Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG.

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

Cryomodule Helium Volumes Tom Peterson, Fermilab AWLC14 13 May 2014.
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Cryogenic Experts Meeting (19 ~ ) Helium distribution system for Super-FRS dipoles and multiplets MT/FAIR – Cryogenics and Magnets Y. Xiang,
Design pressure issues of Super-FRS dipole CrYogenic Department in Common System (CSCY), GSI, Darmstadt Yu Xiang, Hans Mueller* * Primay Beam Magnet Technology.
1 Update on Focus Coil Design and Configuration M. A. Green, G. Barr, W. Lau, R. S. Senanayake, and S. Q. Yang University of Oxford Department of Physics.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
MICE Hydrogen System Design Tom Bradshaw Iouri Ivaniouchenkov Elwyn Baynham Columbia Meeting June 2003.
Current status Arkadiy Klebaner November 21, 2012
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
21/01/02 - ECAL Cooling - Arnaud Hormiere ST/CV 1 Development of ECAL COOLING PLANT Application to a Super Module.
ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.
September 19/20, 2007 SIS 100 Magnet cooling and cryogenic distribution.
Cryomodule Helium Vessel Pressure -- a Few Additional Comments Tom Peterson 18 November 2007.
Workshop on cryogenic and vacuum sectorisations of the SPL CERN, 9 th -10 th November 2009 Workshop Organisation and Goals Vittorio Parma TE-MSC.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
Beijing ILC Workshop Global Design Effort 1 High-Gradient Module Test Lutz Lilje.
5 K Shield Study of STF Cryomodule Norihito Ohuchi, Norio Higashi KEK Xu QingJin IHEP 2008/3/3-61Sendai-GDE-Meeting.
Road map of the workshop Machine availability: – “work-horse” in the injection chain – 100% availability not viable,.What is achievable? And at which cost?
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
a magnetic refrigeration stage
Thomas Jefferson National Accelerator Facility Page 1 SPL Cryogenic and vacuum sectorisations 9-10 November, 2009 Joe Preble Workshop on cryogenic and.
C.KotnigFCC Design Meeting FCC Beam Screen cooling Claudio Kotnig.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
CRYOGENICS FOR MLC Cryogenic Principle of the Module Eric Smith External Review of MLC October 03, October 2012Cryogenics for MLC1.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
SLHC WG3 (Cryomodule) summary & plan with recommendation to the CB V.Parma, CERN TE-MSC P. DUTHIL, IN2P3-CNRS 3rd SPL collaboration meeting, CERN
Dimensions, pressures and temperatures of cryogenic circuits for the SPL U. Wagner TE-CRG.
The integration of 420 m detectors into the LHC
LHC Cryostat evaluation Nikolay Solyak Thanks Rama Calaga, Tom Peterson, Slava Yakovlev, Ivan Gonin C11 workshop. FNAL, Oct 27-28, 2008.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
5 K Shield Study of STF Cryomodule (up-dated) Norihito Ohuchi KEK 2008/4/21-251FNAL-SCRF-Meeting.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
Comments from the SNS Cryostat Design Review February 2010 Tom Peterson, Fermilab 15 February 2010.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
Low Beta Cryomodule Development at Fermilab Tom Nicol March 2, 2011.
Cryogenics for SuperB IR Magnets J. G. Weisend II SLAC National Accelerator Lab.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Integration Open Questions (some urgent questions only … ) ◊Position of the couplers ? ◊Will there be a separate cryoline? ◊Architecture of the RF power:
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
H. Hayano(KEK), B. Petersen(DESY), T. Peterson(FNAL),
R. van Weelderen and U. Wagner CERN
Final Design Cryogenic and mechanical configurations
2016/12/6 Yasuhiro R&D status of a gas-compressor based 2-phase CO2 cooling system for FPCCD vertex detector 2016/12/6 Yasuhiro Sugimoto.
SPL RF coupler: integration aspects
Cryogenic behavior of the cryogenic system
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Project X: Cryogenic Segmentation Issues
ILC Cryogenics -- Technical Design Report Planning
Cryostats Some ideas for the new Q1 to Q3 Hi-Lumi WP3 meeting
Cryogenic behavior of the magnet
Presentation transcript:

Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG

Topics  Introducing remarks  General considerations  Basic parameters  Basic considerations  Different cooling schemes (seven in total)  Cooling scheme options  Advantages / Drawbacks  Topics to be investigated 6/11/20092SPL Workshop NOv. 2009

