LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)

Slides:



Advertisements
Similar presentations
DS Quench TEST 2  MOTIVATION and METHOD: 1. Achieve 500kW on beam 1 – TCP7 collimators.(so far 500kW with beam 2 and 235kW over 1s with beam 1 were reached.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
(n)QPS LHC status LHC: past, present and future Mike Lamont for the LHC team
Status of the LHC Mike Lamont for the LHC team. The LHC Very big Very cold Very high energy 2.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
LHC Machine Operational Status and Plans International Workshop on Linear Colliders 2010, Geneva Steve Myers (On behalf of the LHC team and international.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
02/09/2010 Access conditions for test of the RB.A23 at 17:30. Splice mapping. Complete machine closed by ~18:00.Problems in getting TI2 ready for injection.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
Luminosity expectations for the first years of CLIC operation CTC MJ.
LHC progress Report LHCC Wednesday 23 rd March 2011.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
Turnaround time in modern hadron colliders & store-length optimization
LHC Status Report 1 Jan Uythoven For the LHC Team LPCC
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
The CERN Physics Programme
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
LHC Commissioning with Beam
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Wire, flat beams and beam-beam MDs in 2017
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Beam-beam Effects in Hadron Colliders
Β*-reach in 2017 R. Bruce, S. Redaelli, R. De Maria, M. Giovannozzi, A. Mereghetti, D. Mirarchi Acknowledgement: collimation and optics teams, BE/ABP,
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
Status of LHC Operations
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Tuesday TOTEM and transverse loss map (1) OK
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Week 35 – Technical Stop and Restart
LHC (SSC) Byung Yunn CASA.
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Week 36 Machine coordinators R.Assmann, R.Bailey
LHC Beam Operations Past, Present and Future
Collimation margins and *
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
HL-LHC operations with LHCb at high luminosity
Aims for the week Recover from technical stop and precycle at 10A/s
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Collimators: Operations - Baseline Assumptions
MD Planning Fri – Sat (1. – 2.7.)
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Summary for LPC (March 7th, Ralph Assmann)
Monday :15 fill 3523 dumped by BPMs IP6
Summary Tuesday h23: Machine closed. Precycle started.
Another Immortal Fill….
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)

Integrated Luminosity on 7th July

Summary of Luminosity progress calculated Maximum reached is 10.7x10 30 cm -2 s -1

Week 31 CHIPP HEF, Zurich, Switzerland 30 July to 9 August Luminosity vs time Integrated Luminosity vs time September 1, 20104

1303 (Aug 26) best fill so far This fill gave integrated luminosity exceeding what was shown in ICHEP Paris

Approaching 4pb -1 (TODAY) Bunch Trains Set Up

Peak Luminosity 31/8/2010

Preparations for ? Which scenario is easier? β* = 3.5, Nb = 394, MJ =22.2 β* = 2.0, Nb = 226, MJ = 12.8 Unanimous answer β* = 3.5, Nb = 394, MJ =22.2

Parameters and Conditions – Nominal bunch intensity 1.1E11 – Stick to β* = 3.5 m in all IPs – Commission bunch trains Complete re-do of the whole machine protection set-up – Go to 150 ns bunch spacing – Commission faster ramp (10 A/s) Plan for getting to before ion run LMC 18 th August.

Additional work for bunch trains Completely new set up of all phases of LHC under the new conditions needed for safe operation with high intensity bunch trains – Beam transfer (collimation) – Emittance control in injectors and during ramp in LHC – Transverse damper set up with lower noise – Injection with crossing angles (collimators and unsafe beam), – Accumulation with crossing angle; long discussions about magnitude of crossing angle – Ramp with 10A/s – Squeeze (changing crossing angles to collision values) – Collisions with crossing angles (collimation)

Crossing angles External crossing angles – IR1: -170  rad at inj./ramp and -100  rad in squeeze/collision – IR2: +170  rad at inj./ramp and +110  rad squeeze+collision – IR5: +170  rad at inj./ramp and +100  rad in squeeze/collision – IR8: -170  rad at inj./ramp and -100  rad in squeeze/collision Good for beam-beam (do we need it for 150ns ?) Bad for aperture and MP (are we ready to do this ?) Strategy – Start with nominal angles at injection – Measure IR apertures – Test parasitic beam-beam with lower angles – Decide based on this

Test ramp 10 A/s Ramp duration reduced from 46 to 16 minutes 1 st attempt reached 1.7TeV 2 nd attempt perfect ramp up to 3.5TeV

Orbits, Tunes and Chromaticities measured and automatically corrected during the ramp and stored and fed forward for next ramp Test ramp at 10 A/s B1 horizontal B1 vertical

Feedback during ramp: Thursday 19.8.

