Lau Gatignon / EN-MEF. L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 2 * Introduction * Present and foreseen activities in.

Slides:



Advertisements
Similar presentations
Lau Gatignon, EATM, 7 October  The T9 and T10 lines have been running smoothly from mid July and the T11 beam started up very smoothly for CLOUD.
Advertisements

Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
16.Feb.2005MC meeting, LBNL1 CERN infrastructure A.Fabich, CERN AB-ATB All information available at
1 FUTURE EXPLOITATION OF THE EAST AREA Infrastructure and Equipment - Civil Engineering issues. Jonathan Carr – GS / SE.
Energy Saving Jean-Paul Burnet & Konstantinos Papastergiou CERN Technology Department | Electrical Power Converters.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
(1/15) 08/05/13 – RadWG meeting J. Mekki M. Brugger PS East Area Update Outline Layout updates of the facility Conveyer options Mock-up preparation and.
SHMS Optics and Background Studies Tanja Horn Hall C Summer Meeting 5 August 2008.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
Radiation Test Facilities G. Spiezia. Engineering Department ENEN Radiation tests facilities  Radiation test in the accelerator sector  External facilities.
Status and possibilities for the irradiation facility in the PS East Hall Michael Moll, Maurice Glaser 10 March 2010 – IRRAD Working Group - some notes.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
East Area Day, 1 February 2012 Lau Gatignon / EN-MEF.
The East Area Rende Steerenberg, ps/op PS-Days 2001 Evian.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
CNGS PROJECT STATUS D.Autiero 21/5/2003 General status 2003 Project review CNGS upgrade.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
East Area, M2, K12 Lau Gatignon / EN-MEF, EATM
Reorganization of East Area Beam Lines 2 nd Status Report at IEFC Workshop L.Gatignon, 11/02/2010 EN.
N_TOF Technical Report INTC, CERN 21 May 2007 P. Cennini AB-ATB n_TOF Technical Coordinator Status of the old Target Removal Status of the old Target Removal.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
10.March.2004, phone A.Fabich 1 Technical drawings of TT2A and adjacent galleries Detail – CDD number Overview surface, ----PDP Overview TT2/TT2A/ISR,
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
The CNGS Target Station By L.Bruno, S.Péraire, P.Sala SL/BT Targets & Dumps Section.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
NA61 11 October 2010Light Ion for NA61/ S. Maury1 Light Ion in SPS Foreseen to have primary Ar beam physics in 2012 Nothing runs in 2012 NA61 duty cycle.
PSB dump replacement 17 th November 2011 LIU-PSB meeting Alba Sarrió.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
EAR2 Beam Line Report on the Status C. Weiss EAR2 Beam Line - Report on the Status1.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
M.Moll, M.Silari, H.Vincke – 3.April Feedback  In total 134 forms filled:
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
Dec7,2007 ie-FP7 Test Beams for detector R&D at CERN The PS East Area The SPS North Area Irradiation facilities.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Application of FLUKA to fixed- target programs at CERN: a short, not exhaustive selection M. Calviani (CERN) With contributions from: M. Brugger, F. Cerutti,
Lau Gatignon, EATM,  The construction of the CHARM and IRRAD zones is completed and operation at nominal intensity started yesterday.
M.Moll, M.Silari, H.Vincke – 3.April Mixed field irradiation -- Who answered ?  In total 36 forms filled / 34 persons answered: 38% 62% CERN:
 Based on 2+2 Roman Pot Stations on each side of ATLAS at ~ 240 m from the Interaction Point  Aim in Run 2 at measuring the total cross section and.
Radiation Protection Considerations for the CDR Helmut Vincke DGS-RP.
Mixed field irradiation -- Who answered ?  In total 36 forms filled / 34 persons answered: 38% 62% CERN: mainly LHC related topics CERF: beside LHC topics.
Status of Contributions, Draft Budget Request for 2005 and Outlook for the Longer Term Future Martyn Davenport 8 TH October 2004 CAST FRC-D
Reorganization of East Area Beam Lines Status Report at ATOP meeting L.Gatignon, 06/03/2009 EN.
18, 19, 20 February 2002 Power Converters for magnets (PBS 1.2.3) R. GENAND SL/PO 1 Power Converters for Magnets –Introduction –Specification Magnet characteristics.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Present status of production target and Room design Takashi Hashimoto, IBS/RISP 2015, February.
RF separated beam and other beam issues Lau Gatignon, COMPASS workshop, 22 March 2016.
PRESENT AND FUTURE TEST FACILITIES FOR HIGH- INTENSITY TARGETRY CERN I.Efthymiopoulos, CERN with input from Jacques Lettry & Rende Steerenberg.
Proton and neutron irradiation facilities in the CERN-PS East Hall Maurice Glaser and Michael Moll CERN- PH-DT2 - Geneva - Switzerland 6 th LHC Radiation.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Upgrade of the irradiation facilities in the PS East Hall Maurice Glaser, Michael Moll 30 April 2010 – PH-DT steering board meeting activities are part.
EXPERIMENTAL AREAS CONSOLIDATION EACONS part – early draft from comments.
GIF++ implementation Adrian Fabich, Sylvain Girod, EN-MEF-LE Technical meeting with Supplier of Irradiator, 3 rd October 2013.
1 How Many Protons can we afford to loose in the PS ? Thomas Otto SC-RP.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
East Hall under construction
4th FRC meeting, Antti Onnela, CERN-PH-DT
Joint Meeting SPS Upgrade Study Group and SPS Task Force
B. 163 facility upgrade: work space options in B. 163 and B. 103 F
East Hall under construction
W. T. Weng Brookhaven National Laboratory
Present and Future test facilities for High-intensity Targetry CERN
Experimental Areas – LS2 planning
Presentation transcript:

