March 4, 2013 Photo by Martin Murphy. Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning.

Slides:



Advertisements
Similar presentations
Substation L1/ MCC L1 Update March 21 st, Current Location.
Advertisements

Utility Outage (Steam & Electrical) Commencing March 21, 2009.
January 6. January 7 January 8 January 9 January 10.
July 01, Shutdown Machine Status:  NTF Treatments and Dosimetry as scheduled  Proton Source Commissioning and Studies RFQ Injector.
What is a Conference Assistant??? Conference Assistants (CAs) are on-site liaisons between the Capstone Conference Center and conference participants.
Yasmine Amhis EPFL Yasmine Amhis EPFL Status of the LHC and LHCb Adrenaline.
Communications Infrastructure Committee Update for the IAC Friday, April 15, 2011.
LCLS Beam Parameters, Status and Run Schedule Rick Iverson for the LCLS team 1 R. Iverson ESTB Workshop SLAC, March 2011.
Muon Collider 2011 Workshop Jun 27-July 1 in Telluride, CO Gollwitzer & Nagaitsev presented Attending: Ankenbrandt, Lebedev, Pasquinelli, Popovic, and.
Accelerator Schedules LHC and LHC Injectors Schedules MSWG meeting 16 January 2015 SPSC - 13 January 2015 Rende Steerenberg, BE/OP2 Rende Steerenberg,
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
Summer IT Project Update Tech Talk September 11, 2007.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
Technology Services Update Mary Schoeler: Assistant Vice Chancellor and Chief Information Officer January, 2008.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Expanding and Improving the Technical Infrastructure of the Atlanta Day Shelter for Women and Children Project Advisor Whit Smith Group Members - Taylor.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
PPD Computing “Business Continuity” David Kelsey 3 May 2012.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Linac Status May 19, 2015 Time Meeting D. Raparia.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 1 Draft Schedule Beam off to Experiments 0000 Monday April 30 th Linac continues operations.
1 Kenneth Osborne, 9/14/07 Inter Group communications at the Advanced Light Source. Overview of the different methods of communication between different.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
Maintenance and Accelerator Support RHIC Start Up 12.
LHC (and ATLAS) Status and Plans
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
Asian Test Beam Facilities Satoru Uozumi Kyungpook National University Mar-29 th 2010 Beijing China IHEP Beijing TBF Russia.
PIP Status Report Linac Startup plans 12/05/2012.
May 06, 2013 Photo by Greg Vogel. Thursday, April 18, some tunnel work had to be suspended and many planned jobs had to be postponed due to the flooding.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
HWDB: Operations at the Spallation Neutron Source Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager.
What is a Conference Assistant??? Conference Assistants (CAs) are on-site liaisons between the Capstone Conference Center and conference participants.
NA61 11 October 2010Light Ion for NA61/ S. Maury1 Light Ion in SPS Foreseen to have primary Ar beam physics in 2012 Nothing runs in 2012 NA61 duty cycle.
Andreas Jansson, Neutrino Workshop, ANL, March 3-4, 2004 Possible beta beam scenario(s) in the US Andreas Jansson Fermilab.
Substation L1/ Booster Substation Y-BE2 Update #3 August 15,2012.
PIP Status Report Linac Startup plans 12/05/2012.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Providing Service to High-rise Condominiums Presenter Charles L. Kahanek SWEDE Conference Horseshoe Bay, Texas May 2008.
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
Maintenance Nov 28, Accelerator Access LINAC will remain on RA. It is not yet running. LINAC will remain on RA. It is not yet running. Booster-
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
CTF3 Streak Camera Results and Improvements Aurélie Rabiller BE-BI-PM
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
All Experimenters’ Meeting September 23, Accelerator Operation Summary Calendar Week # 38 NuMI Weekly Integrated Intensity 4.57 E18 protons BNB.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
All Experimenters’ Meeting November 25, 2013 Photo by Martin Murphy.
All Experimenters’ Meeting November 4, Accelerator Operation Summary Calendar Week # 44 NuMI Weekly Integrated Intensity 5.97 E18 protons BNB.
FESS/Ops Shut Down Summary Week Ending 9/7/12. – FESS needs a CUB Cooling Outage for installation of Barriers in the CUB Chiller 4160 Volt Starter Cabinet.
July 29, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.
Uninterruptible Power Supply Improves Reliability at The Australian Synchrotron Sean Murphy – ARW 2013 Melbourne.
Lead from the front Texas Nodal 1 EDS Market Call Weekly Update Feb 06, 2009.
Muon Department Meeting Jerry Annala Staged Commissioning of Muon Campus 17 December 2015.
FESS - OPS SHUTDOWN UPDATE. ELECTRICAL Feeder 46A Cable tie in - COMP. A0,C0, E0 CRYO Transformers & Switchgear - Not Complete Master Substation - COMP.
09:00 Meeting Shutdown Update June 29 th 2015 Cons Gattuso AD Shutdown Manager.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
NA61/SHINE run schedule/plans:
In-Building Working Group Report
CUB Outage Schedule April 21, 2006.
Technology Resources March, 2017.
Photo Gallery Central Location
Presentation transcript:

March 4, 2013 Photo by Martin Murphy

Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning and studies TeV & Muon Rings – Partially available for tours with approval and appropriate training

Power Outages - Unplanned  Feeder 46B o Tuesday, January 29th  Isolated fault (Between F4 & P71)  Repairs pending

MSS Bypass Project - Completed  Booster  High Intensity Lab (HIL)  Neutrino Service Building 7 (NS7)  Proton Service Building 1 (PS1)  Neutrino Service Building 1 (NS1)

Power Outages – MSS Bypass Project  MS2 Oil Switch o February 25 th for ~ 2 weeks  Will be running house power off a generator (Until 3/8)  Impacts – MS2 Service Building and Adjacent Enclosure (M02)  MS1 Oil Switch o March 11 th for ~ 2 weeks (3/11 or 3/ )  Will be running house power off a generator  Impacts – MS1 Service Building and Adjacent Enclosure (M01)

Power Outages – Planned  WH8FC – Wilson Hall 8 th Floor Fiber Central Sunday, March 10 from 0600 – 1200 ○ Although this is a very local power outage, its effects are widespread and all networking in Wilson Hall will be offline including: Finance backup systems (5th floor) Remote Operating Center (ROC) Com Center 12th floor control room Service Desk Cardkey Access – works but no changes or updates ○ DOE Office CUB Minos/IF Underground networking FESS/WH building monitoring (16th floor) Several redundant Kerberos, Windows and Fermi domain controllers will also be down when WH8FC is powered off.

Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - ANU - Proton Source - l