INJECTORS BLM SYSTEM: PROGRESS REPORT Christos Zamantzas on behalf of the BLM team. MSWG 28/08/2015.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
BLM FOR THE INJECTORS PROJECT CABLING NON-CONFORMITIES LIU-PSB Working Group Meeting (15/08/2013) Christos Zamantzas
INJECTORS BLM BI-TB on Proton Injector start-up. Summary of actions 2 BLM SystemComments LINAC2 8 movable detectors.
BI SW for LINAC4 On behalf of BE/BI/SW BI software development process Specifications List of BI Systems – Not covered: PSB ring systems Conclusions Lars.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
CERN Accelerators Topology Configuration and Change Management Engineering Department Thomas Birtwistle, Samy Chemli – EN/MEF/DC.
Status of NA62 straw electronics and services Peter LICHARD, Johan Morant, Vito PALLADINO.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Linac4 FBCT’s 18/ L4 BI BCT review Lars Søby On the behalf of: M. Andersen, D. Belohrad, L. Jensen, Franco Lenardon and J. C. Allica Santamaria.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
1 1. Some recent views ( ) 2 Linac tunnel
Status of NA62 straw electronics Webs Covers Services Readout.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Beam Instruments PSB + Transfer Lines B. Mikulec, J-F. Comblin.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
Overview Consolidation projects for PS LIU-PS Main observable review Conclusion Acknowledgements S. Gilardoni R. Steerenberg G. Metral H. Damerau BI colleagues.
News and hot topics Impedance meeting 14/04/2014.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
LS1 status 6/06/2014. BLM re-installation ARC Sector 3-4 – in work, will be done to Sector 4-5 – from 30(23).06 – Sector for Cool.
LIU-PSB BIS presentation / Christophe Martin TE-MPE-EP 28/02/ Beam Interlock System for Transfer Lines & PS Booster Christophe Martin TE/MPE/EP.
LIU-SPS progress for BE/BI L. Jensen on behalf of BE/BI 27/08/2015Lars K. Jensen BE/BI/SW1.
L4 BCC – 1 Sep 2011 F. Roncarolo, U. Raich L.Soby, J.Tan, C.Zamantzas, F. Lenardon, C.Vuitton, G-J.Focker.
LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
BLM FOR THE INJECTORS PROJECT LINAC4 & PSB Beam Instrumentation Review – 18/10/2011 Christos Zamantzas
Status of LAV electronics commissioning Mauro Raggi, Francesco Gonnella Laboratori Nazionali di Frascati 1 Mauro Raggi - Laboratori Nazionali di Frascati4.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
PS-LIU status S. Gilardoni – BE/ABP H. Damerau – BE/RF LIU-PT 27 Aug
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
Linac4 BCC 14/10/2010 Linac4 Measurement and Dump Lines BCC on the Linac4 Transfer Line Status.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
New PSB beam control BIS Interlocks A. Blas PSB Beam Control 20/01/ BIS: Beam Interlock.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
ELENA installation progress F. Butin / ELENA collaboration.
Status of the BI Work Package in the LIU-PSB frame
Brief Status SPS Prototype PSB Prototype Installed in LS1
ELENA installation and commissioning status
LIU Wire Scanner Milestones June 2017
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Injector De-cabling Project
Injectors BLM system: PS Ring installation at EYETS
LIU–PLI report LIU PSB meeting.
LINAC4 50 MeV phase BIS STATUS
EC Activities Status for the LIU
BE-BI Software for LINAC4
AWAKE proposals for BE/BI
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Status of the BI Work Package in the LIU-PSB frame
WPs concerned by L4 connection:
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
Injectors BLM system: PS and PSB Ring installations at EYETS
LHC BLM system: system overview
Disabling Rules.
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
CONSOLIDATION CPS-BL SYSTEM
CONSOLIDATION CPS-BL SYSTEM
BLM planning 03/03/2014.
J. Emery, B. Dehning, E. Effinger, G. Ferioli, C
LS1 status 28/04/2014.
LS1 status 24/03/2014.
BLM planning 03/02/2014.
ATS Consolidation Day 22nd May 2019 Beam Instrumentation
Status of the BI Work Package in the LIU-PSB frame
SPS Injection BIS - Draft requirements
Presentation transcript:

INJECTORS BLM SYSTEM: PROGRESS REPORT Christos Zamantzas on behalf of the BLM team. MSWG 28/08/2015

Overview Status of the development Status of the Beam Loss Monitoring system upgrade in LINAC4, PSB and PS w.r.t.  Cabling  Detectors  Supports  Electronics  Installation  Documentation  Budget

DEVELOPMENT 28/08/2015

Development Using the prototype installations at PSB and PS we were able to: identify and solve issues in the analogue circuitry of the acquisition card in terms of leakage current, offset, temperature dependence etc.  recently all modules have been sent back to the manufacturer and modified the input stage. develop and validate the firmware and software  recently updated the firmware to control better the start-up procedure of the analogue circuitry.  recently updated the FESA class to provide both raw and normalised to Gy/s measurements. develop and test in real conditions the continuous connectivity check  under development a continuous quality check of the complete chain from the detector to the processing electronics. Still several parts need to be addressed in the firmware: most notably: loading of settings/thresholds, system status information and interlocking.

