Leonardo Rossi – EB 68 – Oct 5, 2001 0 Pixel status and schedule Rad-hard electronics (has always been) on the critical path for the construction of the.

Slides:



Advertisements
Similar presentations
M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
Advertisements

The ATLAS Pixel Detector
HFT Technical Overview September 26, HFT 2013 TPC FGT 2011 STAR Detectors Fast and Full azimuthal particle identification EMC+EEMC+FMS (-1 ≤ 
ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
HFT PXL Mechanical WBS 1.2 March 2010 Howard Wieman LBNL 1.
1 Status of the CMS Pixel project Lorenzo Uplegger RD07 Florence 28 June 2007.
Stave -1 status and other reports Stave Loading Meeting, November 8 th 2011 G. Barbier, F. Cadoux, A. Clark, D. Ferrère, C. Husi, G. Iacobucci, A. La Rosa,
Opto Harness FDR 19/10/01 T. Weidberg1 Opto Harness FDR Scope and aims of review, system overview Available documentation Status of Project & Schedule.
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
ATLAS detector upgrades ATLAS off to a good start – the detector is performing very well. This talk is about the changes needed in ATLAS during the next.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
D. Lissauer, BNL. 1 ATLAS ID Upgrade Scope R&D Plans for ATLAS Tracker First thoughts on Schedule and Cost.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
Atlas OW, Praha, September 16, 2003Vaclav Vrba, Institute of Physics, AS CR 1 Vaclav Vrba Institute of Physics, AS CR, Prague Pixel Detector Status.
DOE/NSF Review of U.S. ATLAS /March 2001 WBS 1.1 Silicon Subsystem M. G. D. Gilchriese Lawrence Berkeley Laboratory.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
SLHC SG: ATLAS Pixel G. Darbo - INFN / Genova SLHC SG, July 2004 ATLAS Pixel at SLHC G. Darbo - INFN / Genova Talk overview: A table with different High.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
1 US Pixel Mechanics Role Global support structureIntermediate support structureLocal support structure Stave SectorDisk Barrel x (9-11) x5 x (22,40,56)
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
27 Octobre 2005IEEE2005 Nuclear Science Symposium, Puerto Rico, Niels Tuning 1/18 A High-Efficiency and High- Resolution Straw Tube Tracker for the LHCb.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
M. Gilchriese - April 2001 Disk Sector Status. M. Gilchriese - April Technical Status Three prototypes to current dimensions(8-sector disks) except.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
LHCC referee meeting L.Rossi - INFN / Genova CERN - March Status of insertable pixel  Layout in 2000 (Dubna layout)  Reasons for the change.
Thin Silicon R&D for LC applications D. Bortoletto Purdue University Status report Hybrid Pixel Detectors for LC.
Communications G. Darbo – INFN / Genova IBL MB#15, 5 October 2009 o Bump Bonding Selex / INFN Roma, October, 30 th 2009 G. Darbo - INFN / Genova.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
M. Gilchriese Pixel Detector Status ATLAS Collaboration Meeting BNL June 5, 2001.
p-on-n Strip Detectors: ATLAS & CMS
DOE/NSF Review of U.S. ATLAS /March 2001 WBS Pixel Overview and WBS Pixel Mechanics M. G. D. Gilchriese Lawrence Berkeley Laboratory.
ATLAS 1 Beam Pipe Support Structure (BPSS) Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman LBNL.
M. Gilchriese - November 14, Module Decision - To Do List By pixel meetings associated with February 22-26, 1999 ATLAS week Beyond making and testing.
1 VI Single-wall Beam Pipe Option: status and plans M.Olcese TMB June 6th 2002.
ATLAS 1 Beam Pipe Support Structure (BPSS) Services Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman, A Smith, LBNL S. Coelli,
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
M. Gilchriese - December 2000 Disk Sector Status E. Anderssen, M. Gilchriese, F. Goozen, N. Hartman, T. Johnson, F. McCormack, J. Wirth and D. Uken Lawrence.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
D0 PMG, May 04, 2000 Slide 1 Schedule DØ SMT Status Report.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Eric Vigeolas, July the 3 rd Status The IBL detector construction already started and the components assembly (flex, modules, stave loagin) will.
Mathias Reinecke CALICE week - Manchester Electronics Integration - Status Mathias Reinecke for the AHCAL developers.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
DPF2000 ATLAS Pixel Detector M. G. D. Gilchriese Lawrence Berkeley National Laboratory August 2000.
Hybrid CMOS strip detectors J. Dopke for the ATLAS strip CMOS group UK community meeting on CMOS sensors for particle tracking , Cosenors House,
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
PIXEL 2000 P.Netchaeva INFN Genova 0 Results on 0.7% X0 thick Pixel Modules for the ATLAS Detector. INFN Genova: R.Beccherle, G.Darbo, G.Gagliardi, C.Gemme,
Atlas SemiConductor Tracker final integration and commissioning Andrée Robichaud-Véronneau Université de Genève on behalf of the Atlas SCT collaboration.
Straw man layout for ATLAS ID for SLHC
FBK / INFN Roma, November , 17th 2009 G. Darbo - INFN / Genova
Francois and Lau EATM 17 July 2012
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
IBL Overview Darren Leung ~ 8/15/2013 ~ UW B305.
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Hybrid Pixel R&D and Interconnect Technologies
Vertex Detector Mechanical R&D Design Questions and Issues
BCM Overview Placement such that system is sensitive to all types of beam accidents. => 2 independent subsystems Halo losses inside the Pixel volume ie.
Presentation transcript:

