A. Perin, TE/CRG, DFBA LSC 14.06.2013 Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation.

Slides:



Advertisements
Similar presentations
Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.
Advertisements

O. Pirotte, A.Perin, TE/CRG, 4 th LHC Splice Review, Page 2 4 th LHC Splice Review, July 22-24, 2013 O. Pirotte (TE-CRG), A. Perin (TE-CRG)
Improved anchoring of SSS with vacuum barrier to avoid displacement Ofelia Capatina (speaker), Katy Foraz (coordinates all the activities), Antonio Foreste,
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
Vacuum, Surfaces & Coatings Group Technology Department Cleanness of the 3-4 cold beam lines Outline:  History: Status of 2009 cleaning  Foreseen and.
New HV test specification for the LHC N. Catalan for the EI section.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Quality control of LHC electrical interconnections to be produced during the 2009 shutdown Since the functional properties of the LHC electrical interconnections.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
Overview of SMACC-QA 1.Recall of SMACC-QA organization 2.Tuning the procedures 3.Main results from the QC teams 4.Auditors findings Ranko Ostojic 23 July.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
Technology Department Second LHC Splices Review Review of actions from last review List of recommendations of the first review Status Category A.Various.
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
Technology Department 1 Visit to Hall 180: Presentation of the consolidation process Third LHC Splice Review, November 12, 2012.
TE/MPE/EE Short ‘Halfway’ Update ELQA – LS1 Activities MPE/The Electrical Engineering section Knud, on behalf of TE/MPE/EE – 20 September LSC Reminder:
Fourth LHC Splices Review Quality Assurance Review Review of actions from 3 last reviews NB : 8 non-closed ones from 1 st review 5 non-closed ones from.
Third LHC Splices Review Review of actions from 2 last reviews Double shunt on quadrupole bus Insulation system Spiders and lyras electrical insulation.
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
A. P. AT-CRG, 21 October MP3 21 October 2009 Gas flow control valves for current leads brief overview A. Perin, TE-CRG.
Fourth LHC Splices Review Quality Assurance Review Introduction Why this 4 th review ? Committee, mandate Questions to the reviewers Overall Quality Assurance.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project … Courtesy ….
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
ABTEF Meeting, V. Namora Quality Assurance in the Superconducting Magnets and Circuits Consolidation (SMACC) project.
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
MPE Workshop for LS1 / 22 & 23 Nov  DFB Instrumentation Upgrade  Cabling Issues  R2E Consolidation  Current Lead Insulation Project  DFB Instrumentation.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
MSC Technical Meeting 29 August 2013 Overheated QBBI.A21L6 F. Savary with contributions from N. Dalexandro, H. Prin, C. Scheuerlein, P. Voisin.
A. Perin TE-CRG, 06 April LMC 08 April 2009 Consolidations related to pressure protection on DFBs and DSLs A. Perin, TE-CRG.
LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Third LHC Splices Review SMACC Organisation Scope of work (What’s new since Nov 2011) Organization chart update Human resources Budget Unforeseen? Unexpected?
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
SMACC Eighteenth report [20 min] 07/02/2014
First LHC Splice Review Introduction
SMACC Tenth report [15 min] 13/09/2013
LEP cryostat Procurement strategy and plans
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
CRG-TM: LS1 projects review
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
Update of cryogenic activities
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
LS1 Committee January 24th, 2014
LHC Dipole Diode Insulation Consolidation Review (I) INTRODUCTION
LHC-TS3 Coordination meeting #3
Consequences of warming-up a sector above 80 K
Reinforcement of the LHC Dipole Diodes Insulation during LS2
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
Consolidation of the dipole diode insulation Technical aspects
Overview & baseline of LS2 and roadmap for CRG
K. Foraz on behalf of OSS members
LHC Machine Advisory Committee Meeting no. 19, June 2006 DFB status
Shortening the long RQF/RQD busbar segments in points 1 and 5
Presentation transcript:

A. Perin, TE/CRG, DFBA LSC Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation team: S. Atieh (EN-MME), P. Chambouvet (TE-CRG), J.M. Debernard (TE-CRG), O. Pirotte (TE-CRG), A. Lees (TE- CRG), J.-P. Tock (TE-MSC), R. Principe (TE-MSC), F. Savary (TE-MSC), D. Duarte Ramos (TE-MSC), C. Scheuerlein (TE-MSC), S. Heck (TE-MSC), D. Lombard (EN-MME), J.-F. Poncet (EN-MME), M. Bernardini (EN-MEF), K. Foraz (EN-MEF), R. Girardot (TE-CRG), P. Cruikshank (TE-VSC), J. Finelle (TE-VSC), V. Baglin (TE-VSC), S. Triquet (TE-MSC), Giulia Papotti (BE-OP), F. Morell (TE-CRG)

A. Perin, TE/CRG, DFBA LSC Page 3 Outline Feedback from first operations Global Status Current issues and how we cope with them Conclusions

