MEB 2004: the lessons learned presented by L. Bottura for the Magnet Evaluation Board Workshop CERNmonix XIV Thursday, January 20 th, 2005.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Advertisements

Highlights of the ATS MD part I (injection and ramp) … An 8h video game party carefully organized by Jorg et al. 1S. Fartoukh, LSWG 24/05/2011.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
Round table magnet discussion and conclusions CARE-HHH IR’07 animated by W. Scandale and F. Zimmermann.
Hybrid QD0 Studies M. Modena CERN Acknowledgments: CERN TE-MSC CLIC Magnets Study Team: A.Aloev, E. Solodko, P.Thonet, A.Vorozhtsov “CLIC/ILC QD0” Meeting.
BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnetic Specifications and Tolerances Weiming Guo, NSLS-II Project In this presentation I briefly introduced the.
1 / 19 M. Gateau CERN – Geneva – CH 14th International Magnetic Measurement Workshop September 2005, Geneva, Switzerland.
What we may gain with the sorting at MEB Presented by L. Bottura for the MEB Session 4 - Magnetic Requirements for Commissioning Divonnix, January 2006.
LHC Magnet Tests: A challenge for an OperationTeam V. Chohan G.H. Hemelsoet CernGeneva Always set the trail, never follow the path.
Magnetic Behavior of LHC Correctors: Issues for Machine Operation W. Venturini Delsolaro AT-MTM; Inputs from A. Lombardi, M. Giovannozzi, S. Fartoukh,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Field Quality Working Group-14/12/04 - Stephane Sanfilippo AT-MTM-AS Field Quality measurements at cold. Standard program v.s extended tests. Presented.
Expected Quench Levels of the Machine without Beam: Starting at 7 TeV ? P. Pugnat CERN, Geneva, Switzerland LHC Project Workshop Chamonix XV, Tuesday 24.
Rev. 0 CONFIDENTIAL Mod.19 02/00 Rev.2 Mobile Terminals S.p.A. Trieste Author: M.Fragiacomo, D.Protti, M.Torelli 31 Project Idea Feasibility.
Quench-based magnet sorting at the MEB presented by L. Bottura Workshop on Beam generated heat deposition and quench levels for LHC magnets March 3 rd,
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
Massimo GiovannozziChamonix XV, January Electrical circuits required for the minimum workable LHC during commissioning and first two years.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
CERN Equipment Management Integrates Safety Aspects EDMS Doc Eva Sanchez-Corral Mena, Stephan Petit / CERN 1 CERN Equipment Management Integrates.
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
Lab Coordination Meeting 3/21/13LHC IR Quadrupole Plan – G. Sabbi 1 LARP Magnet Systems Plan GianLuca Sabbi Lab Coordination Meeting March 21, 2013.
HL-LHC Annual Meeting, November 2013HQ Planning – G. Sabbi 1 HQ Status and Plans G. Sabbi High Luminosity LHC Annual Meeting Daresbury, UK, November 11-14,
1 / 23 Workshop Chamonix XV January 2006, L'Esplanade du Lac, Divonne-les-Bains S. Sanfilippo Transfer Function of the.
Optimization of Field Error Tolerances for Triplet Quadrupoles of the HL-LHC Lattice V3.01 Option 4444 Yuri Nosochkov Y. Cai, M-H. Wang (SLAC) S. Fartoukh,
Workshop Chamonix XIV, Elena Wildner AT/MAS1 E. Wildner Geometry of the Main Bends and the Short Straight Sections.
MTF – Manufacturing and Test Folder Large Scale Deployment of MTF Sonia Mallón Amérigo Elena Manola-Poggioli on behalf of the EDMS Team, TS-CSE.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
E. Todesco EXPERIENCE WITH FIELD MODELING IN THE LHC E. Todesco CERN, Geneva Switzerland Thanks to the FiDeL team CERN, Space charge th April 2013.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
“WISE” Simulation of optical imperfections in LHC P. Hagen AT/MCS Acknowledgements: Colleagues in AT/MAS, AT/MEL, AT/MTM, AB/ABP CERN, October 2006.
2/12/2013 Massimo Giovannozzi - CERN1 Sorting of the LHC magnets and lessons learnt S. Fartoukh, M. Giovannozzi Introduction The LHC in a nutshell The.
CLIC Stabilisation Day’08 18 th March 2008 Thomas Zickler AT/MCS/MNC/tz 1 CLIC Quadrupoles Th. Zickler CERN.
7 th March 2008 Magnet Modelling N. Sammut On behalf of the FIDEL Working Group.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
CERN –GSI/CEA MM preparation meeting, Magnetic Measurements WP.
Expected field quality in LHC magnets E. Todesco AT-MAS With contributions of S. Fartoukh, M. Giovannozzi, A. Lombardi, F. Schmidt (beam dynamics) N. Catalan-Lasheras,
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Workshop on Appraisal of Disassembled Magnets: Lessons learned March 17 th, 2005 Boundary Conditions-Technical Specification Jos Vlogaert.
AB-CO Review, 23 September 2005 L. Walckiers AT-MTM p. 1 Project description  To maintain for LHC completion  Magnet Rescue Activities [MAR]  Support.
DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Answers to committee questions - magnets.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
Threading / LTC/ JW1 How difficult is threading at the LHC ? When MADX meets the control system … J. Wenninger AB-OP &
First evaluation of Dynamic Aperture at injection for FCC-hh
Inventory for the magnet evaluation related activities (1/2) Work-packages CryodipolesSSS MBSpoolsMQLattice corrector Definition of AP criteriaDone To.
CERN, 11th November 2011 Hi-lumi meeting
MQXC Nb-Ti 120mm 120T/m 2m models
SLHC –PP WP6 LHC IR Upgrade - Phase I.
Procurement, Measurement and Installation of 2 Octupoles for ATF
OVERVIEW Impact of Modelling and simulation in Mechatronics system
Optimization of Triplet Field Quality in Collision
Arc magnet designs Attilio Milanese 13 Oct. 2016
Powering the LHC Magnets
Hollow e- lens, Cryogenic aspects
International Review of the Conceptual Design of the Cold Powering system for the HL-LHC Superconducting Magnets J.Ph. Tock
Status of Magnet Setup Cycling for LHC
Circuits description and requirements - Closed Session-
Geometry: analysis and trend.
UPDATE ON DYNAMIC APERTURE SIMULATIONS
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Nonlinear Field Quality Checks
HL LHC WP3 (magnets) TASK 2 ADVANCEMENT
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Field quality of LHC corrector magnets
A. Lombardi and Y. Papaphilippou
Magnetic axis tolerances for the SSS magnets
Triplet corrector layout and strength specifications
Beam dynamics requirements on MQT
On reproducibility From several inputs of N. Sammut, S. Sanfilippo, W. Venturini Presented by L. Bottura LHCCWG
Presentation transcript:

