains Impact on cavity performance (including transient behavior), impedance, stability & machine protection as a function of beam current; interlocks Verify cavity stability over many hours (relevant for LHC physics fill) Long-term behavior of coasting beams in the SPS with 1-bunch Study the effects of cavity drifts, emittance growth, non-linear effects such as RF multipoles

Minimum Test Program (discussed in the 2nd day) Provided by R. Calaga, Minimum Test Program (discussed in the 2nd day) Vacuum & Cryogenic aspects We depend on NEG coating on either side to keep the pressure The cryo limit will determine the operational field Moving a 3 Ton object with 2K He Inject & capture 1-12 bunches – - Beam properties well known, effect of strong impedance might be visible Cavities always on (5-10% of nominal) to ensure RF feedback Amplitude and phase scan Input/Output power to determine the electrical center + correct crabbing phase and counter-phasing for transparency & re-phasing during collisions Have to test a minimum set of RF controls for LHC operational cycle Measurements with other instruments (HT monitor, BPMS …) We are planning ½ day SPS test program meeting to go through the detailed commissioning and testing in SPS at the end of Nov.

Summary Primary recommendations: Keep the current CM design w/ common interfaces to the associate system, Establish the general preparation and test plan to be robust and reliable in schedule, Specially for the cryogenics system installation in 2016- 2017 (short technical stop), and for workflow of the CM assembly with keeping cleanness and performance. Prepare for backup plans with the minimal goal to be reliable achieved.

Aknowledgments We would thank all CC-CM team members for their much effort for design to reach this stage and for the review to have been successfully made.