SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project.

Slides:



Advertisements
Similar presentations
The ice machines are available at various capacities and can be placed where needed in the site. Capacities range from 3 to 70 tons per day. The ice is.
Advertisements

Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
ECFA Preparatory Group "Shutdown constraints and radiation and activation effects”. W. Zeuner, W. Riegler, R. Lindner, B. Di Girolamo, G. Corti, C. Schaeffer,
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Remote manipulations / diagnostics in radioactive areas and handling of radioactive material Workshop, Geneva, Switzerland 6 th May 2013 THE REPLACEMENT.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.
Workshop “Vacuum systems of Synchrotron Light Sources“ organized by MAX-LAB & ALBA Barcelona, th September 2005 Instrumentation and Vacuum Control.
Installation to degrease the SPS magnets chambers Leonel Ferreira.
SPS vacuum modification G.Vandoni SPS vacuum modification, 1.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 1.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
Scrubbing Review, 8/9/2015 Paul Cruikshank1. Contents SPS Layout aC factory options Assumptions & Scenarios Transport issues Radiation issues Coating.
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
Radioactive Magnet Facility B /09/2014 TE-MSC-LMF Luis Mora Vallejo Rosario Principe TE-MSC Technical meeting, 4 th September 2014.
ILC TRANSPORT AND INSTALLATION Questions from last CES: Beam height explanation, Transport implications of sloping access tunnels proposed for access to.
CMS Upgrade Workshop, FNAL, Nov 19-21, O.Prokofiev CMS Upgrade Workshop Updated ME4/2 chamber construction costs and prototype Status and plans.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
LIU-SPS, 29 April 2015 Paul Cruikshank1. Variants today: Starting point: Assume same boundary conditions as 15/4/2015 presentation Analysis is for SPS.
Extraction and beamline progress B.Goddard TE/ABT.
Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Horst Breuker Review Oct ELENA Safety and Radio Protection ELENA TDR : Chapter 6; Safety Files in preparation; Descriptive, Demonstrative (Risk.
LIU-SPS, 15 April 2015 Paul Cruikshank1. In the beginning…. First slide that Brennan gave me – everything decided ! LIU-SPS, 15 April 2015 Paul Cruikshank2.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
The integration of 420 m detectors into the LHC
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
18, 19, 20 February 2002 Power Converters for magnets (PBS 1.2.3) R. GENAND SL/PO 1 Power Converters for Magnets –Introduction –Specification Magnet characteristics.
ECR - PSB: New KSW magnet in 16L1 Luis Feliciano, 4 th February.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
SPS movable table Joanna Swieszek, Kurt Artoos (EN-MME) 14/04/2016.
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Facility to coat the SPS magnets with carbon Objective: coat at least 90% of the SPS with a carbon thin film with low secondary electron emission in order.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
BA6 newsRF power Cable list being worked out. BA6 newsLLRF Cable list done, pending check and confirmation.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
Insertion of 2 MBB with new coated vacuum chambers during technical stop week 35 J. Bauche for the SPSU study group, 24 June 2010.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Linac4-PSB 160 MeV connection readiness review
CLIC Handling Engineering Update
HL-LHC IT STRING and Series test of SC link
TE-MSC activities in SPS during LS2
BA6 – crab cavity activities in EYETS
Installation of an Instrument on a CERN machine
Buffer Zones - Status Report
Mathieu, Gabriel, Max, Spyros, Guillaume
C50 Cavity pair Assembly Changes
RWTCS Steering Commitee
B. 163 facility upgrade: work space options in B. 163 and B. 103 F
TE-MSC activities in SPS during YETS
Status with crucial LSS5 kicker transmission line cables
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Magnet electrical and hydraulic (dis)connections for coating
Coldex disinstallation
XFEL Bunch Compressor BC1 and BC2 Vacuum Issues
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 23/01/2019.
Presentation transcript:

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project  Hypothesis of work  Strategies Layouts of Underground Workshops Strategies in 3 or 4 years  Estimates 3 Years Strategy 4 Years Strategy  Conclusion and Next Steps

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 2 Hypothesis of Work  Coating process → Vacuum chambers: no disassembly of vacuum chambers from the magnets to perform the coating (process would take 100 hours x 3 pers. / magnet, so 223, CHF/hour) → Time of coating process: 48 hours, including installation of equipment, vacuum pumping, coating and dismantling of equipment 4 days, including cleaning (1 day), installation of equipment - vacuum pumping (1/2 day), coating (2 days) and dismantling of equipment (1/2 day) → Position of magnet during process: horizontal  Magnets treated → Only SPS main dipoles ≈ 5 km of vacuum chambers (>70 % of SPS vacuum system length)  Time → Duration of shutdown period: 14 weeks of access in the machine, 10 weeks of effective work + start-up and end phases and safety margin  Ressources → Equipment: use of existing vehicles for transport (2 Dumont handling machines + trailers), possibly with some adaptations (No new vehicule) → Manpower: work done mainly during normal working hours, 5 days/week

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 3 Layouts of Underground Worshop Underground Workshop ECX m2 floor ECA5 Underground Workshop ECX m2 concrete screed ECA5 Capacity of workshop: 16 magnetsCapacity of workshop: 24 magnets

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 4 Strategies  Project in 3 years → Cadency: 6 magnets / day (8h / day) → Startup phase: preparation of 300 m2 concrete screed and painting in ECA5 ≈ 3 weeks (15 days) → Total number of days of work: 744 magnets / cadency = 124 days 124 days + 15 days = 139 days days / shutdown ≈ 3 shutdowns  Project in 4 years → Cadency: 4 magnets / day (8h / day) → Startup phase: preparation of 100 m2 floor in ECA5 ≈ 1 weeks (5 days) → Total number of days of work: 744 magnets / cadency = 186 days 186 days + 5 days = 191 days days / shutdown ≈ 4 shutdowns

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 5 Estimate Project in 3 Years

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 6 Estimate Project in 4 Years

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 7 Optional costs Optional Cost type Quantity Unit price Total Type of estimate TE/VSC Additionnal sectorisation of SPS arcs vacuum system (ITL-ICM) New additional vacuum valves + supportsHW1214,000168,000M Cabling (metres purchased - installed - connected) - avg. 500m / VVHW + FSU6, ,000D Control systems linked to additional VV (Pe Pi gauges, elec. Cards, TPG…)HW130,000 D Vacuum chambers modification - installation VVHW + FSU123,00036,000D Sub- total: 294,000 EN/HE Transport / handling equipment 1 new additional transport vehicleHW1700,000 D Sub- total: 700,000 Total:994kCHF

SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 8 Conclusions and Next Steps  Strategy to choose ? → 4 years: - cheaper, but less space in workshop (ergonomics and safety aspects) - Dumont vehicle more sollicitated, but second Dumont as spare in case of breakdown → 3 years: - more expensive but with more space in workshop - 2 Dumont used simultaneously with reasonable cadencies, but could require building a new vehicle (paid by this project ?) - requires to occupy a large part of the machine  interference with other activities during shutdowns  Next steps → Define more precisely the process: to help defining more precisely the time, cadencies… and price of the project → Try to improve cleaning and coating process: improve the tooling to require less space in workshop, decrease time of coating process, comply with radiation protection safety aspects for cleaning (big quantities of contaminated rinsing water)