MEB 2004: the lessons learned presented by L. Bottura for the Magnet Evaluation Board Workshop CERNmonix XIV Thursday, January 20 th, 2005

Outline What is MEB ? Mandate, membership and mission The case of MB installation situation as of January 2004 and consequences of a blind installation scheme magnet classes, an installation algorithm and its implementation the final touches ? The other magnets SSS IR magnets all the rest Summary

The Magnet Evaluation Board is charged with: Assessment of the suitability of each magnet produced for the LHC accelerator, based mainly on the information from its Manufacturing and Test Folder Optimization of installation and tunnel location of the magnets in the LHC accelerator based on the magnet performance (principally powering, geometry and field quality issues) Requesting competent bodies (Groups and/or Working Groups), to study and produce recommendations on specific issues related to installation strategy The MEB has executive power within the scope of its mandate, and: reports directly to the LHC Project Leader informs the MARIC, and LTC Kick-off on May, 3rd, 2002 (P. Lebrun) Trail-blazing work from N. Siegel (chair), S. Fartoukh, D. Tommasini Now consists of 15 members from AT, AB and TS, L.Bottura (chair), M. Giovannozzi (scientific secretary), E. Delucinge (secretary)

Mission statement If all magnets performed to (beam) specifications, we could install any magnet anywhere In reality, we are faced with magnets performing worse, as, or better than (production) specified, available as produced and requested as from installation schedule Although a global sorting is out of question, delays in the installation (see: the January theorem) have provided a comfortable stock of magnets (e.g. in excess of 400 MB’s) Mission: Find suitable slots for the available magnets that perform better as specified, as specified or out-of-tolerance Preserve and (if possible) optimize the machine performance Include provisions to face day-to-day requirements (faults during processing the magnets) Follow the planned installation schedule with a suitable flow of allocated magnets

