Griffin-Spalding County Airport LPA Group Project Update Presented to September 28, 2009
Today’s Briefing AIP -28 – Project Update –Crack Seal, Rejuvenate, and Marking of Existing Airfield –Repackage West Taxiway Rehabilitation Project –Design Itinerant Apron Rehabilitation Environmental Study Update –Existing and New Airport
AIP-28 – PROJECT UPDATE Crack Seal, Rejuvenate and Marking –Entire Airfield Including Apron and Taxilanes –Scheduled to Start Construction Mid-October –Construction Duration Approx. 1 Month –Will Provide Extended Life to Existing Pavement –Will Give the Airport a Fresh Look
AIP-28 – PROJECT UPDATE
Repackage and Rebid West Taxiway Improvements Project –Last Year’s Project – Pavement Reconstruction –Anticipate Construction Next Summer (depends on State Funding) Rehabilitate Itinerant Apron Project –Overlay and Reconstruction of Terminal Area Apron –Anticipate Construction Next Summer (depends on State Funding)
ENVIRONMENTAL UPDATE Contracts Under GDOT Review –State Block Grant Requires GDOT to Review Contracts –Comments Expected Back This Week Once Contract Finalized, Study Should Take Approximately 1 Year to Complete