Lau Gatignon / EN-MEF

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 2 * Introduction * Present and foreseen activities in the East Area CLOUD AIDA, IRRAD plans Test beam activities * Reminder of proposed new layout * Costs for operating the East Area for 20 more years * nTOF Operation ( ) * Summary and conclusions

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area :Premature end of run due to F61S.BHZ01 failure (type MNP23) 2005:Construction of new MNP23 and Q120 magnets 2006: Three new MNP23 magnets burned out, DIRAC and IRRAD runs lost 2007:Replacement of F61S.BHZ01 by MCB. Works well but loss of cycle efficiency. Presentation by W.Kalbreier at ABOC/ATC days, underlining bad shape of all East Area magnets and difficult conditions for their maintenance 2008: Installation of XDWC and scintillators in test beams. Great improvement! 2009:Presentation of conceptual layout for new East Area at IEFC workshop 2010: Start-up of East Area delayed by > 2 weeks due to MNP23 failure in T9 Presentation of detailed layout and cost for EA upgrade at IEFC workshop. Abandon the idea of PS2 with a new experimental area. Request to investigate costs for 20 more years of operation. Approval of AIDA 2011: Presentation of the global project and costs.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 4 * 5 Beam lines: T7 (IRRAD), T8 (DIRAC), T11 (CLOUD), T9+T10 (test beams) * T7 no longer used as test beam, only IRRAD. But difficult access (stop whole EA), marginal shielding and rates, far too limited in space * DIRAC is expected to stop before the long shutdown. Then move to SPS or GSI? (No details known yet) * CLOUD is considered to have a very interesting physics program * There is a need for test beams at energies below the NA. Also the NA is heavily overbooked and the East Area can accommodate for a fraction of those requests, if the maximum energy is high enough. * The East Area is used as much as ever!

