CS-EE 480 Spring January 2005 Project Grey Wolf Digital CMOS “Memory” Game Team Lindsay Megyesi Taya Campagna Mason Tabata Weston Kurisu Advisor Dr. Lu, Dr. Osterberg Industry Representative Mr. Dave Dunning of Intel
CS-EE 480 Spring January 2005 Overview Introduction Block Diagram Accomplishments Plans Schedule and Milestone Table Issues/Concerns Conclusions
CS-EE 480 Spring January 2005 Introduction Creation of digital “Memory” game using MOSIS technology and a PIC18F452 microcontroller
CS-EE 480 Spring January 2005 Block Diagram
CS-EE 480 Spring January 2005 Accomplishments Design review checklist and approval meeting. Ordered/received parts. We enjoyed Christmas break. ed Sandy a list of supplies. Contacted Dave (our industry rep) and informed him of our schedule.
CS-EE 480 Spring January 2005 Accomplishments…cont Created flow diagram for microcontroller. Completed turn counter for macro model using Verilog. Started random number generator programming for macro model. Received L-Edit chip layout (both BLT and hand versions).
CS-EE 480 Spring January 2005 Microcontroller Flow Diagram
CS-EE 480 Spring January 2005 L-Edit Layout (BLT)
CS-EE 480 Spring January 2005 L-Edit Layout (Hand)
CS-EE 480 Spring January 2005 Plans for February Theory of Operations 0.9, 1.0, and approval. Start putting hardware together. –Establish physical connections between Microcontroller and LCD. Program microcontroller. Complete programming for macro model. Update website when possible.
CS-EE 480 Spring January 2005 Schedule
CS-EE 480 Spring January 2005 Milestones NumberDescription OriginalPreviousPresent (9/28/04)(11/30/04)(1/25/05) 1September Program Review9/28/2004 2Product Approval10/8/200410/14/2004 3October Program Review10/26/2004 4B2 Logic Simulation11/5/2004 5Project Plan 0.911/5/2004 6Project Plan Approval11/12/ tpr File Completion11/19/200411/23/2004 8Submit MOSIS design11/24/2004 9November Program Review11/30/ Design Release and Approval Meeting12/10/ January Program Review1/25/ Theory of Operations Approval2/11/2005
CS-EE 480 Spring January 2005 Milestones Cont. NumberDescription OriginalPreviousPresent (9/28/04)(11/30/04)(1/25/05) 13Macro Model of Chip2/14/ February Program Review2/22/ Microcontroller Programmed2/28/ System Integration3/28/ March Program Review3/29/ Prototype Release and Approval Meeting4/8/ Founder’s Day Celebration4/12/ Final Report4/22/2005
CS-EE 480 Spring January 2005 Concerns/Issues Staying on schedule. Getting reimbursed for parts.
CS-EE 480 Spring January 2005 Conclusions After break, we are ready to start implementing our design. We have completed the necessary steps to begin constructing our project. The bulk of next months work includes programming the microcontroller and macro model. Any questions?