Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.

Slides:



Advertisements
Similar presentations
PIP and the Booster Notch Bob Zwaska October 12, 2011 PIP Meeting.
Advertisements

PIP Update Oct Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken Domann.
Chris Smith Booster RF Cavity Upgrade Contents: The Booster Existing RF Cavities Why Upgrade? New Cavities Prototype Plans University Involvement Prototype.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Proton Improvement Plan (FY13 PMG Q4). William Pellico, Fermilab PMG, Nov PIP FY13 Q4 Summary Task Highlights Budget and Labor Review Summary.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
Proton Improvement Plan (PIP) William Pellico PIP and MI 700 kW review 21 – 22 January 2015.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Getting Beam to NuMI (It’s a worry!) Peter Kasper.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Proton Improvement Plan (FY13 PMG Q1). William Pellico, Fermilab PMG, January FY13 Summary Q1 Task Summary – Highlights RFQ Injector Budget.
All Experimenters Meeting PIP Report William Pellico on behalf of PIP team 4/7/2013.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Improvement Plan Bob Zwaska July 7, 2014 All-Experimenters Meeting.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
Ff NO A Accelerator Upgrades: Status Phil Adamson Fermilab
Proton Study Meeting 4/19/05 Eric Prebys 1 Proton Plan Stage I Eric Prebys.
PIP FY14 PMG W. Pellico 7/8/14 7/8/2014PIP PMG. PIP Activities RIL & Linac – 200MHz RF Power System High Level RF Linac Modulator 7835 Procurement – Accelerator.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
PIP Update Sept. 18 th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Pat.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken.
PIP Update Oct Agenda Summary Update – Current Activities Updates/Talks: Dave Johnson – Linac Notching (laser)
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
Overview of Booster PIP II upgrades and plans C.Y. Tan for Proton Source group PIP II Collaboration Meeting 03 June 2014.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Accelerator Status and Plans
Proton Improvement Plan Overview Bob Webber July 13, 2011.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Alexander Valishev - Simplified Modeling of Space Charge Losses in Booster.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003.
Booster Losses Keith Gollwitzer PIP and MI 700 kW review January 2015.
Doug Michael Sep. 16, GeV protons 1.9 second cycle time 4x10 13 protons/pulse 0.4 MW! Single turn extraction (10  s) 4x10 20 protons/year 700.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
Proton Plan Expectations Eric Prebys AD/Proton Source.
Proton Improvement Plan William Pellico Fermilab Institutional Review June 6-9, 2011.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Proton Improvement Plan William Pellico 44th Fermilab Users' Meeting June 1-2, 2011.
Proton Improvement Plan (FY13 PMG Q3). William Pellico, Fermilab PMG, Aug PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary.
PIP Update April 10 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Eliana.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
PIP Update April 3 rd Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
High Intensity Booster Operations William Pellico PIP II collaboration Nov. 9 th 2015.
Users' Mtg - 4 Jun 08 FNAL Accelerator Complex Status Ron Moore Fermilab – AD / Tevatron Dept.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
Early Beam Injection Scheme for the Fermilab Booster: A Path for Intensity Upgrade Chandra Bhat Fermi National Accelerator Laboratory DPF2015, ANN ARBOR,
Proton Plan PMG 4/18/05 E Prebys/J. Sims 1 Proton Plan Status March Report Eric Prebys Jeff Sims.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
PAC Meeting, December 12, Prebys 1 The Problem.
PIP Update March 6 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Protons for Neutrinos: Mid-Term and Project-X Bob Zwaska Fermilab Intensity Frontier Neutrino Working Group Meeting October 24, 2011.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Matt – Cavity Refurbishment) – Additional Meetings/Notes.
Proton Economics Eric Prebys FNAL Accelerator Division.
Welcome! Robert Zwaska 23 November 2015 Workshop on Booster Performance and Enhancements.
Presentation transcript:

Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 2 Basics Linac and Booster are now running  Being tuned for HEP  Some PIP improvements being realized Major PIP work continues  Preparing major items for future downtimes / shutdowns Cavities, vacuum, transformers, power supplies…  Studies in Linac & Booster Balancing time:  No longer have to compete with shutdown for resources  Now have to compete with operations

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 3 Operating Status Booster is providing beam for NuMI. Typical numbers:  3 Hz beam  ~ 2.5e12 protons / pulse  ~ 2.5e15 protons / hour Present loss levels would accommodate > 6 x throughput Study periods have occasionally higher beam rates and intensities:  NTF (Linac)  Booster Studies Limited mostly by Main Injector  Lower rep rate because there is no slip stacking  Lower intensity until MI conditions

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 4 Linac Items Linac Hatch installed  Allow removal and installation of material into lower-level  Chief need is to put in new house-power transformer Next shutdown Progress on LEL Power supplies and amplifiers  Test cells of Marx generator for high-current, high- voltage pulses  Plans for klystron replacements of amplifier tubes Prototype in the works

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 5 Cavity Refurbishment Refurbishment is the limiting task in getting the Booster to 15 Hz Booster has 17/19 cavities in place with two out for refurbishment  This will continue throughout the next few years Next refurbished cavity to be installed this week  Cavity to be removed was the first- refurbished cavity which is leaking RF  This will continue throughout the next few years PIP anticipates more technicians now that the shutdown is over  These persons have not become available yet, even though the machines are operating now Also need to build new tuners with new ferrites  Issues with ferrite vendors and designs Cavity (RF17) preparing to repair flanges Cones and new cooling loops

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 6 Refurbishment Projections Have had to rework some of the first-refurbished cavities  Process is improving – hopefully accelerating  Expect more perturbation as operations exercises cavities to higher rates

