Payloads Operations Integration Working Group (POIWG) Increments 27 and 28 Payloads Programmatic Status January 25-27, 2011 Keith Beckman Increment Payload.

Slides:



Advertisements
Similar presentations
The Vision for Space Exploration – Challenge & Opportunity ISS Panel Report Robert D. Cabana ISS Panel Chair March 30, 2005.
Advertisements

MISSION OPERATIONS DIRECTORATE CARGO INTEGRATION AND OPERATIONS BRANCH Brion J. Au Johnson Space Center/DO55.
Belgian User Support & Operations Centre Ham Video On-orbit Functional Commissioning - B.USOC Contribution ARISS Workshop 3 – 5 April 2014 ESTEC.
1 Head of Russian Federal Space Agency ISS Program International Cooperation Paris, June 17, 2009.
Columbus Operations Columbus Control Centre 8 October 2009 Prague ASE XXII Congress Space – Opportunities for all An Overview to Columbus Operations Reinhold.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations April 26, 2012.
Transition to 6-person crew ASE conference, Praha Oct 8, 2009 Andreas Schön, ESA All dates used in this presentation are examples only, they do not necessarily.
2010 W EST V IRGINIA GIS C ONFERENCE Wednesday, June 9, 2010.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations January 30, :00 AM.
CCSDS SOIS Wireless Working Group (WWG) 01-Sep-2015 Monthly Webcon/Telecon 1 CCSDS SOIS Wireless WG Monthly Webcon: 01-Sep Sep-2015.
Constellation Space Transportation Planning Office July 30, 2009.
Kiyoshi Higuchi Executive Director Japan Aerospace Exploration Agency (JAXA) JAXA Space transportation systems.
CCSDS SOIS Wireless Working Group (WWG) 04-Aug-2015 Monthly Webcon/Telecon 1 CCSDS SOIS Wireless WG Monthly Webcon: 04-Aug New ESA Wireless WG member.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations February 27, :00 PM.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations January 31, :30 AM.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations December 6, :30 AM.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations July 26, :30 AM EST.
ISS Commercial Resupply Services Michael Suffredini ISS Program Manager June 17 th, 2009 Augustine Committee UPDATED: Corrected page 10 (replaced “first.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations June 29, :30 AM EST.
1 MINUS EIGHTY DEGREE LABORATORY FREEZER FOR ISS (MELFI) MSFC Briefing February 2005 John Cornwell
MOL The Mission Operations Laboratory MOL The Mission Operations Laboratory NASA MSFC Huntsville, Alabama BRIC-17 TIR Overview Aug 28, 2012 Tony Cox EO20.
NASA MSFC Engineering Directorate Mission Operations Laboratory MSFC NASA MSFC Engineering Directorate Mission Operations Laboratory Increment 21 & 22.
NASA MSFC Mission Operations Laboratory MSFC NASA MSFC Mission Operations Laboratory EXPRESS Logisitics Carrier (ELC) Operations Overview POIWG #26, August.
