TE-CRG Activities D. Delikaris, TE-CRG.

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Cryogenics at CERN (LHC)&Helium Inventory Brief review with emphasis given on cryogen management Americas Workshop on Linear Colliders 2014 Fermilab,
L. Tavian, TE/CRG, Page 2 12 th September 2013 Accelerator Consolidation Workshop L. Tavian, TE-CRG.
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
H. Herzog, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN LARGE SCALE CRYOGENIC.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The cryogenic systems of the ATLAS and CMS detectors Johan Bremer on behalf of TE/CRG 06/06/2013AFF.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Experience from large helium inventory management at CERN ILC Cryogenics and Helium inventory meeting CERN, Wed. 18 th of June 2014 D. Delikaris Technology.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
Service Agreements Emmanuel Tsesmelis CERN / TS-LEA RRB Scrutiny Group 31 August 2006.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
O. Kester, NuSTAR annual meeting, 27/02/2013
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 April 27th 20101K. Foraz - Machine Advisory Committee.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Industrial contributions to the maintenance of CERN.
TE-CRG Activities A. Perin, on behalf on the Cryogenics Group.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
OMP: Major maintenance policy of the LHC Accelerator and Detectors Motors & Compressor for the EYETS, YETS & LS2 period.
CONSOLIDATION day in view of HL-LHC Cryogenic aspects
Crab cavities Cryogenics progress for the SPS
IT-4189 Supply and installation of a cryogenic distribution system
BA6 – crab cavity activities in EYETS
Update of cryogenic activities
SPS cryogenic proximity equipment and SM18 validation
The LHC - Status Is COLD Is almost fully commissioned
CRYOGENICS – strategy, unavailability root causes and limitations
Preparation of the activities for the LHC Long Shutdown 2
Keeping LHC cold during LS periods Preliminary proposal
Hollow e- lens, Cryogenic aspects
Activities of the ME section during LS2 ( )
Overview & baseline of LS2 and roadmap for CRG
Status of the cryogenic system for B180
Mathew C. Wright January 26, 2009
Overarching Commissioning Plan
Operator Training Requirements
as a prototype for Super c-tau factory
Review Bloc 4 and SM18 facilities and upgrade
Presentation transcript:

TE-CRG Activities D. Delikaris, TE-CRG

Outline 1.General frame: cryogenic installations under operation, maintenance, consolidations, projects 2.Main activities definition for maintenance and consolidations 3.LS2 baseline 4.Schedule, resources & budget for maintenance, consolidations and projects 5.Conclusions 2D. Delikaris,TE-CRG

Important milestone for the CRG Group: New Operation & Maintenance contract to be implemented by 1 st of July 2016, including: Maintenance (preventive, corrective, predictive) for all cryogenic installations at CERN Full delegation-results oriented operation for non-LHC cryogenics (thus allowing staff resources to be made available for Projects) Tasks oriented operation for LHC accelerator & detectors under CERN’s supervision General frame: cryogenic installations under operation, maintenance, consolidations, projects HL-LHC SM18 upgrade B.163 upgrade B.180; FAIR Neutrino platform Physics LHC accelerator LHC detectors SPS-North Area HIE-Isolde Tests facilities SM18 B.163 B.165 central liquefier services (including AD supply) Operation, Maintenance, ConsolidationsProjects 3D. Delikaris,TE-CRG

Main activities definition; Maintenance, consolidations YETS: 3 days to 1 week maximum stop per installation for basic preventive & scheduled corrective maintenance (two teams of each Mechanics – Electricity/Instrumentation in parallel) EYETS: Equivalent to YETS; extended to additional Safety Valves revision Periodicity recently changed (SSI-M-2-3 Specific Safety Instruction for safety accessories) LS2: Dominated by the major overhauling of helium compressors & associated electrical motors, cold compressors cartridges (12 months) Performing the full preventive maintenance plan (based on LS1 experience with less instrumentation activities) & scheduled corrective interventions (earlier diagnostic required for adequate scheduling) Consolidations (according to the existing list, slide 10) LHC accelerator & detectors 4D. Delikaris,TE-CRG

