Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
● Morning: – Squeeze and collide. – Smooth, orbit rather well under control (max. excursion ~ 0.2 mm at TCT, roughly sigma). Orbit evolution at the.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Friday 23 rd November - morning Coming out of loss maps over night Thu – Fri  in shadow of MKD problem in SPS (and CMS cryo recovery) 07:35 Start pre-cycle.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
Thursday 12 th May - recovery from TS 18:30: cryo back in whole ring, also for RF cavities. Preparing to power. Problem with quench loop S23. Access to.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Tuesday 3 rd May 7:30 Access in the SPS to replace injection kicker magnet terminating resistor after radiation cool down overnight 9:45 probes injected.
“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.
LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
RF observation from Saturday morning Observation of beam induced voltage/power following the two klystron trips: 03:18 3B1 just at end ramp, 1.26E14 p.
Wednesday ● 02h04: Stable beams # b x 121b. – Peak luminosity 1.2e25 cm-2 s-1 ● 08h32: Beams dumped on request. – Length=6h28. Rampdown.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
MP3 List of main Issues during March 2010 MP3 - Team.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
Tue 9/8 – Wed 10/8 Stable beams # :18 RQT12.R7B1 trip. End of STABLE BEAMS # ~86 pb -1 in ~19 hours 20:30 No beam from PSB (RF problem in ring.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Saturday 14:10 Cryogenics back [26 hours 40 minutes] Pre-cycle 15:30 Beam 2 in  Interlock on TCLIB.6R2.B1. Alessandro Masi found a broken sensor, it would.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Tuesday 7/7 & Night 8/7 06:53 Beam lost due to RF problem, understood  08:30 Access –VIP, Experiments, QPS, EPC, ABT, RF, BI, …. 15:15 Access over, expert.
Friday 15th June 01:11 Injection.
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
Summary Friday h38: Ramp down and pre-cycle.
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
Monday morning 08:30 Start of rephasing MD. Dry tests in the morning.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
LHC commissioning Week 38
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Week 36 plan Todo’s: And also: 12+b injection.
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Sunday morning Recovering from 400 kV disturbance.
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Thursday morning 7:20 – 12:30 faults of BLM sanity check, RQX.L8 QPS trip and iris scanner in UJ47. Access: Pt 8 for ELQA on RQX.L8 (The voltage.
Monday 24 October hours of 25ns MD
Tuesday morning 08:30-09:00 Squeeze with probe.
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Thursday 22 September 2011.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Friday morning 08:00 Stable beams with 840b.
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
LHC Status Fro Morning 9-Sep
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Monday 27th August & night
Wednesday 26 October 2011.
Wednesday 14:30 Fill 2011 dumped.
Wednesday morning Waiting for PS – problem on RF cavity.
Saturday 26 November 2011.
Tuesday
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Tuesday
Presentation transcript:

Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15 Pre-cycle 14:16 discovered that RT trims were indeed in during the previous fill and they are probably at the origin of the energy offset of this night. Friday 16 th July - Morning 1

RT funny 2

15:42 Sector 81 tripped. QD threw fast power abort – cause unknown 16:20 Start pre-cycle 18:11 – injecting again 19:22 - fan fault on the power supply for RQT12.R5B2. Reset and go on. Problems loading collimator… Friday 16 th - afternoon 3

Zero injection frequency error AND Perfect Energy Matching. This shows as a very small transient on the Synchro Loop error (peaks at 7 deg max). The initial slope of the Synchro Loop error gives the frequency error on first turns: we have ~ 4 deg in 100 turns = 8.9 ms -> 360 deg in 800 ms. That is a 1.2 Hz error at 400 MHz. The slippage factor is -3.6E-4 at injection and a 10-4 DP/P gives 14 Hz error at 400 MHz. With 1.2 Hz the energy match is better than 10-5 DP/P Injection beam 1 - perfect 4 Philippe Baudrenghien

10 degree phase error Synchro error: ~ 20 deg in 100 turns = 8.9 ms -> 360 deg in 160 ms -> 6 Hz error at 400 MHz or 0.5E-3 Dp/p Try to balance energy mismatch between the two rings: add 5 HZ MHz Injection beam 2 5

Phase and energy fairly well matched for both rings All bunches filled length ranging from 1.27 ns to 1.52 ns No more evidence of bunch lengthening during injections Injection 6

Bunch length at injection 7

8 Nice injection….longitudinally much cleaner than last night, and in fact maybe 2-3 times lower losses on the TDI than over the previous week (still not quite zero, but not far off)

00:44 Stable beams  big beams…  TFB on – helped lifetimes 04:38 Beam dump  vacuum reading acquisition problem, vacuum interlock on dilution kickers – to be followed up today 05:52 QPS OK lost on RB S56 - Looks like one heater power supply (MB.C34R5) is slowly discharging.  Access required – faulty switch (again) Saturday 17 th July 9