CLOUD (T11)

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 7 IRRAD-1 IRRAD-6 SHUTTLE

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 9

WHCAL MUON TESTS IN T7 AREA

NA62 GIGATRACKER TEST

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 12 * The AIDA project started on February 1 st, 2011 and had a kick-off meeting at CERN from 16 th till 18 th of February. * The AIDA proposal includes an upgrade of the IRRADiation facility in the East Area. Their budget of 430 kCHF covers 1 personnel plus some financial EU contribution to the installation. Normally one expects this to be accompanied by a CERN contribution. * The detailed technical studies of a new layout require this new staff and preliminary investigations have started only very recently. * On top of this a substantial sum (~1.5 MCHF) has been provisioned for the IRRAD facility (mixed fields) in the R2E project. * R2E hopes to use the new facility as soon as possible, preferably immediately after the long shutdown (2014). Until then R2E will use H4IRRAD and CNRAD, but on the longer term these are insufficient. * Initial studies are based on the assumption that DIRAC will stop before this long shutdown.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 13 * Mixed Field Irradiations: Important for the present LHC operation and for the LHC Upgrade. Need space for much larger volumes and more infrastructure than in the T7 facility. E.g. irradiations of power supplies. * Proton irradiations: Beam flux can be accommodated for if no more DIRAC running. Beam characteristics compatible with present DIRAC beam parameters. * Proton and mixed field can often use the same protons! * Requires dismounting of DIRAC (PH funding?). Need formal decision on DIRAC future.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 14

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 15 [KCHF] 1.Remote controlled sample positioning systems180 (less if shuttle can be reused) 2.Cabling and instrumentation of irradiation zone150 3.Control rooms and control equipment KCHF Additional technical support during construction: 0.5 FTE Radiation Monitoring (RP)?? in EAST HALL plan ?? Access and Emergency Exit?? in EAST HALL plan ?? Shielding?? in EAST HALL plan ?? Ventilation?? in Mixed Field Facility plan?? Preliminary estimate for proton facility received from PH on 14 th of March To be studied and validated in ATS

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 16 [KCHF] 1.Target Station (design & construction, vault,…)300 2.Shielding (only new and partly mobile part, fixed part and dump will be recuperated) Cooling & Ventilation250 4.Services (Cabling, Cooling, Control)150 5.Radiation Test Infrastructure (test stands, remote control, train, SAS, etc.) Access Control100 6.Monitoring (RP, RadMon, DAQ)150 7.Installation Support (FSUs) 150 Total: 1500 Preliminary estimate for mixed field facility received from PH on 14 th of March To be studied and validated in ATS 1500 kCHF provisioned in R2E project planning

 Use fewer types of reliable magnets with spares  Reduce roof shielded areas and ease access to equipment  Keep radiation restricted to upstream areas as much as possible  Keep T8 beam and DIRAC installed as it is until the end of DIRAC, or for IRRAD in case they take over the DIRAC location  Replace SMH1 and F61S.BHZ1 by two MCB magnets in PPM mode, i.e. no more splitter (F61S.BHZ01 replacement already done).  Could also serve IRRAD as now, through air, however not from ZT7.BHZ01 but from F61S.BHZ02  Design new beam(s) to 1 (or 2) “North target” marguerite(s) - two decoupled beams, but at the cost of cycle efficiency - two beams coupled by “wobbling station”, coupled but higher cycle efficiency  Test beams can provide pure hadron and muon secondary beams up to 15 GeV/c and pure (> 95%) electron beams from  conversion (up to about 10 GeV/c) Inspired by and similar in spirit to West Area rebuild in the end of the 1990’s!

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 18

L.Gatignon, IEFC, 11 February 2010 Reorganisation of East Area Beam Lines 19 OPTICS FOR “T9 ++ BEAM” – UP TO 15 GeV/c SECONDARY BEAM

PS zone Primary zone Sec. zone Open DIRAC Old layout: New layout: The shapes are made as overlays on the old, respectively new layout drawing, on the same scales

* Compatibility with requirements from DIRAC/IRRAD and CLOUD * More flexible and better test beams, but (effectively <<) 1 less Higher top momenta, small production angles, choice of particle type * Only use agreed ‘healthy’ magnets with sufficient spares All magnets and rectifiers exist – reduced cost * Primary beam is dumped almost immediately after target High (also induced) radiation levels restricted to minimal areas * Very restricted number of magnets is under (less heavy) roof shielding The ones in a limited zone following the primary area have only a thin roof shield. Many have no roof shielding.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 22