A. Perin, TE/CRG, DFBA LSC Page 4 Main work planned for LS1 on DFBAs Shuffling module High current module SHM-HCM splices CL – busbar splices (6x) Essentially same type as magnet-magnet Variant based on magnet-magnet Lyras (only on right side) CL line

A. Perin, TE/CRG, DFBA LSC Page 5 Summary of splice work in DFBAs for LS1 During LS1 several type of consolidation will be performed on all DFBAs. Non busbar system consolidations will include (mainly): flexible hoses in the jumper and safety disks. Consolidations on the 13 kA superconducting circuits Consolidation of the 13 kA splices:  135 splices  14 "standard" DFBAs, 2 special cases DFBAP and DFBAK Consolidation of the lyras on the right side shuffling modules

A. Perin, TE/CRG, DFBA LSC Page 6 First feedback from initial operations Work organization and sequence ok: thanks to all !!!! Coordination tools (web site, schedulesm dashboards, LMCO, etc.) ok Durations and estimated personnel: globally ok, most critical operations Busbar consolidation Consolidation of CL line can interfere with other operations Special operation on DFBAK proceeds very well (thank to the team!!!) : no need to remove the High Current Module! Unplanned issues: Delay in the delivery of support for vacuum valves: no major impact until know by rescheduling/anticipating mechanical work Problem with busbar preparation (broaching): cf slides, shunt installation operations halted since 24 May (splice task force approved solution being implemented, restart 24 June) Short to ground in HCM-LCM IC (not impact on 13 kA splices)

A. Perin, TE/CRG, DFBA LSC Page 7 Baseline dashboard Tracking global dashboard

A. Perin, TE/CRG, DFBA LSC Page 8 Global status: Up to and including access to splices: on time, access to 24 splices done Shunt installation stopped after consolidation of 12 splices (18 shunts) Also website for daily updates:

A. Perin, TE/CRG, DFBA LSC Page 9 SHM to HCM interconnection Sequence so far as planned Some difficulties due to geometry (manageable) Reached "ready for shunt installation" step.

A. Perin, TE/CRG, DFBA LSC Page 10 Pigtail to busbar interconnections Sequence so far as planned Reached final leak test step. Some difficulties due to geometry (manageable)

A. Perin, TE/CRG, DFBA LSC Page 11 Special SHM-HCM interconnection of DFBAK No transport of HCM Splices fully consolidated Welding being done

A. Perin, TE/CRG, DFBA LSC Page 12 R. Principe, TE-MSC Broaching is used to prepare the busbar side surfaces before brazing the shunts

A. Perin, TE/CRG, DFBA LSC Page 13 R. Principe, TE-MSC

A. Perin, TE/CRG, DFBA LSC Page 14 R. Principe, TE-MSC

A. Perin, TE/CRG, DFBA LSC Page 15 R. Principe, TE-MSC A. Lees, TE-CR Calculations performed Buckling of side walls Stress in solder Support tooling Can explain the observed result used for improving the tooling R. Principe, TE-MSC A. Lees, TE-CR

A. Perin, TE/CRG, DFBA LSC Page 16 R. Principe, TE-MSC Broaching tests with reduced chip thickness (was approximately 250 for failed one)

A. Perin, TE/CRG, DFBA LSC Page 17 R. Principe, TE-MSC A. Lees, TE-CR Measures to be taken

A. Perin, TE/CRG, DFBA LSC Page 18 Analysis & improvements on broaching operation The problem was caused by: Too high force applied for broaching, due to too thick cut and/or geometry of busbars Non full-area support under the U-part Measures to solve the issue Improve the supporting tooling Reduce the thickness of the cut/chip to reduce force (increase the number of steps) Check the geometry Prepare the busbar to fit in acceptable geometry. Validate geometry. Limit the applied force (applied pressure) Improve traceability and process control Measures validated for re-start of work by the Splice Task Force of Work can restart. Date defined by delivery of new tooling: 24 June

A. Perin, TE/CRG, DFBA LSC Page 19 Non conformity in electrical insulation in DFBAK ELQA at cold ok ELQA at room temperature found a degraded insulation in circuit RCSA56B2 (spool mid point). NC EDMS approx. 2-4 kOhms to ground approx. 6.5 m from current voltage tap. No probelem to other circuits. Approximately area of HCM-LCM interconnection determined by ELQA Vtap Identified problem area interconnection

A. Perin, TE/CRG, DFBA LSC Page 20 IC between HCM and LCM: DFBAK RCSA56B2 (spool mid point), env. 2-4 kOhms vers la terre pas vers les autres env. 6.5m depuis le Vtap Cut (d 135) Cut (d157) Cut (d 175)

A. Perin, TE/CRG, DFBA LSC Page 21 Observed damage to the RCSA56B2 busbar Picture G. D'angelo location of damage IC was opened, sleeves cut Origin of problem confirmed by ELQA team Damage to insulation due to contact with metal edge Picture G. D'angelo

A. Perin, TE/CRG, DFBA LSC Page 22 Other observations in the HCM-LCM interconnection Metal edged unprotected contact with busbars. Presence of dust of fiberglass protection.

