Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed.

Slides:



Advertisements
Similar presentations
XP 1157 Increasing the CHI start-up current magnitude in NSTX B.A. Nelson et al. 1.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Engineering Operations Outage Status: Post-run diagnostic calibrations have been completed and in-vessel work can start on PCHERS, FIDA, MPTS, and the.
August NSTX-U Team Meeting. Engineering Operations August 15, 2014 NSTX-U In-Vessel installations and calibrations have concluded, and activities have.
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
MUTAC Review, 9 April MuCOOL and MICE Coupling Magnet Status Michael A. Green Lawrence Berkeley Laboratory Berkeley CA
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
Fasteners / Joint Design Michael Kalish NSTX TF FLAG JOINT REVIEW 4/10/03.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
REQD FUTURE POWER SYSTEM CHANGES  Following additional work is required to be performed to restore full capability of the machine: 1. Provide power feed.
TF FLAG JOINT HIGH CURRENT TEST FIXTURE INSTALLATION TO BE IN THE NSTX TRANSITION AREA Features Assembled Components: Flag and Mating Section of TF Center.
Office of Science Coupling Coil Status S. Gourlay August 1, 2012.
Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011.
Linac Marx Modulator Update Trevor Butler 5/20/2015.
NSTX TF Flag Joint Design Review INTRODUCTION C Neumeyer 8/7/3.
NSTX TF Flag Joint Design Review OVERVIEW C Neumeyer 8/7/3.
NSTX Center Stack Upgrade Workshop Requirements & Design Point C Neumeyer Jan 22, 2009.
1 CHI Summary Transient CHI (XP606) –All systems operated reliably without any faults Edge Current drive (XP533)
Signals from ISTP-001 April 11-13, 2005 Preliminary Assessment C Neumeyer.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
Engineering Operations OH water leak: Water leak is located ~ 4.5” into the upper OH lead. Leak 2 o’clock Cooling hole in. dia.
Failure of Original TF Inner Leg Assembly C Neumeyer 4/10/3.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
April NSTX-U Team Meeting. Engineering Operations April 25, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in mid-June to shift activities.
1 WANG,Li/SINAP WANG Li, WANG ShuHua, LIU YiYong, SUN Sen, HU Xiao, YIN LiXin Shanghai Institute of Applied Physics, CAS, Shanghai , China Shanghai.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.
CHI Run Summary for March 10-12, 31 & April 9, 2008 Flux savings from inductive drive of a Transient CHI started plasma (XP817) R. Raman, B.A. Nelson,
NSTX NSTX Center Stack Upgrade Ensure fatigue resistant Welds: minimum # of locations shown, could be more. Various Weld Reinforcements & Hardware Replacement.
Engineering Operations FY08 Outage: In-Vessel Work: –BSE Vacuum Vessel Interfaces Completed –Liquid Lithium Divertor Tray trial fit-ups –HHFW Antennas.
1 R Raman, B.A. Nelson, D. Mueller 1, T.R. Jarboe, M.G. Bell 1, J. Menard 1, R. Maqueda 2 et al. University of Washington, Seattle 1 Princeton Plasma Physics.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
TF Joint Operations Review Introduction C Neumeyer 2/10/05 Scope and Outline of Review Summary of Findings from 2004 Run Review of Joint Force, Pressure.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Peer Review NSTX TF Hub Assembly Friction Coating C Neumeyer 10/27/04 Requirements Testing Calculation Update Implementation.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
NSTX TF Flag Joint Torque Collar Chit Review C Neumeyer 9/11/3.
NCSX NCSX CDR May 21-23, 2002 H.W. Kugel Slide 1 Conceptual Design for NCSX Auxiliary Systems Heating, Fueling,Wall Conditioning and Vacuum Systems.
TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking.
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
Solenoid Free Plasma Start-up Mid-Run Summary (FY 2008) R. Raman and D. Mueller Univ. of Wash. / PPPL 16 April 2008, PPPL 1 Supported by Office of Science.
TF Joint Operations Review Simplified Modeling & Protection C Neumeyer 2/10/05 IP and OOP Load Modeling Linear Model of IP and OOP pressure at Joint FEMLAB.
NSTX-U Run Planning Guidance for 2015 NSTX-U Research Forum 1 FY2015 (and 2016) research milestones will guide prioritization of eXperimental Proposal.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
FY10 Ops Preparations: Extended vessel bake (to 3 weeks) Additional Physics Operators Spare LITER probes/fill systems fabricated & new staff Run day status/plans.
Programme for “Target 3” – test of alternative bearing materials (from Jason Tarrant) –Drawing updates by 11 th November –Bearings: Material approval –
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
1 PFC requirements  Basic requirements  Carbon based  Provisions for adding (interface design included in research prep budget)  NBI armor  Trim coil.
Engineering Operations Outage Status: Tile cleaning is complete Tentatively planning on 2 LITER operation. Design Review upcoming Shielding of HHFW/in-vessel.
NSTX TF Flag Joint Status of Design, Analysis, Test Activities & Design Review Preparations C Neumeyer NSTX Team Meeting 7/24/3.
AWB NSTX TF Flag Joint Design Review April 10, 2003 Art Brooks.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
REQUIREMENTS & ASSUMPTIONS C Neumeyer 4/10/3. FIELD AND CURRENT Base GRD requirement: 3kG at R 0 =0.854m with 4.5 sec flat top, once every 300s
NSTX NSTX Team Meeting –Masa Ono August 14, 2015 Masa Ono February 5, 2016 NSTX-U Team Meeting.
Engineering Operations TF Commissioning Mechanical testing of TF flag/box assemblies complete, inner bundle installed, and all joints made up. Joint resistance.
Preliminary Analysis of TF Joint Behavior* C Neumeyer NSTX Team Meeting 2/12/4 *Summary from 1/29/4 Presentation.
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
NSTX TF Flag Joint Design Review OVERVIEW C Neumeyer 8/7/3.
Project Manager’s Report + DC/MoM Report
Run coordinator report March 23 – 30, 2011
Far Detector Activities Late 2017 – Early 2018
Status of the cryogenic system for B180
DEC System Voltage Planning - June 2018
Presentation transcript:

Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed in about a week. The inner TF bundle and upper flags/boxes to be installed on March 14th General test cell access will end on March 14th. Machine techs will start two shift/day installation of lower flags/boxes and the flex bus, as well as “scrubbing’ the machine areas. The ISTP (field coil power tests) will start on March 28th Plasma operations will immediately follow, with the 1st full week of operations beginning on April 4th.

Engineering Operations TF Rework Final Design Review Held 2/10/05 Epoxy potting improvements will overcome primary problem of 2004 run Friction coating on hub disks eliminates a weakness which would have been a limiting factor at higher fields According to our analytic models…. Bt ≤ 4.5kG operation should be robust 4.5kG ≤ Bt ≤ 6kG operation is feasible but with some liftoff Peak pressure at joint, and box/hub friction interface are limiting factors Temperature at joint appears to be within allowables with flat top of 0.5 seconds

Engineering Operations TF Commissioning 6kG operation as analyzed appears to be less severe than worst case joint behavior during prior run period, in terms of peak pressure at joint Instrumentation and data mining tools will guide the commissioning and benchmarking process Initial phase of commissioning will target 4.5kG level Later phase of commissioning will target operation above 4.5kG, approaching 6kG, pending results of benchmarking and experience at 4.5kG Simplified models have been developed for use in real-time protection which shall be implemented prior to operations above 4.5kG

Engineering Operations Some Other Outage Activities Welds have been restored in MG#2. Restart of that set is in progress. A more extensive rework of the MG#1 welds is in progress and will be complete after the start of the run. Commissioning of the Switching Power Amplifier (SPA) to power the RWM error field coils is in progress with plans to complete dummy load testing by the end of March. The CHI transient start-up capacitor bank will be brought on line this year with 2kV capability. Vacuum vessel sections are currently being tested for 2kV CHI Ops.

Engineering Operations NSTX Run Schedule A 2nd bakeout and hot boronization is currently planned for the 1st maintenance week. The run is scheduled to go through the month of September with some “contingency” weeks to make sure we complete our 18 run weeks. We will schedule two weeks in August as “firm” vacation weeks, and will keep the test cell open for maintenance on those weeks. The scheduling of the other maintenance weeks is somewhat flexible.