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 23 ITEMGROUPCOSTFTECOMMENTS Transport & handlingEN/HE months x 3p + 10 kCHF material Rectifiers45 Magnets & servicesTE/MSC250 Vacuum layoutTE/VSC9000.2Revised upward, includes new control etc. AccessGS40 SurveyBE/ABP0.4 Radioprotection Project coord & mgmtEN/MEF1 Others (BI, gas, etc)800.3 DesignerEN/MEF506 months for CATIA drawings TOTAL15553

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 24 ITEMGROUPCOSTFTECOMMENTS MagnetsTE/MSC kCHF if old layout RectifiersTE/EPC28005 Electrical infrastr ACEN/EL1650Transformers date from 1961! Electrical infrastr DCEN/EL130 Air conditioning building EN/CV985 CranesEN/HE600Keep/upgr 40 t crane + ‘palan’ Ventilation prim. zonesEN/CV260Assume DIRAC = primary area Access control buildingGS70 Controls upgradeBE/CO Cesar like in North Area Sub-total consolidation6735~10

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 25 ITEMGROUPCOSTFTECOMMENTS Magnet coolingEN/CV (i.e. 0.2 design, 0.2 superv, 0.1 eng) Separate cooling primary areas, but up to 5 o warmer water For cooling tower Magnet cooling improvementEN/CV500 To avoid increase of cooling water inlet temperature by 3-5 o C Beam stoppers & margueritesEN/STI5003New marguerites to be studied 1 FTE can be a fellow Control rooms consolidationEN/MEF120ALGECO barracks Asbestos?DGS/SEE~ 200Only obligatory parts, tbc Sub-total Sub-total Consolidation

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 26 * Consider as an option the remedial works on main roof and external walls, not touching false roof (avoid asbestos removal), including re- sealing of al junctions and joints with external envelope to meet relevant air tightness specifications and best practice * Do not improve insulation otherwise as costs would exceed benefits and the implications would be complicated and lengthy in time. * Consider double windows.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 27 ITEMGROUPCOSTFTECOMMENTS Civil engineering issues, i.e. re-cladding of the roof double windows incl rooflights) GS/SE<< 2200 Guess ~ 1.5 MCHF 1.5To be balanced vs. energy saving. Need full survey. One project eng. plus 0.5 draughtsman Replacement PVC cablesEN/EL1500From rectifier to TB. ~ 2100 if old layout Upgrade to RAMSES-IIDGS/RP300Already in consolidation Various items~200 Sub-total Consolidation total Layout change15553 GRAND TOTAL kCHF for RAMSES-II Excluding IRRAD transformation and DIRAC dismounting

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 28 * The duration of the work in the zone for the layout transformation is estimated to be a year. The transformation from DIRAC to IRRAD comes on top. * Most of the consolidation work can be done in the shadow of this and/or in subsequent shutdowns. * The long shutdown would fit ideally from the user perspective, but probably the timing would be driven by the MTP.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 29 Nuclear waste transformation Nuclear astrophysics Fundamental nuclear physics

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 30 Achieved: 1.194E19 p Planned: 0.9E19 p Integrated intensity planned and measured for 2010: Thanks to Work Sector of Type A: Neutron capture cross section measurements of 241 Am (nuclear waste transformation)

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 31 nTOF expects to accumulate protons on the nTOF target, which should allow them to advance on several approved proposals. Some innovations: First use of  MGAS for measuring 33 S(n,  ): isotope for possible medical applications First use of large area pVCD diamond for  (n,  ) beyond the MeV frontier First use of  MGAS for measuring  (n,f) at high energy: 240,242 Pu First ever measurement of the radioactive 63 Ni  (n,  ) Some challenges: The use of new (or combinations of) detection systems The unprecedented aimed accuracy for the 238 U(n,  ) measurement 2-3% overall accuracy between thermal and 1 MeV!