The January theorem Statement:whatever the January of year YY, the first magnet should be installed in March YY Proof (by mathematical induction of first-kind): I.BASE clause (P(n 0 )): in January of year n 0 (with n 0 = 2004) the first magnet to be installed was planned for March of year n 0 II.RECURSION clause (P(n))  (P(n+1)): in January of year n+1 (with n = 2004, n+1 = 2005) the first magnet to be installed is planned for March of year n+1 QED Other theorems of the same class: 50 years to fusion: whatever the year Y, thermonuclear fusion power will be available in 50 years from Y

MB situation as of January 2004 all MB cold masses of 1 octant (type R) were delivered approximately only 1/2 octant cold tested (missing cold data) few slots pre-allocated under the pressure of launching tunnel preparation work in SMI-2 various performance concerns: dipoles geometry out of tolerance (10 to 20 % of production) cold mass shape and position unstable (shape changes by more than 1 mm measured in the body) coil cross section changes from the initial production (XS1, non-nominal shims) to the first iteration (XS2) to the present state (XS3) modified systematic multipoles electrical insulation, quench level, instrumentation (approximately 10 % of production needs re-test and/or re-work) other minor hardware faults (faulty T-sensors on 5 % of production) XS1  XS2XS2  XS3  b  b3 -2…-3

Geometry issues out-of-tolerance geometry after cold test, entailing a loss of mechanical aperture of about 1 mm in addition, an unstable geometry, to 1 mm level, would make re-alignment a risky guess-work, increasing uncertainties at operation spool piece positioning off MB axis causes feed- down during corrections b3 corrections with the spool piece off-center horizontally induces a tune change courtesy of E. Wildner Shape change ITP20 to WP08 ends at WP08 sagitta at WP08

Field quality issues  b 3 of ≈ 2 17 mm, as observed for sector 78, could have resulted in a loss of DA of ≈ 1  compensating large (up) and small (down) b 3 (tic-tac and flip-flop schemes) or  -pairing them (same b 3 in dipoles spaced by 2 arc cells) restores the DA close to the nominal 12  value from S. Fartoukh, EPAC 2004

MB variants and constraints hardware variants (LBARA.34R7) 4 dipole types (A/B spool piece, R/L diode) from industry MEB approval 17 types of interconnects, work performed at CERN, resulting in 12 combinations of type+interconnect for the arc, and 20 combinations for the DS 32 variants we need to consider (in addition) specific magnet features and non-conformities closed by project engineers with the statements “use as is” or “dealt at MEB” e.g. temperature sensor out of work, pipe positions out of specification

Geometry classes 4 classes, based on the variation of the beam size along the cell: mid-cell (maximum space where the beam size is minimum) silver (nominal tolerance revised for race-track) silver-right (MQ on the r.h.s., mid-cell on the l.h.s.) silver-left (MQ on the l.h.s., mid-cell on the r.h.s.) golden (reduced tolerance for DS cells) MQMB S to SL MCS to SR MQMB error silver mid-cell Last industry measurement Last WP08 measurement based on proposal from S. Fartoukh specifications after J.B. Jeanneret and the WGA

Field quality classes 4 classes, based on measured field quality vs. specifications: Green (use anywhere, direct and blind installation) e.g. |b1| ≤ 9.8, |a1| ≤ 9.8, |a2| ≤ 0.9, |b3| ≤ 3 at FT Yellow 0-1  (good candidates for direct installation provided the actual running average is checked within bounds) e.g. 9.8 < |b1| ≤ 14.5, 9.8 < |a1| ≤ 14.5, 0.9 < |a2| ≤ 1.9, 3 < |b3| ≤ 4.8 at FT Red 1-3  (require that the running average is within bounds and/or compensation by sorting) e.g < |b1| ≤ 30.5, 14.5 < |a1| ≤ 30.5, 1.9 < |a2| ≤ 5.7, 4.8 < |b3| ≤ 8.4 at FT Blue (marginalization and sorting in any case before a slot is assigned) e.g < |b1|, 30.5 < |a1|, 5.7 < |a2|, 8.4 < |b3| at FT following the definition of S. Fartoukh