1 JEM PAYLOADS Off Console Plan Yoshio Toukaku / JAXA Kensuke Teranishi / JAMSS January 31, 2013 Notice : This technical data is furnished on the condition.
July 26, 2005 Nelda Allen/Colsa1 Configuration Management Process 2 Minor Changes (pages 2 & 5)
NanoRacks, LLC Michael D. Johnson (832) Page No. 1 NanoRacks, LLC Cube Lab Cube Lab Ops TIM – Cube Lab Introduction 11/19/2009 Michael D. Johnson.
Page No. 1 ISS_CM_019 (Rev 01/2011) POIWG – July 2014 Increment 43/44 Overview.
Page No. 1 ISS_CM_019 (Rev 01/2011) Sponsoring Org/Office Code: MIO/OC Name of Forum: POIWG Date: 07/27/2011 Increment Manager/Melissa Owens Increment.
NASA MSFC Mission Operations Laboratory MSFC NASA MSFC Mission Operations Laboratory Approved for Public Release; Distribution is Unlimited Ricardo Rodriguez.
MOL The Mission Operations Laboratory MOL The Mission Operations Laboratory NASA MSFC Engineering Directorate Huntsville, Alabama POIC Status Increment.
Note: The first status check should occur on the launch flight day prior to crew pre-sleep. This is the only feedback the Glacier team has that the Glacier.
MOL The Mission Operations Laboratory MOL The Mission Operations Laboratory NASA MSFC Huntsville, Alabama Cell Bio Tech Demo TIR Overview Aug 28, 2012.
POIWG 1/26/2015 Mana Vautier This presentation is intended solely for the audience to which it is directed. MISSION AND PROGRAM INTEGRATION (MAPI)
EMCS Inc 13 Operations Gary Moore EMCS Ops Lead (256)
Page No. 1 ISS_CM_019 (Rev 09/2011) Pre-decisional, For Internal Use Only Sponsoring Org/Office Code: OZ Date: January 2012 INCREMENT 33/34 PAYLOAD PROGRAM.
Page No. 1 Sponsoring Org/Office Code: MIO/OC Name of Forum: POIWG Date: 01/29/13 Increment Manager/Ben Pawlik Increment Engineer/Maria Baugh-Horstman,
Splinter Utilization Planning Discussion Notice : This technical data is furnished on the condition that it will be used by and disclosed to the receiving.
E-USOC operations in Increments José Miguel Ezquerro Navarro E-USOC/UPM Jul 2010POIWG#28 - Huntsville, AL.
All rights reserved © 2010, Telespazio MARS USOC Operational Scenario Increment and POIWG.
EO10-PPO-051 Revision T 9/25/15 PARC/T. Cassady HRF Rack 2 8PU Drawer Installation and Configuration 1:00 TEXTFlexible Crew  Sessions required as needed.
I29/30 Robonaut Training Strategy Team (TST) Mike Joseph Robonaut Training Coordinator Notice: Material contained.
MOL The Mission Operations Laboratory MOL The Mission Operations Laboratory NASA MSFC Engineering Directorate Huntsville, Alabama Training Strategy Team.
GRAVI2 POIWG #34, July 24 th 2013 Abdul Basit Mohammad N-USOC-NOT-ABM-028, Abdul Basit Mohammad1.
NON-PROPRIETARY July NASA Ames Research Center ARC ISS Utilization Office Cell Bio Tech Demo Payload Overview POIWG MSFC July 25, 2012.
Payloads Operations Integration Working Group (POIWG) #19 Increment 12 Payloads Programmatic Status August 10, 2005 Kevin M. Meehan Increment 12 Payload.
