Summary of the technical stop activities on collimators (w17, 2012) O. Aberle – 07/05/12.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Injection Considerations for Scrubbing Run C. BRACCO, M.J. BARNES, W. BARTMANN, B. GODDARD, M. MEDDAHI, J. UYTHOVEN ACKNOWLEDGMENTS: M. DI CASTRO, M.DONZE,
How to improve operational efficiency ? [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] Beam Commissioning Workshop, Evian Jan 2010.
Tuesday 10 th April - morning Access for:  point 3 Jerome Landaro TCSG one jaw didn't move  point 5 Qps expert on RPMBB.UJ56.RCBXH1.R5  point 6 TCDQ.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
1 Pressure observations at TDI till fill 2158 V. Baglin (27/08/11) CERN TE-VSC, Geneva 1. 2.
O. Aberle, EN/STI/TCD 16 October 2014 WORKSHOP ON R2E, RADIATION AND AVAILABILITY AT THE LHC COLLIMATOR EQUIPMENT AND INTERVENTIONS, OPTIMIZATION OF DOSE/INTERVENTION.
LHC Machine Protection System Review LHC Machine Protection System Review Oliver Aberle13 April 2005 with input from R. Assmann and R. Losito Ensuring.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
Status of North Area Target (TCC2) & prospects EATM 28/07/2015D. Grenier1 Targets (T2, T4, T6 and T10) replaced in 2014 during LS1 (+ 4 spares) Previous.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
LHC progress Tuesday 28 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Preparation for Circulating Beam - Part II Collimators (40') Oliver Aberle o Breakdown of tests foreseen in preparation for beam o Equipment folder: tests.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
MPE Workshop 14/12/2010 Post Mortem Project Status and Plans Arkadiusz Gorzawski (on behalf of the PMA team)
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
Collimator design and operational experience
Wednesday
Review on collimator movement with stepping motors
Machine Coordinators: G. Arduini, J. Wenninger
Wednesday September 14th
MD2036: UFO dynamics studies and UFO fast detection
ATLAS-AFP interlock validation
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Planned activities on collimator for LS1
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Thursday morning – optics correction
Review on collimator movement with stepping motors
Collimator Control (SEUs & R2E Outlook)
LHC Injection and Dump Protection
Summary of Week 16 G. Arduini, J. Wenninger
LHC Morning Meeting - G. Arduini
Week 35 – Technical Stop and Restart
Saturday 28/4 06:30 staring injection and transfer line steering.
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Sunday
Wednesday 03/11 – The Plan Finish electron-cloud program:
(on behalf of the LHC team)
Wednesday 10/5 Cryo recovery until 18:30
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday 24 October hours of 25ns MD
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
Scrubbing progress - 08/12/2012
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Collimation qualification during the first weeks of the 2011 run
LHC - Week 38 Technical stop: Katy Foraz
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Fri :52 Stable beams fill #2536
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Friday 15th February - morning
Tuesday – Morning and Evening
Monday 10th December - morning
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Tuesday
Beam Stability of the LHC Beam Transfer Line TI 8
Presentation transcript:

Summary of the technical stop activities on collimators (w17, 2012) O. Aberle – 07/05/12

Main activities during the last technical stop  TDI.4R8  Collimator roller screw replacement  TIM intervention/observations May 7th, 2012O. Aberle – CWC2

TDI.4R8  TDI.4R8: New x rays have been taken on: Up and downstream beam screen – transition – jaw extremity.  Result: No change since the last scan in January. Stable conditions after the 144 bunches dumping.  The parking settings of TDI.4R8 should be changed from 37 to 55 mm during physics, as in Pt. 2. May 7th, 2012O. Aberle – CWC3

TDI.4R8  Result: No change since the last scan in January. Stable conditions after the 144 bunches dumping.  The parking settings of TDI.4R8 should be changed from 37 to 55 mm during physics, as in Pt. 2. May 7th, 2012O. Aberle – CWC , source , source , tube

Looking at the 2 LVDTs (RU-RU2) Clear symmetric drift of the 2 LVDTs indicating a possible deformation of the right jaw of TDI in point 8. intensity RU RU TDI observations and beam measurements, C. Bracco 130th LMC Meeting held on 25 April 2012 May 7th, 2012O. Aberle – CWC5

Looking at the 2 LVDTs (RU-RU2)  Same LVDT feature in 2011 and However, not seen in 2011, as limits were twice larger (0.5  ) than in 2012 (0.25  ). intensity RU RU TDI observations and beam measurements, C. Bracco May 7th, 20126