Quench classes 3 and 1/2 classes, based on training and electrical characteristics: Golden (bonus magnets, do not detrain ? preferably use in hot regions) N ramp (9 T)  3 and[electrically sound] Silver-plus (nearly as good as golden magnets ? preferably use in hot regions) N ramp (9 T) > 3 and N ramp (8.75 T)  2and[electrically sound] Silver (normal magnets) N ramp (9 T)  9 and N ramp (8.4 T)  2 during first test or N ramp (9 T)  9 and N ramp (8.4 T)  1 after thermal cycleand[electrically sound] or N ramp (9 T)  9 and N ramp (8.6 T)  2 after thermal cycle Reserve (bound to train/detrain, preferably use in shielded regions) training as defined for G, S+, S, but shows detraining, or high splice resistance or deviation from nominal cable margin at 4.5 K NOTE: this is a working hypothesis, as at present: the relation between test training and detraining is not formally established hot locations are identified based on general reasoning on aperture following the definition of A. Siemko, P. Pugnat and E. Floch

Installation algorithm - 1/2 Logic: form pairs of magnets that compensate deviations of field errors from average in the sector (compensated by the correctors) to minimise the effect of the rms exception rules (by priority): satisfy hardware type constraints (diode, spool) no more than 1 magnet with defective T-sensor per cell, in locations that can be accepted by cryo-control power-R magnets in mid-cell locations geo-MC, geo-SL, geo-SR magnets (with out-of-tolerance geometry) in suitable locations in arc cells (mid-cell, right or left of a MQ) geo-G magnets in DS cells power-G and power-S+ magnets in priority to DS (power-S otherwise) not more than 3 magnets in a cell with out-of-tolerance b1 and/or a1 courtesy of S. Fartoukh, presented and discussed at FQWG and MEB References:Proc. of LHC Workshop Chamonix-XIII, pp , 2004 Proc. of EPAC 2004, pp , 2004

Tools MTF hardware description, equipment data, non- conformity reports, ID card (TS/CSE) data base links and viewers geometry viewer (AT/MAS) magnetic viewer (AT/MTM) status pages cryodipole coordination page (Dipcoor) installation sequence (MTF and TS/IC) MEB hardware report as a compact summary of properties for a magnet sequence (MTF)

Sector 78 as of December more dipoles

Lessons from 78 A set of working and adapted tools required about 1 year to be defined, implemented and trimmed, learning what is important on the way. This investment pays off today, and the same system will be used for the arc SSS’s. This time was also needed to speak the same language in the magnet evaluation. In spite of a very heterogeneous and difficult mix of properties and performances in the initial production aperture is expected to be maintained vs. possible 1.4 mm loss (because of the  1 mm out-of-tolerance on the geometry and the  1 mm instability) in the ideal case of perfect IR, DS and MS, the DA is expected to be at 11 to 11.5  (close to target) vs. possible 1  loss (caused by large spread of geometric b 3 ) random b2 in SSS partially compensated to maintain the  -beat budget within spec (7 to 8 %), see later on SSS Completing a sector after an allocation in batches (typically 10) is increasingly difficult (drop-outs, leftovers, availability issues). A different working mode will be adopted for the coming sectors

The 2 coming years for MB’s Allocation on following sectors will take place in batches of 154 magnets (and about 20 spares to cover drop-outs and problem cases). The batch is pre-selected from the stock of  350 CM’s available at CERN For sector 81 (see LHC PN 358) we take the magnets with highest b3 (limiting factor), inner cable type 01B, with enough (  35) golden geometry magnets. The b3 spread is decreased from 1.5 to about 1 17 mm pairing continues to build margin, should it be needed at a later stage All information relevant for slot allocation is collected in a summary table that is obtained as on-line report in MTF We now check the flexibility of this approach vs. the practical demands of installation, and adapt as necessary. sector 81 descends in March prepare work in SMI-2 starting from end of January 30 magnets (slots) by end of January 40 magnets/month on average thereafter allocate following sectors, as the installation rate demands (ramp to steady-state by Spring 2005) IDEA: identify joker magnets that can be used in case of problems originating or discovered after SMI-2 preparation work Complementary activity: feed-back loop in SMI-2, adjustments and special tests as demanded, definition of the installation WP and installation shifts