1 POIF Metric Status January 2010 Lybrease Woodard Marshall Space Flight Center Engineering Directorate Mission Operations Lab Operations Directors Office.
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations Date: April 4, 2013 Time:
Microgravity User Support Center (MUSC) Payload Overview POIWG, July Chart 1> MUSC Payload Overview > Patrick Hambloch POIWG > July 2013.
NASA – MSFC, Huntsville, Alabama Muscle Atrophy Research and Exercise System (MARES) Operations Summary Part I/II Karen Somers EO20/ Operations Lead
NASA MSFC Mission Operations Laboratory MSFC NASA MSFC Mission Operations Laboratory Cindy Grant SPACE-X & Orbital Lead POD Office/EO
Page No. 1 ISS_CM_019 (Rev 09/2011) Pre-decisional John Love Lead Increment Scientist (LIS) Andrew Tucker LIS Rep Cindy Romero LIS Rep ISS Increments 37&38.
1 POIF Metric Status March 2008 Lybrease Woodard Marshall Space Flight Center Engineering Directorate Mission Operations Lab Operations Directors Office.
1 POIF Metric Status August 2010 Lybrease Woodard Marshall Space Flight Center Engineering Directorate Mission Operations Lab Operations Directors Office.
June 16, PMDIS TIM Shuttle Operations Coordinators (SOC) Roles & Responsibilities Beth Griggs Shuttle Operations Coordinator
Inc 35/36 Overview ISS Research/Utilization January 30, 2013 Gina Calderon Lead LIS Rep, Inc 35/36 Vlad Shargorodskiy LIS Rep, Inc 35/36 Jorge L. Sotomayor.
NASA MSFC Engineering Directorate Mission Operations Laboratory MSFC NASA MSFC Engineering Directorate Mission Operations Laboratory Increments
Inventory and Stowage Overview Kay Standridge February 26, 2004 MSFC/ESA TIM #2.
Damec Research Aps POIWG Meeting, July 2011 Upcoming Damec Operations by Thomas A. E. Andersen 1.
Page No. 1 ISS_CM_019 (Rev 01/2011) Increment 49/50 Overview POIWG – January 2016 IDM/Kevin Hames LIS/Vic Cooley POM/Becky Grimaldi This document contains.
Page No. 1 ISS_CM_019 (Rev 01/2011)OC3/Stephanne Ploeger/ Page No. 1 ISS_CM_019 (Rev 01/2011) POIWG – July 2013 Increment 37_38 Overview.
NASA MSFC Mission Operations Laboratory MSFC NASA MSFC Mission Operations Laboratory POIWG 23 Increment 17 Payload Operations Status Patricia Patterson.
MOL Mission Operations Laboratory MOL Mission Operations Laboratory NASA MSFC Engineering Directorate Huntsville, Alabama Increment 12 On-Orbit Operations.
Payload Inventory Management & Stowage Operations Processes 10/19/99 Point of Contact Gordon Boswell MSFC/POIF/OI (256)
GRC/OZ Monthly Tag Up – 1 Glenn Research Center Monthly ISS Payload Ops Review ISS Payload Integration, Planning & Operations August 30, :00 AM.
Wireless WG Monthly Teleconference
CCSDS SOIS Wireless WG Monthly Webcon: 04-Aug-2015
SIS-DTN WG Wednesday Afternoon
Wireless WG Monthly Teleconference
An Introduction to the NanoRack Platform and CubeLab Modules
Investigation X – Increment 33 & 34 Scenario (it’s only a template)
Presentation transcript:

