WP7 Plan – Pilot TSS Cost – Risks Linda R. Coney Group Leader – Target Safety and Controls www.europeanspallationsource.se 15 – 16 February 2016.

Slides:



Advertisements
Similar presentations
Requirements Specification and Management
Advertisements

1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Project Plan The Development Plan The project plan is one of the first formal documents produced by the project team. It describes  How the project will.
Earned Value Project Management: a powerful tool for software projects
Development plan and quality plan for your Project
International Scientific & Technical Conference
From Research Prototype to Production
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
ITER – Interlocks Luis Fernandez December 2014 Central Interlock System CIS v0.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
 AUTOMATION  PLC  SCADA  INSTRUMENTATION  DRIVES & MOTORS.
Software Project Management With Usage of Metrics Candaş BOZKURT - Tekin MENTEŞ Delta Aerospace May 21, 2004.
Project Life Cycle.
Beam Interlock System PR b-CTM, October 7th, 2010 Cesar Torcato de Matos.
11/24/2015Dr. SASTRY-PROJ SOFTWARE PROJECT MANAGEMENT By Dr. M V S PERI SASTRY. B.E,Ph.D.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
Managed by UT-Battelle for the Department of Energy SCL Vacuum Control System Upgrade Derrick Williams
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
IAEA International Atomic Energy Agency Presenter Name School of Drafting Regulations for Borehole Disposal of DSRS 2016 Vienna, Austria Program and Quality.
Project Planning Update 13th Technical Board Meeting Luisella Lari Head planner for Accelerator & Senior Scientist May.
23-Nov-1999STScI Projects Monthly Status Review1 of 8 SpaceTelescopeScienceInstitute COS Status Report for period December, 1998 to November, 1999 Tony.
The Planning Phase Recognize the problem MIS steering committee 7. ManagerSystems analyst Define the problem Set system objectives Identify system constraints.
IAEA International Atomic Energy Agency Development of the Basis Document for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
Where Module 04 : Knowing Where the Project Is 1.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
SwCDR (Peer) Review 1 UCB MAVEN Particles and Fields Flight Software Critical Design Review Peter R. Harvey.
Electrical Engineering for NSS - Status and Planning- Thomas Gahl Electrical Engineering Group Leader February 26, 2014.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
Status and Plans for the Target Safety System Linda R. Coney Group Leader – Target Safety and Controls April 1-2, 2015.
Status report on ICS interfaces (Accelerator, Target, NSS, CF) and related activities Miha Reščič Deputy Project Manager, ICS
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
2050AP Project WP5: “Conclusions” UPM Madrid 11 de Octubre 2013.
ESS (vacuum) control system Daniel Piso Controls Division February 20, 2013.
Daniel Piso Fernández Some Ideas about Integration Support Cases and PLC Activities at Controls Division.
ESS Vacuum Standardization
Instrument Construction Phase 1 and beyond Rob Connatser Chief Instrument Project Engineer September, 2014.
WP6 – Monitoring and Evaluation 17th November 2014 Rome.
ELENA installation progress F. Butin / ELENA collaboration.
CNGS Review 15 July 2003 M. Meddahi1 EVM for CNGS Definitions Pre-requisites Application to CNGS.
Cryoplant Controls Installation
Cryomodule test stand at ESS site
Current Status of ITER I&C System as Integration Begins
Cryogenic C&C Scope of work
Lockheed Martin Canada’s SMB Mentoring Program
Vertical Cryostat Kick-off metting
The Bunker Project Overview Zvonko Lazic
ESS Main Control Room & ICS Infrastructure
Bunker Internal Review Welcome & Charge
PSS0 Design & Concept of Operations
Imaging & Engineering STAP Meeting 12th-13th of April 2018
PSS verification and validation
On behalf of protection systems
PSS0 Configuration Management,
Welcome Update on ESS Construction Project
Ola Ingemansson Electrical & Instrumentation Engineer
Machine Protection PLC Based System Verification and Validation Plan
Licensing update ESHAC #7, October 2017
Operation of Target Safety System (TSS)
TSS Management: Procurement & Installation Planning
Atefeh Sadeghzadeh Control engineer – Target safety and control
Mikael Olsson Control Engineer
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
SNS-PPU upgrades the existing accelerator structure
Overview of the TARGET Monolith Rough Vacuum
Stuart Birch On behalf of Protection Systems Group
General Overview of WP 12 ESS Vacuum System
Presentation transcript:

WP7 Plan – Pilot TSS Cost – Risks Linda R. Coney Group Leader – Target Safety and Controls 15 – 16 February 2016

Outline WP7 Project Plan for TSS – P6 Pilot TSS Cost Estimate Project Risks – Exonaut Conclusions 2

WP7 Scope 3 WP7 covers the tasks and activities needed to design, procure, install, test, and commission the Target Safety System (TSS). WP7 leads the Hazard Analysis process for the Target Station to identify events leading to a risk of release of radioactive material – this defines requirements for the TSS & other target systems. WP7 provides support for the development of process controls for target station systems.