Ramp with 10 A/s Chromaticity during the ramp reproducible (RS) Beam 1 Beam 2

Correction of Beta beating (Wednesday 8 th Sep) Squeeze B2 Brief optics studies on B2 – Global correction – 100 quads ! – Impressive results ! IP IP IP IP

Friday Inject 1 train of 4, then 3 trains of 8, both beams

Saturday 11.9 RF setting up – Finally the complete injection sequence of 13x4 bunches per beam was executed and went smoothly with very little uncaptured beam

Lifetime when Reducing Crossing Angle 3 batches of 8 bunches each, spacing 150 ns  up to 6 LR interactions per bunch 100  rad 170  100  rad 80  rad 70  rad 60  rad 50  rad 40  rad 30  rad 20  rad 90  rad Conclusion: Minimum required crossing angle is ~100  rad in 2010.

Measured 450 GeV Aperture Predicted aperture bottlenecks in triplets (n1=7) do not exist. “Measured” n1 = 10 – 12 (on-momentum) instead design n1 = 7 “We discover the aperture gold mine for performance” Beam / planeLimiting element Aperture [  ] Beam 1 HQ6.R212.5 Beam 1 VQ4.L613.5 Beam 2 HQ5.R614.0 Beam 2 VQ4.R613.0

Conclusion from Aperture Plenty of aperture at triplets: > 13  (n1 > 10) Can open tertiary collimators, e.g. to 13  at injection. Can stay with 170  rad crossing angle at injection. Can also review settings for injection protection  Relax? We will measure aperture also at top energy with 3.5 m beta*. If (when) similar margins found, this will open the door for smaller beta* with same risk level.

Unexplained Beam Losses Losses with almost identical loss characteristics 4 unexplained beam losses (dump provoked by the Beam loss monitoring system) 1 unexplained beam loss while moving Roman Pots 1 beam loss provoked by a wire scan Suspicion is that debris if falling into the beam provoking a small beam loss seen by the BLM which triggers the beam dump (machine protection works well) Proposal to verify the thresholds of the BLMs by doing a “quench” test. 5

Very similar time structure than the 4 events with losses on SC magnets – loss map less localized than during alignment event. TOTEM event in stable beams (V B1) RP BLM CHIPP HEF, Zurich, SwitzerlandSeptember 1,

Update on UFOs (fast BLM event in SC regions) ● 7 beam dumps due to fast (~ ms scale) losses in SC regions, triggered by the BLMs ● Search for similar events, but that did not trigger a beam dump, using the data logged in TIMBER. – The analysis was concentrated on the period with 24 and 48 bunches.

Sub-threshold UFOs

Distribution along the ring

Correlation of Number of fast Losses with beam Intensity We expect more as the intensity increases

Outlook for the second half of this week Bunch trains (with stable beams)!

Reconsidering rate of MJ increase Following the external review of the machine protection system – Considering speeding up the increase of MJ per week to 2 instead of 1 – Could allow some time before the ion run for slight reduction of the beta* or increase in the number of bunches

Intensity increase ● Intensity increase roadmap – Start train operation with 3x8 (or equivalent) – 2 fills, stabilize the sequence. Then move on to 6x8 (or equivalent). – 3 fills at a given intensity. Integrated physics time of ~20 hours. – Intensity step 48 bunches (+- 10%). – A checklist will be defined with the requirements for increasing the intensity. – Follow up on review items – as appropriate/possible. – Injection: significant change as we are now injecting unsafe beam. – Very careful monitoring of abnormal injections.

Aggressive Schedule (short term) 48 Injection of 24 bunches Reserve

The 10 year technical Plan

The progress and performance of the LHC machine is striking. It is a great personal pleasure to acknowledge this success, due to the excellence and hard work of a wonderful team. Acknowledgements

Thank You for your attention

SPARES