Status of the Solenoid Status of procurement Plans for transport Storage and tests on arrival at CERN Installation in the ISOLDE Hall Location Footprint.

Slides:



Advertisements
Similar presentations
Advanced Implantation Detector Array (AIDA): Update & Issues Tom Davinson School of Physics & Astronomy The University of Edinburgh presented by Tom Davinson.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Mu2e Solenoid System Status. Mu2e Experiment 9/23/20132 Production Solenoid Transport Solenoid Detector Solenoid Production Target Collimators Stopping.
COBRA Magnet Test Milestone AssemblyDesignManufactoring DesignAss.TestWinding & Cryo. Deliv. PSI Test Platform Calibration Mapping device.
P.-R. KettleMEG-Review February MEG Beam Line Studies  E5 Z-Branch NOW !!! NOW !!!
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
Status of the External Solenoidal Spectrometer for the TSR Robert Page Why an external spectrometer? Solenoidal spectrometer Baseline design parameters.
ISOL-SRS project.
Downstream PID Review Alan Bross MICE CM 16 October 8, 2006.
Upstream PID Review Alan Bross MICE CM 16 October 12, 2006.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
We are Here! Gluex Collaboration Meeting May Engineering Status - Presented by Tim Whitlatch1.
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
F-595 Chiller contract report Jose Botelho Direito EN/CV/DC Thermosyphon cooling workshop §5 Thursday, October 20, 2011.
John LeRose March 12, A Program of three “projects” to assemble the Super BigBite Spectrometer for a series of experiments in Hall A There is a.
PH Dept News Long shutdown 1: Baseline Project Project Leader Freddy Bordry Injector shutdown Dec 2012-Mar 2014 means 1 year stop for ISOLDE Physics LS2.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
Thia Keppel 6/4/13 Hall A Update. Near term accelerator schedule – same as last meeting Accelerator Run II: Beam in hall 3/2014, or maybe as early as.
NIKHEF B-field monitors Paul Balm November 11 th, 1999.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
MICE Phase 1 Koji Yoshimura KEK June
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
Lucie Linssen, PH senior staff meeting 23 Nov ’05 slide 1 EUDET Links: Public EUDET pages: Internal EUDET pages:
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Upgrade projects and APT update DT-LHCb coordination meeting 28 September 2015.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
Maria J. G. Borge Beam Lines for HIE-ISOLDE. Status of HIE-ISOLDE 2 May 2010: 34 LoI submitted 1 Nov 2012: INTC endorsed the increase of 2 GeV-proton.
Long DB Si- telescope Integration of a Si-telescope in the HIE ISOLDE long diagnostic boxes 21/09/2015LDB Si-telescope1.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
SBS Magnet and Support Status Robin Wines June 2013.
SPOKESMAN’S UPDATE K. Long Imperial College London/STFC.
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
CLAS12 – CND PARAMETERDESIGN VALUE Detector typeBarrel of scintillators Angular coverage40 o to 120 o Number of radial layers3 Number of azimuthal segments48.
Maria J. G. Borge 10th November 2015 News of the Group Courtesy of M. Huyse on behalf of IS557.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
CERN Neutrino platform 24 th July, 2014 S. Bertolucci CERN.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 16, 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
PH Department News Discussion with management
Completion and Pre-Exploitation Costs for the Initial ATLAS Detector
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Update of experimental hall in Japanese mountain site
Target and Horn status report
The ISOLDE Solenoidal Spectrometer project
Status of Solenoidal Spectrometer
Far Detector Activities Late 2017 – Early 2018
Sub-Detector Assembly Area Summary of discussion at ALCW2015
X-ray Pump-Probe Instrument
HIE-LINAC status report
66th ISOLDE Collaboration Committee meeting
PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100%
East Hall under construction
Presentation transcript:

Status of the Solenoid Status of procurement Plans for transport Storage and tests on arrival at CERN Installation in the ISOLDE Hall Location Footprint Shielding Timeline Robert Page

collaboration First meeting 29 th September 2015 Peter Butler, Robert Page, David Joss Liverpool Sean FreemanManchester Mike Cordwell, Alan Grant, Marc Labiche,Daresbury Ian Lazarus, David Sharp, John Simpson Tom DavinsonEdinburgh Riccardo RaabeLeuven Janne PakarinenJyväskylä Ben KayArgonne Lolly PollaccoSaclay Maria Borge, Magdalena Kowalska,ISOLDE Karl Johnston, Fredrik Wenander

Solenoidal spectrometer concept DSSDs with ASIC readout. x: 128 × 0.95 mm, y: 11 × 2 mm

Status of magnet procurement Magnet funding awarded (STFC/UoL) Magnet available from Brisbane (UQ) OR66 4T ex-MRI magnet “Active shield” reduces stray field Installed February 2003 Discharged then warmed ~2013 UoL received draft contract from UQ Contract with UoL Procurement To be delivered & paid by 31/3/2016

Status of procurement

Plans for transport Discussed requirements with Siemens Purchased shock log device Discussing with UK shipping company Details of Brisbane company Despatch December 2015? Transportation ~40 days? Delivery address at CERN needed

Storage and tests on arrival at CERN Special area for commissioning,... Commissioned by Siemens? Will need to be cooled (6500 l He) Field mapping Shielding tests KU Leuven have offered effort Meeting Thursday to discuss details

Installation in the ISOLDE Hall >17 t magnet, 10 t crane => skate

Footprint

Argonne magnet support structure

Installation in the ISOLDE Hall 10 M 7 M 2 T 2T Layout from Yacine Kadi Beam transport calculations will be required

Shielding Contacted Davide Tommasini He will perform shielding calculations CAD layout of ISOLDE Hall sought Siemens field maps provided to DT

Field maps

Timeline Magnet leaves Brisbane December 2015 Arrives CERN January/February 2016 Magnet commissioning & field mapping Move into ISOLDE Hall – when? Construct shielding – when? Preliminary physics experiments 2017/18 – Argonne’s prototype detector available – Leuven TPC plans Early 2019 – commission new Si detector

Some ISOLDE Hall logistics Magnet to be in place before 3 rd beam line 3 rd beam line supports will be moved Magnet initially downstream of existing detectors on 2 nd beam line? Move detectors to 3 rd beam line when ready Move magnet and triplet to final positions Later think about move to TSR Hall