July 7, 2008 TPTF Texas Nodal Market Implementation: - Market Readiness Metrics Update Jerry Sullivan.

Slides:



Advertisements
Similar presentations
1 Market Trials Outage Scheduling Qualifications Weekly Update March 4, 2010.
Advertisements

1 Market Trials Outage Scheduling Qualifications Weekly Update February 18, 2010.
June 26, 2008 TAC Texas Nodal Market Implementation: Program Update Jerry Sullivan.
July 21, 2008 TPTF Texas Nodal Market Implementation: Market Readiness Metrics Update Karen Lamoree.
November 1, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan, Executive Director.
1 TSP Nodal Engagement Market Participant Call ERCOT August 04, 2010.
August 2, 2007 TAC Meeting Texas Nodal Program Update Tim Pare.
1 Texas Nodal Texas Nodal Program Implementation TPTF June 6, 2006 Agenda.
Texas Nodal 1 Nodal Telemetry Outreach and Recent Changes to Focused Input Testing (FIT) NATF Sep 29, 2009 Stacy Bridges, ERCOT.
1 Market Trials Outage Scheduling Qualifications Weekly Update April 02, 2010.
TPTF Meeting Texas Nodal Program Update Market Readiness Metrics Update Chris Wilkinson PMO.
October 23, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan Program Director, Market Redesign.
1 Market Trials Outage Scheduling Weekly Update July 23, 2010.
22 May 2008 TPTF Texas Nodal Program: Market Readiness Metrics Update Mike Beck.
Market Implementation Board Presentation October 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program status.
Texas Nodal Program ERCOT Readiness Update TPTF March 31, 2008.
June 7, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan.
July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
Market Implementation Board Presentation July – v1.1F 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program.
July 23, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
November 28, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
ROS Meeting – 12/06/071Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 12/06/2007.
TPTF Meeting Texas Nodal Program Update Market Readiness Metrics Update Chris Wilkinson PMO.
Lead from the front Texas Nodal 1 Registration Market Call June Data Collection Window Aug 14, 2009.
1 Market Trials Outage Scheduling Weekly Update June 25, 2010.
January 15, 2008 Monthly Board of Directors Meeting Texas Nodal Market Implementation Program Update Jerry Sullivan.
1 Market Trials Outage Scheduling Weekly Update July 02, 2010.
July 7, 2008 TPTF Texas Nodal Market Implementation: - Program Update - Market Readiness Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF - November 6 th, 2006.
Lead from the front Texas Nodal 1 Texas Nodal Registration Kick-off Meeting Matt Mereness June 6 th, 2007.
Lead from the front Texas Nodal 1 Registration Market Call Oct 31, 2008.
September 25, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
April 17, Texas Nodal Market Implementation Readiness Update May 8, 2007.
EDS 2 Early Delivery Systems Release 3 – Workshop August 16, 2007.
Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS Market Call May 30, 2008.
May 22, 2008 TPTF Texas Nodal Market Implementation Program Update Raj Chudgar.
Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS Market Call June 20, 2008.
1Texas Nodal Texas Nodal COPS Commercial Systems Update By Raj Chudgar, ERCOT Wednesday, 11/16/2006.
1 Readiness Scorecard – May ‘10 NATF Brandon McElfresh Nodal Readiness and Transition May 4, 2010.
Texas Nodal Program ERCOT Readiness Update TPTF June 23, 2008.
EDS 1 Early Delivery Systems EDS 1 Update Jonathan Pulcini - Project Manager August 13, 2007.
1 Market Trials Update NATF May 4, 2010.
October 8, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan Program Director, Market Redesign.
Lead from the front Texas Nodal 1 Registration Update to TPTF Patrick Coon / Matt Mereness August 13 th, 2007.
1 Market Trials Outage Scheduling Weekly Update August 13, 2010.
November 29, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan, Executive Director.
April 1, 2008 TPTF Texas Nodal Program Update Market Readiness Metrics Update Chris Wilkinson PMO.
July 7, 2008 TPTF Texas Nodal Market Implementation: Metrics Revisions Jerry Sullivan.
August 27, 2007 Executive Committee Meeting Texas Nodal Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Current Telemetry Dashboards NDSWG March 24, 2009.
Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS Market Call April 25, 2008.
EDS 1 Early Delivery Systems EDS 1 Update for Workshop Jonathan Pulcini - Project Manager August 17, 2007.
Lead from the front Texas Nodal 1 Nodal Transitional Qualification Approach to Qualifications for the Nodal Market August 16, 2007.
April 1, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.
June 9 th, 2008 TPTF Texas Nodal Program: Market Readiness Metrics Update Mike Beck.
October 2, 2008 TAC Texas Nodal Market Implementation: Program Update Ron Hinsley.
May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.
January 3, 2008 TAC Meeting Texas Nodal Program Update Jerry Sullivan.
1 Market Trials Real-Time Market / LFC Weekly Update March 26, 2010.
Lead from the front Texas Nodal 1 MP10 / MP11 Registration Data Update Oct 14, 2008 TPTF.
Lead from the front Texas Nodal 1 Registration Market Call Nov 14, 2008.
Texas Nodal Market Implementation Transition Planning Task Force Metric Framework Review Readiness Advisor January 24, 2006.
April 4, 2008 TAC Texas Nodal Market Implementation Program Update Jerry Sullivan.
June 5, 2008 TAC Texas Nodal Market Implementation Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Registration Market Call Nov 21, 2008.
1 Market Trials Outage Scheduling Qualifications Weekly Update March 26, 2010.
August 11, 2008 TPTF Early Delivery Systems Status Daryl Cote.
1 Readiness Scorecard – Market Readiness Series Brandon McElfresh Nodal Readiness and Transition January 28, 2010.
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
Market Trials Open Market Participant Call
Presentation transcript:

July 7, 2008 TPTF Texas Nodal Market Implementation: - Market Readiness Metrics Update Jerry Sullivan

2 2 Texas Nodal Program UpdateJuly 7, 2008 Agenda: Market Readiness Metrics Update Status Update –ERCOT Staff Readiness –Market Participants Cycle 4 Survey Update Metric Update –EDS Appendix (see separate file) Metrics Review (see separate file)

3 3 Texas Nodal Program UpdateJuly 7, 2008 Status Update All status levels for overall readiness remain the same

4 4 Texas Nodal Program UpdateJuly 7, 2008 ERCOT Readiness Engagement (green) new survey results came out at the end of June - ERCOT remains fully engaged Training (amber) training efforts are on-going Process (amber) one department in System Operations is behind performance levels Staffing (amber) ERCOT is currently ~95% staffed (98% required for green status) recruitment is on-going Testing (green) no recent developments ERCOT Staff Readiness status is AMBER 15 July 2008 ERCOT Public

5 5 Texas Nodal Program UpdateJuly 7, 2008 Market Participant Readiness Market Participant Readiness status is AMBER Engagement (amber) limited survey response from QSEs and LSEs drives amber status Connectivity (green) several new entrants to the market have been successfully tested Registration and Qualification (amber) MP10 (resource mapping) has, again, improved steadily since the last meeting MP11 (RARF data) – only 5 RARFs have not been received (RARFs representing more than 99.5% of MWs have been submitted) Telemetry (green) no change Training (amber) limited survey response from QSEs drives amber status Trials Participation (green) improvement in MP15 (EDS 3 trials participation) 15 July 2008 ERCOT Public

6 6 Texas Nodal Program UpdateJuly 7, 2008 Cycle 4 Survey Update There were varying degrees of response to the Cycle 4 Survey – QSEs with Resources and TDSPs had 100% response to the Cycle 4 Survey – 87% of QSEs have responded to the survey (up from 72%) – 81% of LSEs have responded to the survey (up from 67%) This limited response is driving several metrics to red – QSEs without Resources are red for MP1, MP12, and MP13 – LSEs are red for MP19 ERCOT Account Managers will continue their outreach efforts to MPs who were non-responsive to the Cycle 4 Survey or who reported negative answers The survey will remain open through August 15 th Updates to the Cycle 4 Survey can be submitted using the excel form found on the metrics website (same process as previous surveys) Cycle 4 Survey Data was reported on the scorecards on June 12th

7 7 Texas Nodal Program UpdateJuly 7, 2008 Metric Updates Metrics will be updated on a weekly basis Changes will appear on the scorecard on Wednesday afternoon You will be notified Tuesday or Wednesday morning if you will be going red Contact us if you notice any inconsistencies Survey data will now be stockpiled and updated on a weekly basis There will not be a “Wall of Shame” in the Board presentation next week

8 8 Texas Nodal Program UpdateJuly 7, 2008 Status Update: EDS EDS 1 (green) no changes EDS 2 (red) state estimator convergence values were consistently higher last week EMO12 (Network Operations Model and SE Performance) is now amber approximately 71 unobservable buses (less than 2%) EDS 3 (amber) Maintained amber status CRR5 (Trial Operation of Annual CRR Auction during Trials) expected to go amber 7/11 EDS 4 (red) waiting on EMS 5 delivery to proceed with EMO3 (Verify Outage Evaluation System Functionality) site fail-over test scheduled for 7/8 EDS status remains unchanged since the last meeting

9 9 Texas Nodal Program UpdateJuly 7, 2008 Questions ?