Plan for TSS Development Accident Analyses Q – Q Pilot TSS Design – logic, architecture, interfaces Q – Q – MS: PDR of Pilot TSS February 2016 Test Stand 2015 – Oct 2016 Design of TSS Architecture – Includes documentation, interface finalization, & safety analysis of system – MS: CDR of TSS System Q Manufacturing Sept 2017  July 2018 – Supplier chosen Sept 2017 – Factory acceptance test May 2018 – Delivery to site July 2018 Installation July 2018  Oct 2018 Testing Oct 2018  Jan 2019 Integrated testing Jan 2019  Aug 2019  then beam commissioning 4

Schedule 5 Concept PhaseFinal Design Make Phase PDRPDR PDRPDR 2014 Q Q1 Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q3 Q4 Installation & Testing 2019 Q1 Q2 Q3 PDRPDR PDRPDR PDR PDRPDR PDRPDR Site Inst. & Testing CDR PDRPDR PDRPDR Delivery to ESS PDRPDR PDRPDR PDRPDR PDRPDR PDRPDR PDRPDR Target Safety System

Schedule – Milestones First milestone – Pilot-TSS design PDR Current forecast dates for all milestones shown below YTD actuals (Dec 2015): 0.91 M€ SPI: EV/PV = 0.97 (aim > 1; Nov 0.95) CPI: EV/AC = 0.98 (aim >1; Nov 0.98) 6 IDName Current Date A77370PDR – Pilot TSS designFeb 2016 A53380Hazard Analysis for TSS CompletedApr 2016 A53480TSS Logic description completeMay 2016 A53560CDR for TSSFeb 2017 A63480Acceptance of Factory Test for TSSMay 2018 A Delivery to siteJuly 2018 A77850On-site TSS Testing Starts (end of Installation)Oct 2018 A63560On-site tests complete (TSS system tests)Jan 2019 A63580End integrated tests with Target systems and AcceleratorAug 2019

Schedule Performance – EVM Graph 7 Accumulated Scheduled Variance (EV-PV) -22,986 € -25,547 € -8,818 € -38,213 € -57,080 € -46,205 € -29,066 € Accumulated Cost Variance: (EV - AV) -35,150 € -26,028 € -11,857 € -28,917 € -25,608 € -13,982 € -17,570 € Last Month's Scheduled Variance (EV-PV) -14,970 € -2,560 € 13,418 € -29,394 € -18,867 € 10,876 € 17,139 € Last Month's Cost Variance: (EV – AV) -9,929 € 9,122 € 14,219 € -17,060 € 3309 € 11,626 € -3,557 € Controls 30/06/201531/07/201531/08/201530/09/201531/10/201530/11/201531/12/2015 Earned 652,092670, Actuals 687,242696, Scheduled 705,657696, June JulySeptAugOctNovDec

CPI & SPI Trends 8

Major Procurements Safety system cost in P6 Hardware and software for Target Safety System 4.7 M€ Not in-kind contribution Cost estimate 2 train system 1 with PLC, distributed I/O and fiber cables 1 with relay and copper cables 15 shared instruments (9 helium + 6 shaft rotation) Process instruments – based on SNS TPS and discussion with Emerson Control hardware & programming – based on Siemens products. ESS has agreement with Siemens for safety/standard control equipment Racks and Cabinets – based on Rittal Cables – based on web search & internal ESS experience Documentation – based on SNS considering 15 instruments Work – based on SNS proposal & ICS proposal for Pcool control equipment 9

Pilot TSS cost estimate EquipmentSiemens refrenceQnt Price per unit Price (€) Instrument in Utility room Safety Process instrumentation Motor and shaft monitoring other material (small parts, wires,connector,..) Train 1 – sensors, utility room equipment Input cabinet in Utility Room_Train Cabinet 450*450*300 mm (W*H*D) Simatic F-digital input6ES7136-6BA00-0CA SIMATIC PROFINET INTERFACE IM155-6PN6ES7155-6AU00-0CN BUSADAPTER BA 2XSCRJ6ES7193-6AP00-0AA SIMATIC ET 200SP, BASEUNIT6ES7193-6BP00-0DA Mounting rail sectional railwidth 35MM6ES5710-8MA Simatic HMI 7"6AV2123-2GA03-0AX Power supply SITOP 24V/10 A6EP3334-8SB00-0AY Redundancy module for power supply6EP1961-3BA other material (small parts, wires, bolts, circuit breakers, Work (Mounting,..) 12000

