MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses controls VME crate & magnet ON lamp monitoring –Awaiting delivery of monitoring crate. Due end July-07 –Rack 95% complete –Wiring & Termination drawings complete –Electrical & controls checkout w/c 30-July-07
MICE Project Progress Update Decay Solenoid Solenoid power supply tested & ready for return to RAL –To be located on mezzanine floor –Mezzanine floor requires strengthening –Control interface requirements known –Drawings to be updated to show requirements
MICE Project Progress Update Cable Management Basic tray & trunking layout complete Drawing sheets 1 to 7 issued –Installation can now proceed Main MICE Hall cable routes & to LCR design complete Cable schedule complete for magnet power converters Mains distribution for power converters & LCR complete Mains distribution boards to be purchased & installed LCR tray work design complete –Rack support frames to be manufactured –Tray work to be installed –Raised floor to be installed Phase 2 electrical requirements under review –Detailed information for all systems required
MICE Project Progress Update Personnel Safety Rack Internal wiring 75% complete Terminals & relays installed Control crates in build UPS on order Testing at DL mid-August Delivery to RAL end August