MB approval rate 1000 magnets in 18 months: ≈ 50 magnets/month

The arc SSS’s The many hardware variants (60 arc SSS types, depending on magnetic, electric and cryogenic function) are finalized in industry at the moment of assembly in a cold mass. A sorting, as done for MB’s, is not possible The main issue is the random b2. Limited b2 pairing of SSS’s (using slot equivalence for some 1/2 of the SSS types) is possible, and has been done in sector 78 (A. Lombardi)  b2  15 units vs. 10 units specified reduced to an effective  b2 effective  5 … 10 units through pairing, bringing the expected  -beat from SSS random b2 within budget As from end of January we proceed to sector 81 with high priority Approval tools and specifications not yet final ! finalize race-trackization of the geometric tolerances (WGA) automatic ID cards production from data-bases confirm 10 slots/month (provisional) as of January complementary activity: verify shapes as measured in 908, define optimal installation shifts

Cryomagnets for IR (US-LHC) MEB examines magnets prior to shipment, try to identify any no-go issue before the magnets are at CERN magnets are already approved by acceptance boards at US-Labs and US-LHC project management discussion on suitability for ring installation and operation (FQWG, WGA, EEWG may be asked to give recommendation) data transfer to CERN databases is a mandatory step before approval for shipment ID card provided by US-LHC, pre- filled with acceptance data summary Status: four D1’s (BNL) and six D2’s (BNL) are approved (all D2 allocated) (M. Giovannozzi) approval of 3 D2’s: March 2005 approval of D3’s and D4’s: June 2005 discussion on triplet (Q1, Q2 and Q3 (FNAL)) after shipment to approve installation based on the final geometry (re- measured at CERN): start March 2005 The MTF work is reduced to the minimum necessary for installation and operation no detailed breakdown of production data from J or US The IR magnets work is presently not on a critical path few magnets can be treated as the need arises

MS’s and DS’s quadrupoles The plan is to install the first IR, MS and DS at point 8 between July and August 2005 Today, 3 magnets have been cold tested in SM-18, one measured magnetically in 2004, production and testing will ramp-up in 2005 These magnets are complex assemblies, very small series The tools developed for MB and SSS require adjustment to produce efficiently the respective ID cards (work for 2005) sorting of completed Q4…Q7 is not possible because the number of units/variant is small some limited sorting can be done on Q4…Q7 before completion of the cold mass, based on warm data (and cold data from B4) for completed Q8, Q9 and Q10 some sorting is feasible We need to define a rationale for slot allocation and adopt a working mode adapted to the demand, anticipate the discussion geometry performance (including correctors) field quality (other constraints)

Warm magnets Total of 154 magnets, do not forget them ! The issues for warm magnets are clearly different from superconducting magnets (where we allocated most of our efforts so far) pole geometry alignment field strength, direction and field homogeneity Critical elements: MBXW for installation, MQW for sorting in Q4/Q5 assemblies sorting of magnets/vacuum pipes to maximise aperture Work required define alignment (mechanical, references) (WGA) present results on a magnet-by-magnet basis (geometry, magnetic) define and approve slots

Summary The MB activity for sector 78 has shown that it is possible to preserve projected performance (mechanical and dynamic aperture), and optimize the machine (build margin now for later needs) This requires commitment and continuous interaction between the members (and their teams) involved in magnet manufacturing, testing, installation and beam physics The MEB has acted in this direction, working as a decision body for slot allocation, as well as a bridge between hardware characteristics and beam requests The activities in 2005 will focus on mass allocation (MB’s and SSS’s) define and implement a suitable working mode for magnets in small series (MS and DS quads, warm magnets)

Acknowledgements MembersAlternate Members Luca Bottura (Chairman) Massimo Giovannozzi (Secretary, ABP-IR, MS and DS SS) Stephane Fartoukh (ABP-MB)Oliver Bruening Alessandra Lombardi (ABP-SSS) Karl-Hubert Mess (Electrical Engineering)Ranko Ostojic Ranko Ostojic (IR, SSSS)Karl-Hubert Mess Dominique Missiaen (Survey) Suitbert Ramberger (Resistive Magnets)Willi Kalbreier Michele Modena (SSS)Vittorio Parma Stephane Sanfilippo (Field) Elena Wildner (Geometry)Walter Scandale Jean Bernard Jeanneret (Aperture) Frank Schmidt (ABP-IR)Oliver Bruening Andrzej Siemko (Quench and Protection)Pierre Pugnat Davide Tommasini (MB)Theodor Tortschanoff