Introduction  The SPL is presently in the phase of a Design Study.  CERN has no experience operating pulsed SC cavities at 2.0K.  We try to define a “baseline” design for the cryogenic distribution.  However this design will look like, we cannot consider this as “the Solution”; it may still be subject changes.  None of the proposals in this presentation is considered to represent the desired baseline. 6/11/2009SPL Workshop NOv General note

Introduction  Availability is a key requirement for all accelerators  The SPL is “second-in-line” of an injector chain  Availability even more important  Operation should be considered under degraded conditions like: Leaks Faulty components High local heat loads 6/11/2009SPL Workshop NOv Availability

Basic parameters  The following is considered as decided:  Cooling of the cavities with helium II at ~ 2.0 K  Cavities inside the saturated bath  To profit from low  p and good p-stability  (Not cooled by sub-cooled pressurized helium)  Anything else may be discussed / changed 6/11/2009SPL Workshop NOv Assumptions that are considered as decided

Basic parameters 6/11/2009SPL Workshop NOv Capacities The choice of the cryogenic distribution may influence the static heat load only !

Basic parameters LineTemperaturePressureDesign Pressure Header A2.2 K0.3 MPa2.5 MPa Header B2.0 K3.1 kPa0.6 MPa Header C5.0 K0.55 MPa2.5 MPa Header D8.0 K0.50 MPa2.5 MPa Header E50 K1.8 MPa2.5 MPa Header F75 K1.7 MPa2.5 MPa 6/11/2009SPL Workshop NOv Pressures and temperatures These values are fixed The rest is for “orientation” only and may be modified

Basic Considerations  The distribution scheme needs to satisfy requirements for:  Nominal operation  Cool-down, warm-up and purge  Operation under degraded conditions  Diagnosis  Safety equipment 6/11/2009SPL Workshop NOv Distribution scheme requirements Considered Not yet considered To be defined / discussed

Basic Schemes 6/11/2009SPL Workshop NOv Single Cavity Cooling LP SPLHP SPL Diameter “x” [mm]4080 Thermal shield and coupler cooling in “series” He II cooling Coupler cooling Thermal shield cooling Cool-down / Warm-up Purge

Basic Schemes 6/11/2009SPL Workshop NOv Single Cavity Cooling LP SPLHP SPL Diameter “x” [mm]4080 Thermal shield and coupler cooling in “parallel” He II cooling Coupler cooling Thermal shield cooling Cool-down / Warm-up Purge

Basic Schemes  Advantages  Less equipment  Simple operation  Disadvantages  No isolation of single elements in degraded conditions  “Last-in-line” always on higher limit temperature  Long response time for control  Advantages  Isolation of single elements possible  Little temperature spread  Short response for control  Disadvantages  More equipment  More control effort 6/11/2009SPL Workshop NOv “series” versus “parallel” cooling Series coolingParallel Cooling List not necessarily exhaustive

Module Schemes 6/11/2009 SPL Workshop NOv Scheme no 1: “Single cavity cooling” LP SPLHP SPL Diameter “x” [mm] %

Module Schemes  Simply a combination of single cavity cooling loops  Liquid HeII: individual per cavity  Coupler: in series or parallel for several cavities  Thermal shield:in series or parallel for several cavities  WU / CD:individual per cavity  Equipment intensive  Feasibility seems guaranteed 6/11/2009SPL Workshop NOv Comments on scheme no 1

Module Schemes 6/11/2009 SPL Workshop NOv Scheme no 2: “Common bath cooling” LP SPLHP SPL Low  High  Low  High  Diameter “x” [mm] %

Module Schemes  Combination of several cavities in one bath  Liquid HeII: one loop per bath  Coupler: in series or parallel for one or several baths  Thermal shield:in series or parallel for one or several baths  WU / CD: one loop per bath  Low amount of equipment needed  Feasibility seems possible  Cooling by conduction in the bath requires very big channel diameters  Could be feasible for LP version with 3 / 4 cavities per bath 6/11/2009SPL Workshop NOv Comments on scheme no 2

Module Schemes 6/11/2009 SPL Workshop NOv Scheme no 3: “ILC-like” LP SPLHP SPL Diameter “x” [mm] %

Module Schemes  One cavity per bath with common 2-phase header  Liquid HeII: one loop per group of cavities  Coupler: in series or grouped for several cavities  Thermal shield:in series or grouped for several cavities  WU / CD: one loop per group of cavities  Low amount of equipment needed  Feasibility of the WU/ CD questionable  The combination of several 2-phase volumes seems dangerous  The equal distribution of flow for CD (less for WU) seems difficult to guarantee  He II loop should be thermo-hydraulically validated 6/11/2009SPL Workshop NOv Comments on scheme no 3