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 32

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 33 Flight path length 20 m at 90 o angle → higher flux, reduced t o flash

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area Neutron fluence for neutron-induced fission and/or capture measurement on small 20 m 7-8*10 6 n/cm 2 /pulse >20 MeV 8-9*10 5 n/cm 2 /pulse 2. Testing of active electronic equipments for LHC and other m >20 MeV 8-9*10 5 n/cm 2 /pulse 1 Pulse every 3 sec → 5-10*10 10 n/cm 2 /week 3. Passive irradiation of (small) equipment in high fluence m 1-2*10 10 n/cm 2 /pulse 1 Pulse every 3 sec → ~ 3*10 15 n/cm 2 /week

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 35 * A new design of the East Area beams exists and the transformation costs just over 1.5 MCHF plus 3 FTE. * However, to operate the area for two more decades in correct conditions an additional spending of about MCHF seems required plus additional 15 FTE. * This does not include the resources and time needed for DIRAC dismounting and IRRAD upgrade. * The project would need one year of installation time and would allow much safer and correct exploitation of the area and would provide better quality beams. * The East Area is already becoming increasingly popular and seems essential to satisfy the requests of test beam users, the irradiation facility and CLOUD. * Also at the PS, nTOF has an active and successful program, in the past, at present and also for the future.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 36 O.Aberle, V.Baggiolini, C.M.Bernard, Y.Bernard, J.L.Blanc, D.Bodart, Y.Body, Y.Bonnet, H.Breuker, M.Brugger, M.Calviani, J.Carr, D.Chapuis, G.Dore, G.Dumont, C.Griggs, J.Hansen, W.Kalbreier, M.Lazzaroni, G.Le Godec, P.Lelong, F.Loprete, A.Manarin, A.Masi, R.Molay, M.Moll, B.Morand, R.Morton, R.Necca, M.Obrecht, Th.Otto, J.Pedersen, S.Pelletier, E.Perez, B.Pichler, O.Prouteau, C.Rembser, S.Roesler, J.Spanggaard, R.Steerenberg, M.Tavlet, D.Tommasini, G.Vandoni, M.Widorski, Th.Wijnands, …. With apologies to those that I may have forgotten

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 37

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 38

L.Gatignon, IEFC, 11 February 2010 Reorganisation of East Area Beam Lines 40 SECONDARY BEAM OPTICS FOR “T10 ++ BEAM” – UP TO 12 GeV/c

PS zone Primary zone Sec. zone Open DIRAC Carefully studied by Thomas Otto / RP (then) Side shielding thickness 6 to 6.4 m (as now) 2.4 m roof shielding, i.e. 0.8 m Fe m Concrete Need ventilation (cf nTOF target area) Optimise entrance chicane Thickness of shielding 2.4 m (as shown before) Height of walls > 4 m to reduce sky-shine No roof shielding required Optimise access chicane Optimise target design (shielding vs intervention time) OK as it proposed

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 43  Improved building insulation could save ~265 kHCF/yr  However, the civil engineering implications to achieve this are huge in time and costs, therefore not obviously economical.  This will be aggravated by complications due to asbestos issues if work is done on the false roof and/or the walls. Complicated, long and expensive. Need to work at 20 Pascal under-pressure, etc. Co-activity implications.  The asbestos situation in general is not critical and there is no obligation to intervene (apart from items touched by the works – new MTP), except for - the floors of the two galleries below the roof - some tubes which contain asbestos. Total cost for those interventions ~ 200 kCHF (to be confirmed).  We therefore propose to limit ourselves to consolidate the status quo of the building and some simple improvements where appropriate.  For heating one could consider local systems (e.g. in control rooms)  A full building upgrade (+asbestos removal) requires a full study.

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 44

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 45

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 46

L.Gatignon, IEFC Workshop, 22 March 2011What Future for the PS East Area 47