Leonardo Rossi – EB 68 – Oct 5, Pixel status and schedule Rad-hard electronics (has always been) on the critical path for the construction of the pixel detector. DMILL technology has proven (contrary to published specs) to be unable to meet pixel requirements (low yield for complex and dense chips). DeepSubMicron (0.25  m gate length) technology appears to be able to meet pixel specs (at reduced cost), but transition DMILL  DSM has taken ~1.5yrs. Pixel underwent layout modifications to cope with rad-hard electronics delay. This means that pixel detector must be installed “independently” from the rest of the ID (=insertable pixel). While doing this mod we tried to preserve as much as possible all the development work done to date. I’ll then report on 2 important changes (DSM and Insertable layout) and on progress about the rest of the project, schedule will be illustrated.

Leonardo Rossi – EB 68 – Oct 5, After succesfull Rad-soft FE and MCC (demonstrating that ATLAS specifications could be met), Rad-hard development began with Atmel/DMILL in 8/98  back 11/99 with very poor yield. Second run with Atmel (7/00) after investigations and some corrections. One option (FE-D2s) excluding circuit elements sensitive to technology problems but at cost of removing some functionality. Yield of FE-D2S good enough to proceed to build a few active modules and test single-chip, but hopeless for production. Design work stopped for FE and MCC in DMILL in 9/00 and all efforts concentrated on 0.25  process, which is now (10/01) ready for submission. Lesson 1: for pixel FE (once you have a working chip design) a transition from one technology to another takes 1 to 1.5 yr. A correction cycle in the same technology takes less: 0.6 to 1 yr. Rad-hard electronics

Leonardo Rossi – EB 68 – Oct 5, During 2001 DSM ATLAS pixel design has been characterized with a 20- pixel chip built using both TSCM and IBM foundries. All characteristics (noise, jitter, etc.) are within specs (except threshold dispersion 2x out) and stay ~the same after 50+ Mrad (55 MeV p). FDR passed on June, follow up passed few days ago, submission week43 (22/10). Expect DSM chips back in week51. Another DSM iteration foreseen (July02) to fix threshold dispersion and possible mistakes in DSM1. In between some small submissions (of critical parts) to secure the DSM2 success. Finally production should begin in 4/03

Leonardo Rossi – EB 68 – Oct 5, The delay of rad-hard electronics implies separate installation of the pixel system. This can be done by permanently installing a CRF tube attached to the barrel ID and then sliding in the pixel system later. Only the CFR tube must be ready together with the barrel ID. PP0 SCT TRT 3450mm 3400mm (end-plug face) Length of service panel Pixel + Pigtails 795mm (Barrel Tube half length) PP1 Insertable layout

Leonardo Rossi – EB 68 – Oct 5, Advantages: flexibility (easier upgrade & repair & coping with production delays) testability (the full system is tested on surface, then connected at PP1) smaller system (less (-17%) modules to build) ID service routing easier (PPB1) Disadvantages: pixel installation needs vacuum breaking (2 b_pipes needed) and displacement of a 7.5m long object (SR building  pit) pixel (and pixel induced) performance are degraded (more material, some acceptance losses and smaller pixel lever arm) mechanics more difficult Advantages outweight disadvantages.