Payloads Operations Integration Working Group (POIWG) Increments 27 and 28 Payloads Programmatic Status January 25-27, 2011 Keith Beckman Increment Payload Manager (IPM) JSC/ISS Payloads Office (281) Vic Cooley Lead Increment Scientist (LIS) JSC/ISS Payloads Office (281) Jeff Crislip Increment Payload Engineer (IPE) JSC/ISS Payloads Office (281) Pat Patterson Payload Operations Manager (POM) MSFC/Payload Operations Integration (256)

Page No. 2 Purpose and Agenda l Purpose ‒ Overview Increment 27/28 USOS utilization objectives, research plan, and key issues affecting utilization l Agenda ‒ Increment 27/28 overview ‒ Utilization crew time status »IDRD Main Book allocations »27/28 PTP requirements ‒ Manifest overviews ‒ Issues and watch items

Flight Program Working Group (FPWG) Crew Rotation and Port Utilization Graphic – For Reference Only NASA Official: Sean Fuller Prepared by: Scott Paul Chart Updated: Jan. 11 th, 2011 SSCN/CR: (Post SSPCB) For current baseline refer to SSP IDRD Flight Program Launch Schedule Crew Rotation Stage EVA Port Utilization /7 End DST 3/13 Daylight Savings 2011 PMA-2 SM-Aft FGB/ MRM1 DC-1/ MLM MRM2 (SM Zenith) OCT NOV DEC JAN FEB MARAPR MAY AUG SEP OCT NOVDEC JAN FEB MAR APR MAYJUN JULAUG SEP 11/6 End DST Launch |  | - Cutout (60  ) |  | > (60  ) 28S 9/30 N o S 38P SpX-D3 10/8 2/23 SpX-D2 7/15 9/25 24S 10/8 N o 701 N o P 9/10 24S 10/10 39P 2/19 25S 12/15 N o S 12/17 11/26 Increment 26 9/12 N o P 10/27 40P 7/17 – 7/19 SpX-D2 Window (22S)  R R N 176 days N R N Walker Yurchikhin Wheelock (CDR-25) (23S)  163 days Inc 25 Inc 24 8/31 10/2510/30 ATV2 HTV2 1/20 3/16 1/24 1/30 26S 3/30 N o 231 N R R S. Kelly (CDR-26) Skripochka Kaleri 159 days (24S)  159 days (24S)  159 days (24S)  R N E Kondratiev (CDR-27) Coleman Nespoli 109 days (101 docked) N o P 4/27 5/16 N R R (26S)  Inc 27 Increment 28 26S 4/1 4/26 27S 5/30 N o S 6/1 N R (27S)  6/4 (25S)  43P 6/23 N o P 6/21 A. Borisienko (CDR-28) R. Garan A. Samokutayev J ATV2 2/15 9/16 N o P 8/30 SpX-1 12/7 8/29 42P 4/29 44P 9/1 M. Fossum (CDR-29) S. Furukawa S. Volkov 152 days 170 days N o P 1/28 41P Strategic Timeframe R-28 N o P 10/26 45P 10/28 12/26 10/25 28S 10/2 29S 11/30 N o S 12/2 N R R (28S)  (29S)  Inc 29 Increment 30 R N R-29 R-30 # / days R-27 10/10– 11/4 SpX- D3 25 day U-15, 16, 17 12/14 – 1/8 ATV Dck Win 2/8 – 2/132/20 – 3/10 ATV ULF6 4/20 - 4/30 2/26 – 3/5 ULF5 (14+1) 190 nm 4 EVA 105 STS134 NET 4/19 4/18 EDT LON-MPLM 7/1 – 7/8 8/7, 8/11, 8/16 8/22 – 8/26 11/17 – 11/25 1/14 – 1/22 4/16 – 4/19 6/11 – 6/20 8/11 – 8/17 11/10 – 11/17 8 docked 8/13 – 8/24 8 docked 11/7 – 11/23 8 docked 1/4 – 1/20 10 docked 4/4 – 4/17 Peak ~ 62.0  10 docked 5/30 – 6/18 8 docked 8/1 – 8/15 8 docked 10/31 – 11/15 STS335 LON-MPLM 6/ (12+0) [58] 4-crew 1 EVA 23S 3/16 Burbank(CDR-30) Shkaplerov Ivanishin 168 days Kononenko (CDR-31) Kuipers Pettit 168 days E 5/16 (22S)  R R N (30S)  4/1 MLM (5/7) 12/29 5/1 3/5 ATV3 3/8 N o P 12/27 30S 3/30 N o 704 3R (MLM) 5/5 47P 5/14 31S 5/30 SpX-2 4/12 Orb-1 3/8 ATV3 2/29 HTV3 1/20 SpX-2 4/14 – 5/13 29 d berth 3/11 – 4/9 Orb-1 29 d berth 1/25 -2/24 HTV3 30 days 1/7– 1/16 4/11 Peak ~ 60.5  U-18R Inc 31 46P 4/26 – 5/5 ATV 5/9 6/15 ATV Undock Window 2/21 11/15 R-26 1/21 #5 7/27 Oct JanFeb STS133 2/ (11+1) 190 nm 2 EVA SpX-D1 12/8 Node-2 Nadir HTV2 1/27 60 d berth 3/28 2/183/7 #2 #4,# 3-59 #1 [61] #3 Node-2 Zenith SpX-1 12/9 39 d berth 1/17 12/13 12/19 – 1/5 Orb-D1 12/14 17 day 4/16 4/19 47P N o 415 TBR # 3-60 # 3-8 # 3-61