YETS LHC accelerator; helium management Baseline: beam stop Mon.14/12/2015 Helium inventory: 90% remains in the magnets (IT, DFB, 20 K) In case of plant stop (cryogenics or utilities) and restart within 12 h: no helium losses Alternative: all 20 K, helium inventory removed to surface; constraint for helium management: beam stop Wed. 09/12/2015 LHC accelerator; specific interventions (Cat. A: Perturbation of Cryo-Maintain or Cat. B: Cryo-only) P8 (Cat. A): two weeks for repair of helium leak to insulation vacuum, cold box K (S81) P4 (Cat. A): two weeks oil pollution check and change of surface activated charcoal adsorber on K (S34) P18/P2: replacement of one electrical motor P8: replacement of one helium compressor 5D. Delikaris,TE-CRG

YETS LHC detectors CMS specific interventions Chemical cleaning of the cold box (underground) in collaboration with VSC group; duration under definition Liquid nitrogen distribution & heat exchanger repair, leak to insulation vacuum of the cold box (underground): 2 weeks (external specialised firm) Primary oil removal system replacement (surface); order in preparation in the frame of an existing supply contract; duration under definition Repair of partially damaged cryogenic valve on top of intermediate cryostat (underground) Dryer commissioning ATLAS specific interventions Dryer commissioning 6D. Delikaris,TE-CRG

LS2 ( ) maintenance forecast based on LS1 experience & Experience gained form LS1 Ideal LS2 baseline for maintenance activities: 12 to 13 months LS2 duration dominated by the Helium Compressors-Motors & Cold Compressors major overhauling to manufacturer’s premises Emptying (LHC acc.), securing helium inventory, leak testing (localising potential damage on QRL bellows and/or DFB gimbals), warming up (3 months) Pressure tests, if any; Sectors cooling down, commissioning 7D. Delikaris,TE-CRG

Major overhauling of helium compressors-motors stations 8D. Delikaris,TE-CRG

Helium Compressors major overhauling forecast (& experience from LS1) Helium Compressors sent for major overhaul during LS1 per manufacturer with average major overhaul period per compressor and total major overhaul period LS2 forecast for helium compressors major overhaul to manufacturer's premises repair LS2 9D. Delikaris,TE-CRG

Maintenance, Consolidations & Spares: schedule, resources and budget 10D. Delikaris,TE-CRG

Projects: schedule, resources and budget HL-LHC SM18-UPG Overall CRG project support to: SM18-UPG ( ) accounts for 27.1 FTE (18.7 MCHF) & HL-LHC ( ) accounts for FTE (94.3 MCHF) 11

HL-LHC, cryogenics general schedule No more sc P7 New LS2 datesNew LS3 dates YETSEYETS LS2 YETS + 11T P2 ? + possible work on some LSS2-LSS8 beam-screens? “spare” P4 + … Cryo for Crab Cav. At SPS New Cryo for RF at P4 Cold Powering sc links New Cryo at P1 and P5 12/7D. Delikaris,TE-CRG

Conclusions (1/2) Cryogenic operation, maintenance & consolidation activities for LHC accelerator and detectors adapted to YETS & EYETS definition and duration Specifically for YETS special attention is given to CMS interventions, in order to fulfil the Collaboration’s requirements and schedule The CRG group has an important milestone by the implementation of a new Operation & Maintenance contract by the 1 st of July 2016, fulfilling two major objectives: To cover all EYETS, YETS and LS2 maintenance activities The full delegation-results oriented operation for non-LHC cryogenics (thus allowing staff resources to be made available for Projects) 13D. Delikaris,TE-CRG

14 The major overhauling of the cryogenic equipment to manufacturer’s premises is well adapted to the new LS2 duration and experience gained from LS1 performance can be applied During the warming-up phase, in case of discovery of mechanical damages to QRL or DFB components a dedicated team has to be allocated (in collaboration with VSC and MME groups) In parallel with the cryogenic operation activities CERN wide, during , a strong CRG support to projects is on schedule, in particular for the SM18 upgrade and HL-LHC activities Conclusions (2/2)

Thank you for your attention