Francesco Cerutti ENERGY DEPOSITION ASPECTS FOR LHCb REQUEST 5th Joint HiLumi LHC - LARP Annual Meeting Oct 29, 2015 through L.S. Esposito’s work and essential.

Slides:



Advertisements
Similar presentations
Recap of heat loads and peak doses from HL-LHC Q1 to Q7 L.S. Esposito, F. Cerutti HL-LHC WP3 meeting, 22 May 2014.
Advertisements

Results of dosimeter readings in IR3 and IR7 DGS-RP High Level Dosimetry LHC Collimation WG meeting 03/09/2012.
24/01/08Energy deposition, LIUWG, Elena Wildner1 Upgrade phase 1: Energy deposition in the triplet Elena Wildner Francesco Cerutti Marco Mauri.
ENERGY DEPOSITION IN HYBRID NbTi/Nb 3 Sn TRIPLET CONFIGURATIONS OF THE LHC PHASE I UPGRADE FermilabAccelerator Physics Center Nikolai Mokhov, Fermilab.
Spectrometer compensation in IR2 and IR8 during the 450 GeV collision run September 11, 2006 LOC meeting Y. Papaphilippou Thanks to S. Fartoukh, W. Herr,
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
* IP5 IP1 IP2 IP8 vertical crossing angle at IP8 R. Bruce, W. Herr, B. Holzer Acknowledgement: S. Fartoukh, M. Giovannozzi, S. Redaelli, J. Wenninger.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
E. Todesco PROPOSAL OF APERTURE FOR THE INNER TRIPLET E. Todesco CERN, Geneva Switzerland With relevant inputs from colleagues F. Cerutti, S. Fartoukh,
Detector studies, Radiation Simulations, Organization FCC Hadron Detector Meeting July 27 th 2015 W. Riegler.
Beam Background Simulations for HL-LHC at IR1 Regina Kwee-Hinzmann, R.Bruce, A.Lechner, N.V.Shetty, L.S.Esposito, F.Cerutti, G.Bregliozzi, R.Kersevan,
DS Heat Load Scenarios in Collision Points and Cleaning Insertions. Prepared by F. Cerutti, A.Lechner and G. Steele on behalf of the FLUKA team (EN-STI)
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The Large Hadron Collider Contents: 1. The machine II. The beam III. The interaction regions IV. First LHC beam [R. Alemany] [CERN AB/OP] [Engineer In.
Review of Quench Limits FermilabAccelerator Physics Center Nikolai Mokhov Fermilab 1 st HiLumi LHC / LARP Collaboration Meeting CERN November 16-18, 2011.
Thursday Summary of Working Group I Initial questions I: LHC LUMI 2005; ; ArcidossoOliver Brüning 1.
With a lot of help from Reine Versteegen, John Jowett, Richard Jacobson, Burkhard Schmidt, Gilda Scioli, Werner Herr CERN-LHC * IP5 IP1 IP8 Spectrometer.
1 CONSIDERATIONS ON WARM MAGNET MEASURED DOSES 2012 September 3rd Francesco Cerutti for the team key contributions by TE-MSCDavide Tommasini and Pierre.
HL-LHC Annual Meeting, KEK, 11/21/14WP3 Summary – G. Sabbi 1 Work Package 3 Summary GianLuca Sabbi, Ezio Todesco 4 th HiLumi LHC – LARP Annual Meeting.
Heat Deposition Pre-Evaluation In the context of the new cryo-collimator and 11-T dipole projects we present a review of the power deposition studies on.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Shielding the 140 mm option F. Cerutti, L.S. Esposito on behalf of CERN FLUKA team.
Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LHC Interaction Region Upgrades and the Machine- Experiment Interface Emmanuel Tsesmelis CERN TS/LEA CARE-HHH-APD Mini-Workshop IR'07 Frascati 8 November.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
08/11/2007M. Giovannozzi – CARE-HHH-APD IR’071 Optics issues for Phase 1 and Phase 2 upgrades Massimo Giovannozzi, CERN Outline: –Option for Phase 1 and.
Energy Deposition Issues in LHC IR Upgrades LHC IR Upgrades Workshop Pheasant Run, St. Charles, IL October 3-4, 2005 Fermilab LHC IR 2005 Nikolai Mokhov,
H. Matis, S. Hedges, M. Placidi, A. Ratti, W. Turner [+several students] (LBNL) R. Miyamoto (now at ESSS) H. Matis - LARP CM18 - May 8, Fluka Modeling.
E.B. Holzer BLM Meeting: Q & A March 20, Questions and Answers.
A liner in the Corrector package A Cu liner has been inserted in the gap between the CBT and the coil aperture of all the corrector package elements (see.
31/07/08Review new IRs: Energy Deposition1 Energy Deposition in the New IRs Francesco Cerutti, Marco Mauri, Alessio Mereghetti, Ezio Todesco, Elena Wildner.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
ENERGY DEPOSITION AND TAS DIAMETER
Status of the magnet studies in the ARCS (FLUKA)
CERN, 11th November 2011 Hi-lumi meeting
High Luminosity LHC M. Giovannozzi – CERN Beams Dept.
Operating IP8 at high luminosity in the HL-LHC era
Francesco Cerutti, Andrea Tsinganis WP10 Energy deposition & R2E
Beam Energy & Intensity: One bunch during full cycle
On behalf of the FLUKA team
TAXS and TAXN ABSORBERS - OVERVIEW
Energy deposition studies on magnets. Aim. First applications
Optimization of Triplet Field Quality in Collision
Accelerator and Experiment Interface Session: LS2, LS3
Progress in Collimation study
Spectrometer Operation in IP2 & 8
Follow-up of HL-LHC Annual meeting
Β*-reach in 2017 R. Bruce, S. Redaelli, R. De Maria, M. Giovannozzi, A. Mereghetti, D. Mirarchi Acknowledgement: collimation and optics teams, BE/ABP,
Energy deposition studies in IR7 for HL-LHC
DEBRIS IMPACT IN THE TAS-TRIPLET-D1 REGION
WP3 meeting Aug 21, 2015 V1.1 RECAP Francesco Cerutti.
Interpretation and use of BLM Data
Beam-Induced Energy Deposition Studies in IR Magnets
Alternative design of the matching section for crab-cavity operation
Upgrade phase 1: Energy deposition in the triplet
Optic design and performance evaluation for SPPC collimation systems
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
1st HiLumi LHC / LARP Collaboration Meeting 2011 Nov 17th
Global aperture measurements at 450 GeV with 170 mrad crossing angle
Collimation margins and *
PROPOSAL OF APERTURE FOR THE INNER TRIPLET
Revised estimates of heat loads and radiation damage in the IT and D1
HL-LHC operations with LHCb at high luminosity
FLUKA Energy deposition simulations for quench tests
A. Tsinganis, F. Cerutti (EN/STI/FDA)
Review of Quench Limits
Presentation transcript:

Francesco Cerutti ENERGY DEPOSITION ASPECTS FOR LHCb REQUEST 5th Joint HiLumi LHC - LARP Annual Meeting Oct 29, 2015 through L.S. Esposito’s work and essential discussions with G. Arduini, M. Brugger, H. Burkhardt, R. De Maria, B. Di Girolamo, I. Efthymiopoulos, S. Fartoukh, M. Giovannozzi, S. Redaelli, S. Roesler, L. Rossi, A. Santamaria, B. Schmidt, …

2 SCOPE F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015 proton-proton collision debris impact on warm dipoles ( MBXWS.1R8 ) muon chambers ( neutron background ) triplet-D1 D2 electronics QRL [access, activation] RP

3 compensator dipoles LHCb spectrometer outside the ring D [on the horizontal plane for the outgoing beam] F F D IR8: TRIPLETS F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015 [FLUKA geometry of the detector from RP and LHCb colleagues]

4 OFF ON SPECTROMETER EFFECT F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

5 MBXWS R8 30 MGy after 100 fb -1 in the IP side return coils (to be protected in the front) cm -2 s mm diam. aperture filling the air gap with tungsten (to use it as a 1m long “TAS”) one collects 115 W more calculations for 385 urad half horizontal crossing angle F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

6 NEUTRON cm -2 s -1 F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, cm < x < 5 cm 18.8 m < z < 18.9 m with tungsten filling inside MBXWS (lead) shielding - here not included - already in place?

total power [W] MARGIN TO QUENCH & cm -2 s -1 corresponds to 45 MGy after 300 fb -1 vs. 30 MGy design design limit LIFETIME 385 urad half horizontal crossing angle F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

8 IR8: D1 AND D2 outside the ring F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

9 TWO PROTECTION ELEMENTS FOR LS2 L8 X F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015 i.e. mini-TAN

10 MASK EFFECTIVENESS cm -2 s -1 (power),50 fb -1 (dose) 385 urad half horizontal crossing angle factor 5 reduction in peak power density/dose in addition to the factor 2 provided by cm -2 s W in the D2 cold mass 5 mW/cm 3 peak in D2 coils i.e. 30 MGy after 300 fb -1 F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

11 90 cm W-TANmini MASK EFFECTIVENESS [II] F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

12 L.S. Esposito, talk at the 4th HL-LHC Coordination Group Meeting, F. Cerutti, talk at the LHC Machine Committee, L.S. Esposito, F. Cerutti, A. Lechner, A. Mereghetti, V. Vlachoudis, A. Patapenka CERN-ACC (IPAC 2013) A. Santamaria, L.S. Esposito, R. Alemany, H. Burkhardt, F. Cerutti, N.V. Shetty CERN-ACC (IPAC 2014) F. Cerutti, talks at the WP8 Bi-weekly Meetings, and UPGRADE TO cm -2 s -1 AND 50 fb -1 (POST LS2) no need for a TAS (values not exceeding IR1 and IR5 at L 0 ) D2 (L&R) protection required: 50cm Cu mask (in addition to a 60cm W absorber at the beam chamber separation) F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

13 MATCHING SECTION F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015 R5 (CMS) need for designing a collimator (TCL) protection system Looking for reference at Point cm -2 s -1 L.S. Esposito 2 nd Joint HiLumi LHC - LARP Ann. Meet. Nov 2012 major role played by TCL4/TCL5 Point 8 specificities: different crossing angle, different TAN, injection kickers and septa around Q5R

14 [cm -2 ] [Gy] vertically averaged from -1.1m to 2.4m (0 is the beam height) longitudin ally averaged over 4m (from 2m to 6m, 0 is the cavern center) x [cm] y [cm] SINGLE EVENT EFFECT RISK limit of 10 7 cm -2 per year to be kept facing a 2 to ~100 fb -1 lumi increase F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015

15 QRL F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015 assuming there 1 kGy per 100 fb -1 one gets cm -2 s -1 L8

16 TOWARDS cm -2 s -1 AND BEYOND MBXWS as TAS is a promising option, importance dependence on the crossing angle. Impact of IP displacement and additional dipole to be evaluated. Background from backscattering to be evaluated with the actual shielding configuration (neutron fluence rate in the unshielded muon chamber above the forward iron block up to several MHz/cm 2 ) LS2 mini-TAN+D2 mask solution to be optimized: real TAN? TCLs for the matching section quadrupole protection Electronics shielding (US85 safe room) F. Cerutti5 th Joint HiLumi LHC – LARP Annual MeetingOct 29, 2015