Page No. 4 Inc 27/28 Crew Time Status IDRD Main Book Allocations from approved TCM package for Revision to CR 12535A Note: Despite 807 hr allocation, Inc 27/28 predicted to be oversubscribed by ~350 hrs PTP Requirements from Inc 27/28 PTP Working Version as of 1/21/11

OZ/Keith Beckman, OZ/Jeff Crislip Page 5 27S Soyuz Ascent: Eval. Of Onboard Diagnostics Kit 0.98 kg Manifest Content Manifest Content Russian Flight Manifest Summary 43 Progress: [FASTER] Vascular CARD [Physiology] [JAXA EPO 7] HRF pantry/SCKs Int. Immune Kits kg 42 Progress: [GRAVI2] SOLO [JAXA Commercial] [CubeLab resupply] [DCB] Ice Bricks HRP SCKs [Int. Immune Kit] SS-HDTV VO2 Max Consumables PCBA Batteries kg 25S Soyuz Descent: Mini ECCO Hicari Int. Immune Samples 4.43 kg 44 Progress: [FASTER] Vascular CARD JAXA EPO 7 HRF pantry/SCKs [MSL SCAs] [Seed Growth] TRITEL HiMassSEE kg 26S Soyuz Ascent: [TRITEL] [Area Padles 6] 0 kg [Red] items planned for deletion. Blue items planned for addition.

OZ/Keith Beckman, OZ/Jeff Crislip Page 6 Docked Operations DCB Packing GLACIER: Transfer ops and packing VIABLE Myco 3 Triplelux A Reaction Self Test CSI-05 Int. Immune Spinal Long Integrated Immune (SDBI) (pre- and post) MAUI, RAMBO, SEITE, SIMPLEX IAPE, BIOKIS, IENOS, IFOAM, Night Vision CubeLab module 7 & 8 MISSE 7 & 8 (EVA) NLP-Cells [5] & 6 NLP-Vaccine-10 Spinal Elongation Orbiter Stand-alone Ops Manifest Content ULF6 Flight Manifest Summary Middeck (ascent) 2DNT2 [SS-HDTV] AMS DDRS NLP-Vaccine CubeLab GLACIER MISSE ORMatE IAPE BIOKIS IENOS VIABLE Night Vision BLB Gloves TRIPLELUX-A MELFI EU Lego Bricks [NLP-Cells] UMS hose Middeck (descent) DCB (x5) GLACIER Vascular CsPINS ISSMP samples [UMS Samples] AMS DDRS NLP-Vaccine CubeLab IAPE BIOKIS IENOS Night Vision IFOAM ERB-2 [Asian Seed] Nanoskelton 2 Hair LOCAD-PTS [PCDF-EU] BLB Microscope & Spectrophotometer Marangoni MSL SCA SODI Colloid CSLM-2 HRF Electronic Media Int. Immune MSG resupply SAME BXF Sleep Short Spinal Spheres tanks NLP-Cells JAXA Commercial Myco Cargo Bay MISSE 7 PECs MISSE 8 SWC InSpace-3 LMM Bio Robonaut SHERE II Sleep Short [SPHERES] CSI-05 VCAM Cable J. Try Zero G J. Commercial Myco Cargo Bay MISSE 7 SWC MISSE 8 PEC AMS ELC3 STP-H3 Ascent Middeck kg Cargo Bay kg ELC 344 kg Ascent Middeck kg Cargo Bay kg