Pilot TSS cost estimate 2 11 Main Rack_Train Rack Rital 600/1800/ Mounting rail 160 mm6ES7590-1AB60-0AA0118 3CPU 1516F-3 PN/DP6ES7516-3FN00-0AB Memory Card 24 MB6ES7954-8LF02-0AA Comunication processor6GK7543-1AX00-0XE Profinet switch SCALANS X204-26GK5204-2BB10-2AA Simatic HMI 12"6AV2123-2MA03-0AX Power supply SITOP 24V/10 A6EP3334-8SB00-0AY Redundancy module for power supply6EP1961-3BA PC other material (small parts, wires, bolts, circuit breakers, Work (Mounting,..) Fiber optic-Train fiber optic cable 1500 m to FEB Conduit 1500 m to FEB Fiber Optic cable 3500 m to control room Conduit 3500 m to control room Cabinet in Control room Cabinet 400*800*300 mm (W*H*D) Trapped Key System ??? other material (small parts, wires, bolts, circuit breakers, Work (Mounting,..) Train 1 – rack in room#1, fiber optic cables, MCR cabinet

Pilot TSS cost estimate 3 Output cabinet in FEB_Train Cabinet 450*450*300 mm (W*H*D) Simatic F-digital output relay type6ES7136-6RA00-0BF0196 3Simatic F-digital output6ES7136-6DB00-0CA Simatic digital Input6ES7131-6BF00-0CA0196 5BUSADAPTER BA 2XSCRJ6ES7193-6AP00-0AA SIMATIC ET 200SP, BASEUNIT6ES7193-6BP00-0DA Base Unit type F06ES7193-6BP20-0BF0118 8SIMATIC PROFINET INTERFACE IM155-6PN6ES7155-6AU00-0CN Mounting rail sectional railwidth 35MM6ES5710-8MA Simatic HMI 7"6AV2123-2GA03-0AX Power supply SITOP 24V/10 A6EP3334-8SB00-0AY Redundancy module for power supply6EP1961-3BA other material (small parts, wires, bolts, circuit breakers, Work (Mounting,..) Cabinet for the contactors in FEB Cabinet 400*800*300 mm (W*H*D) Safety Contactor other material (small parts, wires, bolts, circuit breakers, Work (Mounting,..) Train 1 – cabinet in FEB, contactors for ion source

Cost Estimate Total Cost €Total Cost Train 1 HW shown817,989 Cabling – ,000 PLC coding and validation – ,000 Spare parts – ,000 Documentation – ,000 Validation/verification/test – ,500 Train M€ Train 2 (sensors and contactors already included in cost for Train 1) 0.35 M€ Total1.43 M€ 13 Cost for complete TSS depends on results of AA and new safety functions to be implemented within the TSS

Risks and Issues Biggest risk for Pilot TSS – definition of requirements – Finalization system requirements and design depends on completion of accident analysis scenarios – Allocation of safety functions from ESS facility to Target Station to Target systems – SSM requirements applicable to Pilot TSS 14 IDRiskTreatmentStatus 3 Licensing framework for ESS target station is not well defined, or is changed Work with ES&H division to understand SSM documentation and expectations Participate in Safety Advisory Group (SAG) Complete hazards analysis in a timely manner and perform design basis accident analysis Target division engagement in the development of an ESS-wide safety classification methodology Attend SAG meetings Progressing with Accident Analyses Documenting Target hazard analysis process Reviewed and applied ESS safety classification scheme Reviewed proposed content for license 2 SSM application 43 Design and interface information given to CF too late Use the formal documents ICD and ICD-R to communicate the requirements TSS-CF ICD written & reviewed for PDR Regularly meet with CF re. TSS

Summary WP7 developing Pilot-TSS design Timely completion of accident analyses critical for establishing TSS requirements and identifying additional target station SSCs – Analyses depend on effort within all Target system groups, in-kind partners, and ES&H – Accident analyses results will impact safety requirements for Target systems including TSS – Results from accident analyses are likely to require new interfaces between TSS and additional target systems Cost estimate will be affected when additional requirements for TSS come out of the accident analyses 15

Concluding Remarks This concludes the material we have to present Thank you for your time and participation in the review We welcome your comments and advice to help us complete this effort in the best possible way 16