Leonardo Rossi – EB 68 – Oct 5, X0 increase (CFR support tube, services along support tube, Al cooling tube inside staves) DUBNA LAYOUT INSERTABLE LAYOUT 7.5% Peak due to B-layer services, can be reduced if symmetric B_services are finally chosen

Leonardo Rossi – EB 68 – Oct 5, hit acceptance losses of 2-3% mostly at interface barrel disks (impossible to get disks closer) close to  =2.5 (disk cannot be smaller as b_layer must slide in) Acceptance losses

Leonardo Rossi – EB 68 – Oct 5, Pixel system is squeezed (inward:R out 14.2  12.2 cm and outward:R in 4  5 cm in barrel) and shortened. The number of disks is reduced (5  3) 130 cm Longitudinal view Barrel Transverse view

Leonardo Rossi – EB 68 – Oct 5, IP resolution degrades for low p T tracks (R in increase), but stays the same for high p T tracks. b-tagging is marginally affected, layer1 is the less critical (results depend on sw tuning) No final results on EM Calo yet (about to come). 1 GeV  M H (400 GeV) Phys TDR: Ru=183  17 for  b =50% Ru= 80  5 for  b =60%

Leonardo Rossi – EB 68 – Oct 5, Progress on mechanics PRR on local supports passed on July (both supports use C-C supports and Al cooling tubes), production started (material procurement and part fabrication) for all layers. Good progress on support tube and global pixel support, ready for launching Insertable ECR by mid-October Bi-stave Assembly Sector Assembly

Leonardo Rossi – EB 68 – Oct 5, Progress on sensors Preproduction (75CiS+75Tesla good tiles) done. Oxygenated moderated p- spray. Tesla delivery slower, quality acceptable, final irradiation studies underway Good agreement between firms and lab acceptance measurements. Production DataBase in operation in all sensor labs Ready to go for 2000 tiles production (within CORE boundaries), must start soon as production rate is limited.TeslaCis Bad tiles (vendor test)

Leonardo Rossi – EB 68 – Oct 5, Progress on hybridisation Module is made out of a bare module ( sensor tile +16 chips flip-chipped on) and flex circuit (+MCC). FDR of bare module and flex passed (8/00&12/00). Three generations of flex approaching final layout, 4th ongoing, then preproduction (7/02). Progress on modules slowed down due to missing electronics (4 modules done with DMILL). 100 dummy modules in fab. to check bumping firms + jigs in labs + technical staff and procedures in labs/firms. 8” bumping in hand. BaremoduleMCC Flex module MCC MCC

Leonardo Rossi – EB 68 – Oct 5, Progress on local services Taiwan optopackage chosen (6/01), progress on optochips (DORIC and VDC) satisfactory. Both DMILL and DSM can be used, we prefer a unique technology for all rad-hard electronics. Decided to place optolinks at PP0 (fibre routing & optical connectivity). Progress on pigatils: prototypes with microAl cables under construction (need special wirebonding machines available to the collaboration). Design of power supply system with rad-hard voltage regulators is ongoing (need ST regulators).

Leonardo Rossi – EB 68 – Oct 5, Global schedule

Leonardo Rossi – EB 68 – Oct 5, Sensor production schedule

Leonardo Rossi – EB 68 – Oct 5, Electronics production schedule

Leonardo Rossi – EB 68 – Oct 5, Module production schedule

Leonardo Rossi – EB 68 – Oct 5, Module production schedule (cont.)

Leonardo Rossi – EB 68 – Oct 5, Installation schedule

Leonardo Rossi – EB 68 – Oct 5, Final comments à Schedule can be “certified” only after some (25%?) production à Hard to meet the pilot run (even with 2 layers), is it worth? à Installation time before the 1st physics run long enough? Time window for pixel available there? à Insertable layout cannot be avoided, must go through ECR soon. à To proceed along this line we need to be assured that: à in-situ beam pipe baking is possible (double wall pipe) à a 7.5 m long object can be installed during shut down à effects in EM Calo are acceptable à activation does not prevent insertable layout installation/dismount