OZ/Keith Beckman, OZ/Jeff Crislip Page 7 ULF7 Flight Manifest Summary Docked Operations DCB Packing GLACIER: Transfer ops and packing MICRO4 NLP Cells7 Bisphosphonates Myco 3 Robotic Refueling Reaction Self Test Integrated Immune Spinal Long STL, CBTM-3, AEM Integrated Immune (SDBI) (pre- and post) MAUI, RAMBO, SEITE, SIMPLEX BRIC/SyNRGE CubeLab NLP-Vaccine-17 Sleep Short FOB Myco PSSC Orbiter Stand-alone Ops Manifest Content Middeck (ascent) Vaccine GLACIER Micro4 STL CBTM-3 AEM1 BRIC/SyNRGE DCB (x2) NLP-Cells CubeLab Forward Osmosis Bag (FOB) Plant Signaling Sleep Short MSL SCAs J. Commercial JAXA EPO7 SS-HDTV Myco VCAM Middeck (descent) Vaccine GLACIER Micro4 STL CBTM-3 AEM1 BRIC/SyNRGE DCB (x2) Cubelab ISSAC DCB (x3) NLP Cells-5 [CSI-05] Forward Osmosis Bag Sleep Short UMS Samples Integ. Immune Vascular BLB Microscope Spectrophotometer J. Commercial CsPINS 2DNano Marangoni JAXA EPO Myco MPLM HRF ECG Kit HRF SCKs Integ. Cardio Integ. Immune UMS validation Kit PFS Cylinders Bisphosphonates SPHERES CO2 Tanks Dynamic Surf FSL VMU EPM Video Unit LUXAIS ESEM (x5) Remote power Electrical Module PCDF EU MPLM [DCB] Cubelab HRF pwr supply FCF H/W Amine Swingbed MERLIN Tomatospheres [HiMassSEE] SPHERES Plant Signaling Robonaut Express equip. [MSL LGF FM] [ALTEA Shield Tiles] Mini ECCO Energy kit ESEM(4) Cargo Bay Pico Sat Robotic Refueling Ascent Middeck kg MPLM kg Cargo Bay kg Descent Middeck kg MPLM kg Cargo Bay 49.9 kg

OZ/Keith Beckman, OZ/Jeff Crislip Page 8 Issues and Watch Items Vehicle traffic –Timing of ULF5, ULF6 and ULF7 –Possibility of SpX-D2 and D3 combining and launching in SpX-D2 window –HTV2 and ATV2 undockings and “road to” tasks for each Crew time –Inc 26 roll-over uncertainties (both utilization and non-utilization) –Stowage jamboree –Stowage and trash ops between ULF5 and HTV2 undock –Possibility of USOS EVA between ULF6 and ULF7 Manifest –Utilization req’ts for Progress continue to evolve –Number of AEMs on ULF7 (2 vs. 3) –ULF5 and ULF6 return manifests full, yet more to return Utilization ops –Remote terminal (RT) / Low Rate Telemetry (LRT) limitations for P/L MDM –Robonaut –MARES commissioning –SS-HDTV –MSG annual certification and overall schedule

Page No. 9 Summary l Per IDRD allocations, USOS Utilization looks good (~800 hrs), but Inc 27/28 oversubscribed by ~350 hrs l Upmass is not a problem, but continual movement of req’ts between flights is challenging l ULF5 and ULF6 returns are full; capability exists on ULF7 ‒ Please request return of any items no longer needed on ISS l Utilization is well positioned going into Final OOS, but crew time impacts from existing oversubscriptions and Inc 26 roll-overs may create problems for Inc 27 planning l Inc 27/28 team will ensure science is optimized for all Partners within given constraints ‒ Experienced and cohesive Utilization team ‒ Superb requirement look-ahead and tracking tool ‒ Top-notch planners at POIF and JSC ‒ Positive culture shift underway (towards Utilization first)