A. Perin, TE/CRG, DFBA LSC Page 23 Findings DFBAK The short to ground of circuit RCSA56B2 was identified at the HCNM-LCM interconnection of the DFBAK The short was due to a damaged insulation resulting from friction on a metal edge in the interconnection Other issues with the protection of metal edges and busbar insulation were identified in the interconnection. There is a strong potential for damage to the insulation with the existing configuration The insulation will be repaired and the configuration will be improved with insulating pieces at the flanges and towards the interconnection sleeve. Other DFBAs: HCM-LCM interconnections: Configuration essentially identical to the DFBAK according to pictures : same potential risk Can probably be checked by X-ray SHM-HCM interconnections: N' line: ok for all DFBAs N line: ok for 5 / 11 IC. Can probably be checked by X- rays

A. Perin, TE/CRG, DFBA LSC Page 24 Actions & possible consolidation for the HCM-LCM IC Picture F. Laurent SHM-HCM IC of DFBAD Presented at MP3 of 04 June 2013: recommendations (EDMS ) Damage simlar to the observed NC likely to occur at locations A & B. repair time approx 6-8 weeks. Inspect and repair. Less likely in location C. Inspect. Inspect (X-Ray) other potentially risky IC. Action plan : Develop a consolidation solution for the HCM-LCM interconnection (protections, cf pictures). Validation by MP3 ( ) Perform an assessment of the situation for all line N SHM-HCM interconnections for whiche there is no documentation (X-rays). Plan a possible intervention. Estimation of time & resources (preliminary): Duration: 5-6 days / IC mechanics + 2 days for leak tests Possible teams being defined Budget estimation: approx. 90'000 CHF

A. Perin, TE/CRG, DFBA LSC Page 25 Conclusions Work organization and sequence ok: thanks to all !!!! Durations and estimated personnel: globally ok Special operation on DFBAK proceeds very well (thank to the team!!!) : no need to remove the High Current Module! Unplanned issues: Delay in the delivery of support for vacuum valves: no major impact until know by rescheduling/anticipating mechanical work Problem with busbar preparation (broaching): cf slides, shunt installation operations halted since 24 May (splice task force approved solution being implemented, restart 24 June) Short to ground in HCM-LCM IC: evaluation being done for decision asap Global re-scheduling being done: probable impact 1 month delay for initial DFBAs. No impact on global SMACC schedule. Work on lyras will be presented to splice task force on 19 June.

A. Perin, TE/CRG, DFBA LSC Page 27 Project organization (main tasks) Project coordination A. Perin (TE-CRG) Dep.: O.Pirotte (TE-CRG) Std. Mech. work A. Perin (TE-CRG) Welding, DFBAP, DFBAK S.Atieh, D. Lombard. (EN-MME) Insulation vac. P. Cruikshank (TE- VSC) Beam Vacuum J. Finelle (TE-VSC) Busbars & shunt R. Principe (TE- MSC) Shunt QC C. Scheuerlein (TE- MSC) ELQA G. D'Angelo (TE- MPE) SMACC coordination J.-P. Tock (TE-MSC), G. Papotti (BE-OP) LS1 scheduling M. Bernardini (EN-MEF) + Survey: M. Tortrat (BE-ABP) + Consolidation of SHM right side lyras (A. Lees, TE-CRG, F. Morell, TE-CRG) + DFBAK: disconnection/reconnectiion: N. Bourcey (TE-MSC) (not needed !) + DFBAK: Transport DFBAK: C. Bertone (EN-HE-HH) (not needed !) Project scheduling R. Girardot (TE-CRG) Operations coordinator N. Bonetti (TE-CRG) QA & Doc. mgmt. S. Knoops(TE-CRG)

A. Perin, TE/CRG, DFBA LSC Page 28 Workflow for SHM-HCM std. splices consolidation Break vacuum Open / cut vacuum envelope & inner sleeves Remove insulation of busbars QC of splice Ok? no Redo splice Machine busbar QC of shunt OK ? Repair shunt Install insulation and supports Weld sleeve Weld vacuum envelope ELQA QC of weld QC of welds yes OK? no yes no Repair Leak tests OK? no yes Repair OK? no yes Repair repair OK ? no yes Repair OK? no yes Leak & pressure tests with sector Beam vacuum equipmt. TE-SVC-LBV TE-CRG-ME TE-MSC-LMF TE-VSC-EIV QC of machined busbar Ok ? TE-MSC-SCD no yes Install shunts TE-MPE-EE EN-MME Cut Open CC IC bellows Prepare work Re-instlall beam vac equipmt. Finalize work