Proposed LCLS-II SCU Schedule Soren Prestemon (LBNL) SCU 3-Lab Review Meeting December 16, 2014.

Slides:



Advertisements
Similar presentations
SCU Development at LBNL Soren Prestemon Lawrence Berkeley National Laboratory Superconducting Undulator R&D Review Jan. 31, 2014.
Advertisements

OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
OFFICE OF SCIENCE Review of Critical Decision 2 for the Large Liquid Argon Detector for Neutron Physics (MicroBooNE) at Fermi National Accelerator Laboratory.
Undulator System Review Closeout Erik Johnson, Kem Robinson, Dieter Walz 4 March 2004.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
RF Cavity / Coupling Coil Module
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Page 1 MODEL TEST in the small GENERALIZE PROGRAM PROCESS allocated maintenance changes management documents initial requirement project infrastructure.
From Research Prototype to Production
1 ISA&D7‏/8‏/ ISA&D7‏/8‏/2013 Systems Development Life Cycle Phases and Activities in the SDLC Variations of the SDLC models.
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
Needs of a European SCRF Facility - the BIG plan Lutz Lilje DESY -MPY- DESY 11/2006 Planning Resource needs.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
1 The Design & Value Costs SRF Technology The XFEL as a Prototype Japan as a Host International Linear Collider Status Mike Harrison.
Cost Estimate Marion White (Argonne) SCU 3-Lab Review Meeting December 16, 2014.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
Report from MICE project teams Feedback from PPRP MICE funding: various scenarios Issues  Financial year 2003/04  iMICE common fund.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
Global Design Effort Introduction and goals of the meeting Andrei Seryi, Toshiaki Tauchi Fifth ATF2 Project Meeting December 19-21, 2007.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
Procurement and Manufacture of LCLS Undulators FY 04 Activity: Complete design of Second Prototype Undulator This will include field control comb Procure.
SCU 3-Lab Review Meeting, Dec. 16, 2014 SCU Presentations Today Intro. & Performance Motivations (P. Emma, SLAC, 20+5) Conceptual Cryostat Design: Option-A.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
The categories for ILC budget planning are: R&D – work done in laboratories to develop and verify subsystem components. This supports the cost reduction.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
European Spallation Source Overview and Status Technical Advisory Committee 1-2 April 2015 James H. Yeck ESS CEO & Director General
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
SRF Collaboration Shekhar Mishra Fermilab. Overview Charge: Does the laboratory make effective use of collaboration and existing SRF capabilities at other.
ITOP Quartz Procurement Status James Fast Pacific Northwest National Laboratory PNNL-SA
LARP Crab Cavities Cryomodule Integration Meeting Final Notes A.Ratti LBNL.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
ACD Down-Select Criteria and Time Scales for HLRF ML-KOM FNAL September 27 、 2007 S. Fukuda, KEK & Ray Larsen, SLAC For the ILC HLRF Collaboration.
Summary of discussions
Camera PDR/CD1 Planning 19 September 2008
Jim Fast Pacific Northwest National Laboratory
FEL SCU development at APS/ANL
Summary of Session: Magnets and undulators for light sources 2
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
Crab Cavities Contribution from the U.S.
WBS 1.03 Readout Systems Scope, Cost and Schedule
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
TBL, Status, Plans, Experiments
EDR HLRF Work Packages Draft Summary
ESS RF Development at Uppsala University
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Summary of discussions
A Cold SCU Phase-Shifter
TSF Upgrade Project Overview Resources Plans and Timetable
Electron Beam Systems ETC and Methodology
Daresbury ESS In-Kind Contributions
Conventional Facilities
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Proposed LCLS-II SCU Schedule Soren Prestemon (LBNL) SCU 3-Lab Review Meeting December 16, 2014

SCU 3-Lab Review Meeting, Dec. 16, 2014 Considerations that set the stage Aggressive schedules (but not fantastical…) – Assume funding is there when we need it – Assume we can access the right people: We have considered resource needs, but did not attempt to develop a true resource loaded and leveled schedule – Success-oriented schedule: Each stage of the project is sufficiently successful to proceed to the next stage Some risk mitigation integrated into schedule – Sub-component prototyping early in project – Introduce vendors early in the project – Multi-lab collaboration

SCU 3-Lab Review Meeting, Dec. 16, 2014 Example of possible work flow Many parallel efforts can be done by industry Two final assembly lines and test stations at Laboratories We take advantage of DOE Lab capabilities: expertise and infrastructure Cryostat line 1 Cryostat line 2 Cold-mass test and tune: station 1 Cold-mass test and tune: station 2 Final assembly station 1 Final assembly station 2 Final test: Calibration and fiducials: Station 1 Final test: Calibration and fiducials: Station 1 Final test: Calibration and fiducials: Station 2 Final test: Calibration and fiducials: Station 2

SCU 3-Lab Review Meeting, Dec. 16, 2014 Aggressive SCU schedule FY14FY15FY16FY17FY18FY19FY20FY21FY22 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Cold-mass prototype complete [funded] 3x1.5m test & tune complete Critical Decision: baseline selection Production readiness review Project complete Prototyping First articlesProduction Installation CD-2/3 Review PDRFDR Start production First Undulator delivered Last Undulator delivered Design production undulator and interfaces Fabricate pre-production unit Assembly Testing Material lead time 1st article fabrication Production delivery to SLAC Install in tunnel Integration & test Design

SCU 3-Lab Review Meeting, Dec. 16, 2014 FY14FY15FY16FY17FY18FY19FY20FY21FY22 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Q1Q1 Q2Q2 Q3Q3 Q4Q4 Schedule uncertainty – possible scenario 5 Cold-mass prototype complete [funded] 3x1.5m test & tune complete Critical Decision: baseline selection Production readiness review Project complete Design First articles Production Installation CD-2/3 Review PDRFDR Start production First Undulator delivered Last Undulator delivered Design production undulator and interfaces Fabricate pre-production unit Assembly Testing Material lead time 1st article fabrication Production delivery to SLAC Install in tunnel Integration & test 2 nd prototype Prototyping

Roll-up of detailed schedule 6 Calendar year

Highlights of built-in risk mitigation efforts 7 Multi-lab collaboration – provides project with flexibility to access critical resources – leverage existing infrastructure Vendors identified and performance demonstrated early – Use design&prototyping phase to identify and qualify vendors ✤ components, long-lead items; winding and VPI setups Develop & prototype subcomponents early – Identify critical subcomponents; prove them early (cold BPMs,…) Invest in critical infrastructure early – Test facilities for 1.5m cold-masses – Test facilities for complete cryomodules – Planning for final cryogenic system Qualification of two parallel production lines – Provides redundancy in case of issue with one line

SCU 3-Lab Review Meeting, Dec. 16, 2014 Recap of critical assumptions to hold schedule Funding starts now - and at appropriate level Project depends critically on early, aggressive design and prototype development Resources are identified and made available when needed DOE Labs must be committed to providing resources and infrastructure Project progresses well (no contingency in the schedule shown) Holding to a success-oriented schedule requires parallel mitigation efforts, e.g. funds and resources to develop and test subcomponents Critical decisions are made at appropriate times

SCU 3-Lab Review Meeting, Dec. 16, 2014 Issues & alternative scenarios LCLS-II project needs to continue with current baseline technical approach Schedule, critical decisions Proposed SCU schedule depends critically on immediate and full funding towards prototype Alternatively, SCU progress requires continued investment to bring to a state of technology readiness for future BES facilities: Need to maintain, and build on, current momentum of the teams