Solar Probe Plus FIELDS Team Meeting Management 7/07/2015
Agenda 1. Science (Bale) a. FIELDS Paper 2. Management (Harvey) a. Deliverables b. EM Test Schedule c. ISSUES d. Upcoming Dates 7/17: AEB PWB review 7/28: Post EM Completion Review 3. Systems (Goetz) a. RFAs b. Flight Drawings Status c. Commissioning 4. Mechanical/Thermal - Bill D., David G., Paul Turin, Millan D. a. MEP b. Antennas c. Thermal 5. Electrical Status DCB-RFS, FSW Daughterboard, Alignment Jig AEB, PREAMPs TDS-LNPS, FSW DFB MAG SCM 6. Ground Support - Quinn 7. SOC ( Pulupa )
DELIVERABLES SCHEDULE Updated verification matrix FIELDS2 input for Cmd & Telemetry & Flight Rules FIELDS2 Preliminary Software Test Plan L4 Requirements Update
EM TESTS Main Electronics Antenna Electronics completed all EM tests Antenna EM Thermal Balance continues to slip badly with no reported progress in June. Antenna coatings is an issue
ISSUES Source: SPF_MGMT_026_ISSUES.xlsx
REVIEWS Reviews: SOC CDR - COMPLETE Date: 6/16/15 RFAs Identify Software ReUse Define Pre-Encounter Data Reqs Define Tohban role Identify Major Contingencies Define SSR Management “Post-EM Testing” 28 July 2015 Location: Webex
SCHEDULE MILESTONES Source: SPF_MGMT_021_MILESTONES.xlsx
FM Schedule (iCDR)