Conclusion  We see a drift of the TDI LVDTs mainly during physics  jaw position outside interlocks (±0.25  ) when back at injection setting (already observed last year but tolerances more relaxed)  Symmetric drift for the 2 LVDTs located at the 2 sides of the motors  jaw deformation?  Measurements with beam indicate a possible deformation towards the beam (“safe” side) of the order of 0.5   Angular scan on the cold jaw did not show any evident change.  Not always clear correlation between LVDT drift and beam condition  need more statistic  Not clear correlation between LVDT drift and jaw deformation  need reference measurement with cold jaw (right after TS, no angular scan)  repeat measurements with warm jaw (including angular scan)  Once we define if and by how much the TDI jaw is deformed and the correlation LVDT/jaw  setup thresholds accordingly to insure protection in case of miss-injection (TDI grazing)  Still to be understood the cause of the warming up when the jaws are at 55 mm (high order modes?), are we heating the jaw or the full structure? (N.B. after opening TDI jaws from 20 mm to 55 mm vacuum improved but there was no clear evidence of improvements in heating………) Works ongoing!! TDI observations and beam measurements, C. Bracco 130th LMC Meeting held on 25 April 2012 May 7th, 2012O. Aberle – CWC7

Collimator roller screw replacement  Elogbook 22/04/ :16:45 22/04/ :46:43 00:29:58  Collimator Hardware TCSG.5L3.B1 Collimator stuck; won't drive to injection settings. - The TCSG.5L3.B1 failed to go correctly to injection settings after the collimator setup ( suspected problem with roller screw), and required piquet reset. Normally this collimator should not be included in the active set until the hardware problem is fixed.  Performance loss on axis B. First steps lost during the week end, recovery with simple resetting. Within 3 days the situation was degrading a lot. The axis, and therefore the collimator had to be disabled in parking position after regularly loosing steps.  This triggered a systematic sound check with the TIM in point 3. The noise profile off all 16 out of 18 collimators have been registered, a list of conspicuous collimators has been delivered for further inspection.  In parallel, torque measurements have been performed on most of the collimators, in reducing the motor current until steps are lost.  These values have been compared with original data taken during commissioning campaigns.  All suspicious collimators have been checked and validated for operation in situ. May 7th, 2012O. Aberle – CWC8

Collimator roller screw replacement  The roller screw on TCSG.5L3.B1 had to be replaced due to mechanical wear. There is a clear correlation between a high torque value and the noise pattern.  "SEM observations and EDS analyses of debris found in a roller screw from a LHC TCS collimator table“  The roller screw is still in the RP buffer zone and will be analysed as soon as possible.  A second roller screw was found, based on the noise recording. The torque measurement did not yet indicate problems.  Affected is the axis A on the TCP.6R3.B2. The screw showed signs of wear and was exchanged preventively.  Collimators in Pt. 3, 5, 7 and 8 have been crosschecked with visual inspection. No further case has been found.  All collimators are commissioned and ready for operation. May 7th, 2012O. Aberle – CWC9

Collimator roller screw replacement May 7th, 2012O. Aberle – CWC10 Dust and debris in the end cap and the housing Some dry screws regreased

Collimator roller screw check May 7th, 2012O. Aberle – CWC11 Collimator Functional Name Collimator CERN name TCSG.5L3.B1TCS025 TCDIH.29465TCDI212 TCLIA.4R2TCLIA002 TCP.6R3.B2TCP103 TCSG.6L7.B2TCS019 TCDIH.20607TCDI207 TCTH.4R5.B2TCT301 In combination of acoustic check and torque measurement a good indication for problems can be found, but: TCP.6R3.B2 not detected with torque measurement

Collimator with the problem May 7th, 2012O. Aberle – CWC12

TIM intervention May 7th, 2012O. Aberle – CWC13  Set up and tuning of TIM in Point 3: ~ 5 h. This can be faster with final parameters, around 2 h.  Sound recording of 16 collimators during 6 h (night, no access).  Remote control from the CCC with data analysis in parallel.  Visual inspection with camera will be useful in the future.

TIM exercise - Sound inspection of the collimators in S34 (23/24 April 2012) Microphone Roller screw TCSG.5L3.B1_L_IN_OU T TCLA.A5R3.B1_L_IN_OUT Faulty (the initial one): Normal: TCP.6L3.B1_L_IN_OUT TCP.6R3.B1_L__IN_OUT Suspicious: EN/HE - EN/STI Collaboration EN/HE - EN/STI Collaboration O. Aberle – CWC14 Courtesy R. Folch, B. Feral

Outlook May 7th, 2012O. Aberle – CWC15  Improve the sound and image quality for the TIM, very powerful tool for the future.  Reference sound recording of all collimators.  Improve the accessibility to the screw (cap).  A regular check during long breaks and shut-downs with re-lubrication of the screw.  Automatic motion cycles during LS1 to be planned.