Prototype installation PSB One complete rack with all electronics has been installed  covers all L2 locations in the PSB ring (32 ch.) and  some channels in 4L1 hotspot (4 ch.) Advanced versions of Firmware and Software available. Direct Ethernet connection to each acquisition module available for detailed analysis and debugging.  2 μs samples continuously Through FESA class, system provides the ‘evolution’ data synchronised with the basic period.  1 ms samples during beam presence Have already been used in a couple of MDs. OP has a first version of its fixed display.

LINAC4 28/08/2015

LINAC4 1/3 Detectors have been defined and available  Will use LHC type ICs,  Exception at 50 MeV to be equipped with a Diamond Supports for the machine line (+ some spare) have been designed and produced  Some have already been installed  The remaining are scheduled from Nov  Found solution for the non-conformity issue not seen earlier during integration check Supports for the transfer line are pending  Meeting in September with Alessandra and the integration team to clarify the position of channels  Based on that outcome, we will know if we can re-use the current support design or we will need a new one.

LINAC4 2/3 Majority of the cables have been installed (CKB50 type)  All cables in the tunnel are enclosed in a metallic tray  Missing installation of one channel  issue with crossing a wall  waiting for decision from EN/EL-BE/OP Assembly of connectors of signal cables  Not done - we need first the supports installed  this blocks us also from installing all other electronics in the rack.  EN/EL agreed to go for partial assembly  first assemble all connectors in the surface and  then batches in the tunnel following the installation.

LINAC4 3/3 All electronics produced, tested and ready  Installation planned for November Firmware and Software  Ready for measurements  Interlocking abilities Q Specifications agreed Budget OK

PSB 28/08/2015

PSB 1/2 Detectors:  75 ICs and 32 FICs - all procured.  8 Diamonds - to be procured this year.  also spare detectors for all types will be available Cabling list request have been updated with  new channels and spare cables for all locations  Ring: 32 ch. w/ FIC, TL: 43 ch. w/ IC and BI: 8 ch. W Diamonds  Spare channels: 16 in the Ring and 7 in the Transfer Lines Support’s design for Ring L3 positions (FICs) is complete  Waiting for integration team to give also the ok before we go into production.  A prototype will be tested in the machine next week. Supports for the new injection section (ICs and Diamonds) is complete  Design will circulate for approval soon. Supports design for all remaining transfer line detectors (ICs) has not started  Next week first try in collecting all data/photos.  We expect it to be very complicated due to topology and space.

PSB Supports for FIC

PSB Supports for new Injection line

PSB 2/2 Three new racks have been assigned positions and requested for installation. All electronics for the ring and BI line produced, tested and ready for installation Electronic modules for the ejection lines in planned for the next production to start at Q Specifications are agreed. Defined and agreed naming convention for all channels with quality assurance team  with the exception of Observation system Budget is OK.

PSB Expert Name Convention BR.BLMI.04L2.ES Accelerator (2 or 3 letters) : LT – LINAC Transfer LTB – LINAC to Booster transfer LBE – LINAC to Booster Emittance LBS – LINAC to Booster Spectrometer Line BR – Booster Ring BR1, BR2, BR3 or BR4 – Booster Ring (Individual) BI – Booster Injection BE – Booster Extraction BT – Booster Transfer BTP – Booster Transf. to PS BTM – Transf. to Measurement line BTY - Transfer to Isolde Detector type: I – IC S – SEM L – LIC F – FIC D – Diamond A – ACEM Radial Position: E – external I – internal T – top B – bottom L – left to beam direction R – right to beam direction X – between beam pipes Period/Section (2 to 4 letters) : for the ring: – number of period L1-L5 – fixed or for the transfer lines: xxx – distance [m] (BTY line) xx – 10, 20 for first, second etc. (for all other lines) Vertical Position: (only for BR, BI, BT) S – Superior I – Inferior

PS 28/08/2015

PS 1/3 Detectors:  16 Diamonds procured  160 ICs are in production. Delivery expected in All cabling is planned for LS2  we will ask if possible to install earlier the Diamond connections during WTS 2015/2016. Supports:  Design for the ring detectors (ICs and Diamonds) has started.  Prototype has been tested on a spare magnet.  Next step: design office for the production documents  Transfer lines have not been considered yet.

PS Ring Support Prototype

PS 2/3 Specifications:  After providing additional information to Rende on the specifications, he ‘approves’ current proposal with some modifications.  Will meet again after OP’s internal discussion.  Specifically for the OASIS connection  in the legacy system the signal of all ACEMs is split and one part is send to OASIS acquisition cards and the other to the on-board integrators.  proposal is in the future to provide 1 ms digital samples directly to an OASIS class.  Specifications document will be amended and redistributed

PS 3/3 Budget is at large part ok  LIU, CONS and BE are all contributing  BE: already paid  LIU: 250 kCHF missing - Malika & Rhodri are discussing this last part  CONS: request made, pending approval in October 2015 Estimated budget required: split by project Estimated budget required: yearly apportionment

Thank you

Spare slides

System Overview

Detector Support – PSB Ring Very tight integration. Verified all locations; no interference / obstruction to other systems. 24

Custom support for period 15 No space to add the detector on the inside of the ring ACEMs mounted on the same plate 25

BLM Cable installation in PSB 26 New cable (CKC50) production run on tight schedule: −Modification of the CKB50 specs −Completed and delivered on-time Re-installation in PSB −Conformity measured (developed a test-bench) −Completed on-time Patch-Cords −Several types needed (length and connector type) −Completed and tested HV CablesSignal Cables Signal and HV Patch-Cords