OZ/Keith Beckman, OZ/Jeff Crislip Page 10 June 5, 2009 Back-up: Inc 27/28 Multi-lateral Utilization Plan (r) – Reserve Activity 27S/ULF-7 Stages 26S/ULF-6 Stage JAXA Payload Ops ● Area Padles ● Biological Rhythms ● Commercial ● CsPINs -2 ● Hair ● Hicari ● JAXA PCG ● Marangoni Exp ● Marangoni UVP ● Myco ● Ryutai Rack maintenance ● Saibo rack maintenance ● TEM for SpX ● 2D Nano Template-2 NASA Payload Ops. ● AMS ● ARISS (r) ● BASS ● BCAT-3 (r) ● BCAT-5 ● BCAT-6 ● Bisphosphonates ● CCF ● CFE-2 (r) ● CSI-05 ● Cube Lab ● DECLIC HTI-R/SCWM ● DTN ● EarthKAM ● Education-1 ● EPO-Demos (r) ● Functional Task Test ● HREP ● HRF Facility ● InSPACE-3 ● Integrated Cardiovascular ● Integrated Immune (r) ● ISSAC ● NIH-1 ● NLP-Cells-7 ● NLP-Vaccine-13 ● NLP-Vaccine-17 ● Nutrition (r) ● MDCA/FLEX ESA payload ops. ● ALTEA-Shield ● BioLab (r) ● CARD ● EMCS Maintenance ● EPM VU Removal ● FSL VMU Removal MAR APR MAY JUN JUL AUG SEP 4/1 26S 6/23 43P 7/1-7/8 ULF-7 9/1 44P NASA payload ops. ● AMS ● ARISS (r) ● BASS ● BCAT-3 (r) ● BCAT-5 ● BCAT-6 ● Bisphosphonates ● CCF ● CETSOL-2 ● CFE-2 (r) ● Cube Lab ● DECLIC HTI-R/SCWM ● DTN ● EarthKAM ● Education-1 ● EPO-Demos (r) ● FLSS/SQF ● Functional Task Test ● HREP ● HRF Facility ● InSPACE-3 ● Integrated Cardiovascular ● Integrated Immune (r) ● ISSAC ● MDCA/FLEX ● MDCA/FLEX-2 ● MICAST-2 ● Micro-4 ● MISSE 8 JAXA payload ops ● Area Padles ● Biological Rhythms ● Commercial ● CsPINs -2 ● Evaluation of onboard diagnostic kit ● Hair ● Hicari ● JAXA EPO6 (return only) ● JAXA EPO 7/ Doctor Demo ● JAXA EPO7/ Educational activity ● JAXA EPO7/ Space poem ● JAXA EPO7/ Try Zero G ● JAXA EPO7/ Video ● JAXA PCG ● Marangoni Exp ● Marangoni UVP ● Myco ● Saibo rack maintenance ● SS-HDTV ● TEM for SpX ● 2D Nano Template-2 ● Ryutai Rack maintenance ESA Payload Ops ● BioLab (r) ● EMCS Maintenance (*) ● Geoflow-2 ● Gravi-2 ● Greenhouse (r) ● Passages (r) ● SOLO ● Thermolab (r) ● TriTel (r) ● Vessel Imaging ● Vessel ID ● 3D-Space (r) 3/16 24S 5/16 25S 4/29 42P 6/1 27S 4/3-4/12 ULF-6 9/16 26S ● MDCA/FLEX-2 ● Micro-4 ● MISSE 8 ● PACE-2 (FIR) ● Pro K ● Reaction Self Test ● Reaction Self Test (r) ● REBR ● Repository ● Robonaut ● Seed Growth-2 ● SLICE ● SNFM ● SpaceDRUMS ● SPHERES ● SPRINT ● STP-H3 ● VCAM ● VO2 Max CSA Payload Ops ● Vascular ● Comm & Outreach * – Can occur in different stages, but performed only once CSA Payload Ops ● Vascular ● Comm & Outreach ● MSRR-1/MSL ● NLP-Cells-7 ● NLP-Vaccine-13 ● Nutrition (r) ● PACE-2 (FIR) ● Pro K ● Reaction Self Test (r) ● Repository ● Seed Growth-1 ● SETA-2 ● SLICE ● SNFM ● SpaceDRUMS ● SPHERES ● SPRINT ● STP-H3 ● VO2 Max ● VCAM ● Geoflow-2 ● Mini ECCO Packing ● Passages (r) ● PCDF EU Removal ● SOLO ● Tritel ● Thermolab (r) ● Vessel Imaging ● 3D-Space (r) ● Vessel ID (*)