Module Schemes 6/11/2009 SPL Workshop NOv Scheme no 4 : “ILC-like SPL version A” LP SPLHP SPL Diameter “x” [mm] %

Module Schemes  One cavity per bath with common 2-phase header  Liquid HeII: one loop per group of cavities  Coupler: in series or grouped for several cavities  Thermal shield:in series or grouped for several cavities  WU / CD:one loop per cavity  High amount of WU/ CD valves  Feasibility seems ok  He II loop should be thermo-hydraulically validated 6/11/2009SPL Workshop NOv Comments on scheme no 4

Module Schemes 6/11/2009 SPL Workshop NOv Scheme no 5 : “ILC-like SPL version B” LP SPLHP SPL Diameter “x” [mm] %

Module Schemes  One cavity per bath with common 2-phase header  Liquid He II: as ILC-like SPL version “A”  Coupler: as ILC-like SPL version “A”  Thermal shield:as ILC-like SPL version “A”  WU / CD:one loop per group  Low amount of equipment  Feasibility of WU /CD with contact cooled liquid helium tank to be investigated  He II loop should be thermo-hydraulically validated 6/11/2009SPL Workshop NOv Comments on scheme no 5

Module Schemes 6/11/2009 SPL Workshop NOv Scheme no 6 : “ILC like SPL version “A” with separate cryogenic feeder line” LP SPLHP SPL Diameter “x” [mm] %

Module Schemes  One cavity per bath with common 2-phase header  Liquid He II: as ILC-like SPL version “A” (or “B”)  Coupler: “parallel” cooling  Thermal shield:“parallel” cooling  WU / CD: as ILC-like SPL version “A” (or “B”)  High amount of equipment  Feasibility as for ILC-like SPL version “A” (or “B”)  All cooling loops of a group of cavities can be completely isolated  Independent WU/CD not possible 6/11/2009SPL Workshop NOv Comments on scheme no 6

Module Schemes 6/11/2009 SPL Workshop NOv Scheme no 7 : “ILC like SPL version “A” with separate cryogenic line equipped for independent cool-down, warm-up and purge” 1.7 %

Module Schemes  One cavity per bath with common 2-phase header  Liquid He II: as ILC-like SPL version “A” (or “B”)  Coupler: “parallel” cooling  Thermal shield:“parallel” cooling  WU / CD: as ILC-like SPL version “A” (or “B”)  Very high amount of equipment  Feasibility as for ILC-like SPL version “A” (or “B”)  All cooling loops of a group of cavities can be completely isolated  Independent WU/CD and purge possible 6/11/2009SPL Workshop NOv Comments on scheme no 7

Separate cryogenic line  Advantages  Less complexity for the main cryostat  Potential to completely isolate “faulty” modules  Disadvantages  Requires more tunnel space  Higher static heat load  Cost aspect  Not easy to identify separate line most probably more expensive  More complex cryostat and installation vs. cryostat plus line, two installations and more tunnel space 6/11/2009SPL Workshop NOv Advantages / Disadvantages

Single Module WU / CD Option 1: WU of complete machine -> exchange / repair -> CD complete machine  All machine warm –Possible with schemes 1 to 7 Option 2: WU distribution headers & concerned loops -> exchange / repair-> CD distribution headers & concerned loops  No active cooling for rest of machine –Possible with scheme 1 to 7 but increased radiation load for schemes 1 to 5 -> preferable scheme 6 & 7 Option 3: WU individual module -> exchange / repair -> CD individual module  Active cooling for rest of the machine –Possible only with scheme 7 6/11/2009SPL Workshop NOv Procedure options for exchanges / repairs

Open Topics  Ambient-temperature equipment  What can be at ambient, what must be at ambient?  Magnets cooling  If possible at ambient, why operate lower?  Coupler cooling  5-8 K best compromise? (why not 4.5 K – 300 K e.g.)  WU / CD  Contact cooled WU/CD of helium tank feasible? (would save on equipment) 6/11/2009SPL Workshop NOv To be investigated 1

Open Topics  Limits of operation under degraded conditions  When is a repair / exchange mandatory  Cool-down and warm-up times for the whole machine  “Natural” warm-up by static heat load for  Modules without active cooling (scheme 6)  Modules without active cooling and warm headers in cryostat (scheme 1 to 5)  Time necessary for exchange / repair of faulty components 6/11/2009SPL Workshop NOv To be investigated 2

Last Slide Thank you for your attention 6/11/2009SPL Workshop NOv