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting Loss reduction: Booster Aperture  Magnet moves  Scans  Location: Long 16 Vertical Move  Fourth magnet move  Ready for a fifth  Plan several more as time allows Tunnel Location m

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 8 Loss Control: Booster Notching A “notch” of beam is removed from the Booster near injection to allow the risetime of the extraction With the previous scheme, at 15 Hz we would be putting 300 W of losses into the Booster from the notch alone  This loss was localized in a few gradient magnets PIP has a 3-stage approach to eliminating the losses from the notch 1.Modify the notcher arrangement in the Booster Relocated loss into a dump 2.Cog with the corrector magnets instead of RF phasing Under test now 3.Make most of the notch in the Linac Loss at 750 keV instead Gap

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 9 New Absorber & Kickers Relocate notch location from a series of kickers into a well- designed dump  Old extraction area to Main Ring Capable of absorbing 300 W of notching  Booster loss budget is 525 W New notcher has been operating since startup this year Future improvements: shorter kickers for cleaner pulses Beam direction

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 10 Laser Notcher Neutralize a portion of the Linac beam with a pulsed laser  Remove the majority of the loss from the Booster entirely Prototype of the laser front- end is operating  Atypical laser Multiple timescales High-pulse power Moderate average power (few W)  Final gain stages being specified Prototype of interaction region built with 3-D printer  Looking into collaborative production and testing of the final chamber

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting Booster Aperture  Magnet moves  Scans  Location: Long 16 Vertical Move  Fourth magnet move  Ready for a fifth  Plan several more as time allows Tunnel Location m

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 12 Summary Proton Source is operating  Operations are at a moderate level of intensity with low losses  Some PIP improvements in place  High-power beam awaits MI conditioning –or – Recycler slip stacking – or – Booster Neutrino Beam Work continues alongside operations  Refurbishment is the limiter to reaching 15 Hz operation Critically need labor to support the refurbishment effort and coordination of various groups (also operations again) Other systems also need replacement – but not time-critical yet  Studies in progress to reduce and control losses  Major upgrades still in the work to ensure long-term viability of the Proton Source

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 13 Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 14 Proton Improvement Plan Projection NOvA Shutdown g-2 Mu2e 8 GeV 120 GeV LBNE William Pellico, Fermilab PMG, Aug MiniBooNE Maybe

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 15 Booster - Historical Performance Recent Modifications: Booster Collimators FY04 Booster Low Level/Damping FY04 New Booster Injection Line FY FY06 Removal of L13 Extraction Region FY07 Linac Quad PS FY07 Linac Low Energy Low Level FY08 New Ramped Correctors FY09 Annual E19

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 16 The Proton Improvement Plan should enable Linac/Booster operation capable of  Delivering 2.25E17 protons/hour (at 15 Hz) in 2016 while  Maintaining Linac/Booster availability > 85%, and  Maintaining residual activation at acceptable levels and also ensuring a useful operating life of the proton source through The scope of the Proton Improvement Plan includes  Upgrading (or replacing) components to increase the Booster repetition rate  Replacing components that have (or will have) poor reliability  Replacing components that are (or will soon become) obsolete  Implementing improvements or operational changes to reduce beam loss  Studying beam dynamics to diagnose performance limitations Several significant activities are well underway Goals for the Proton Improvement Plan

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 17 Booster 15 Hz Synchrotron Resonant Gradient Magnets Tunable RF Cavities 400 MeV to 8 GeV Beam Input MI-8 8 GeV

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 18 Proton Improvement Plan Development Proton Task Force (PTF) FY10  Initial effort to understand Proton Source Concerns  Focused on reliability and modernization Proton Improvement Plan Workshop – Jan 2011  Review of PTF  Review of additional issues associated with flux Management Structure – 2011 Summer  Established project team and ground rules Planning Structure – 2011 Fall  Managers established for all subprojects Resource Loaded Schedule 2011 Winter  Bottoms-up estimation of all subprojects Detailed Project Organization – 2012 January  Project Management Plan  Project Design handbook  Accounting codes & signature authority

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 19 References A Plan for Delivery of 8-GeV Protons through 2025, Beams- doc-3781, docid= docid=3781 Proton Source Task Force Report, Beams-doc-3660, docid= docid=3660 Proton Source December 2010 Workshop, conferenceid=114 conferenceid=114 PIP Home Page: ad.fnal.gov/proton/PIP/PIP_index.htmlhttp://www- ad.fnal.gov/proton/PIP/PIP_index.html

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 20 Booster Losses Losses at injection  Poorly captured beam Notch creation  Gap for extraction  Created with a kicker  Lost in gradient magnet Slow losses at high-energy  Optics issues  RF variation Transition  Occasionally significant, but can usually be tuned away

Sept. 9, 2013 Bob Zwaska All-Experimenters Meeting 21 Path to Higher Proton Throughput Loss reduction  Lower linac emittance RFQ & linac lattice improvements  Apertures & alignment Comprehensive survey of apertures Alignment where necessary (including within girders) Opening apertures where possible  Optics adjustment Comprehensive survey of lattice and coupling Control of tunes and chromaticity Automated orbit and optics smoothing  RF improvements Increased voltage from amplifiers Cavity modification/replacements  Instabilities Dampers  Injection painting Orbit Control  Magnetic Cogging Prerequisite for other work Loss Control  Rework of notching in Booster Perform earlier in cycle New notch kickers and absorber Exploration of full or partial notching in Linac  Collimation system Operate as true, two-stage system Run beam near primary scatterer Optimize primary scatter thickness  Adjust radiation shielding where advantageous