2/27/ PHENIX WEEKLY PLANNING Feb. 27, 2014 Don Lynch
2/27/ This Week Run 14 Continues Plan/Install MPC-Ex FEM Plan for 2014 Shutdown Tech Support for Run 14 as required New work permit for MPC-Ex FEM & rack installation Support for sPHENIX efforts as required
2/27/ Next Week Run 14 Continues Access 3/5? Install MPC-Ex FEM & Install S/S tubing on leaking VTX/FVTX Teflon Other IR maintenance/repairs Plan for 2014 Shutdown Tech Support for Run 14 as required Support for sPHENIX efforts as required
Mechanical installation Complete Services connected Rack assembly & FEM assembly waiting for final FEM modules MPC-Ex Initial (Partial) Installation 2/27/2014 4
5 sPHENIX Prototype Beam Test of combined EMCAL and HCAL prototypes at Fermilab in Feb /27/2014 Should be finishing up at FERMILAB Next week
2/27/ sPHENIX Detector Subsystems
sPHENIX Overall Detector Design Concept 2/27/2014 7
8 sPHENIX Overall Structural/Support Concept
2/27/ sPHENIX HCal Mechanical Design Concept HCal Module HCal Internal Steel Assembly (Same as concept used in prototype) HCal Scintillator Light Collection (Improvements to Prototype are needed)
2/27/ sPHENIX Flux Return End Caps, Basic Concept
2/27/ Updated sPHENIX Models PHENIX Decommissioning Plan is evolving sPHENIX
2/27/ ePHENIX Plan View Elevation View
2/27/ planned Technical Support & 2014 Shutdown Support for run 142/3-6/30/2014 Support for sPHENIX prototype tests at FermiLab1/21-2/25/2014 Procure & Fabricate parts for MPC-Ex North and South1/1/2014-6/30/2014 Assemble & test MPC-Ex South, ready for installation3/1-7/1/2014 End of Run Party7/11/14? Assemble & test MPC-Ex North, ready for installation7/1-9/25/2014 Start of Shutdown Tasks (purge flammable gas, disassemble and stow shield wall, remove collars, move EC to AH, Move MMS south, etc.)7/14 – 7/25/2014 Install scaffolding in Sta 1 South7/28/2014 Remove MPC-Ex prototype, Install new MPC-Ex South7/28-8/22/2014 Maint. & Repairs for MPC South, BBC South, RPC1 South, MuTr sta 1 South, as necessary7/28-8/22/2014 Remove scaffolding from sta 1 south, Move CM South8/25/2014 Install scaffolding in Sta 1 North8/26-8/29/2014 Prep MPC-Ex North installation area9/1-9/26/2014 Install new MPC-Ex North9/29-10/17/2014 Remove Sta 1 North scaffolds, Move CM North 10/20-10/24/2014 Other detector supportTBD Infrastructure Maintenance and ImprovementTBD Decommissioning of obsolete PHENIX detector equipmentTBD sPHENIX Supporton-going End of Shutdown Tasks (Move MS north, roll in EC, install collars, remove 10 ton cart, plates and manlifts, build shield wall, etc.)10/27-11/26/2014 Pink/White/Blue Sheets1/17/2014 End of Shutdown Party???? Start Flammable gas flow???? Close shield wall, install radiation interlocks and prepare for run 1412/31/2014 Start run 151/2/2015
2/27/ PHENIX Safety and Security 1. From Ray Karol: BNL can now can accept plastics marked with numbers 1 to 7 for recycling, the same as in Brookhaven Town. In the past only 1 and 2 plastics were accepted. 2. Enter your FY 2014 Goals with PeopleSoft by March 7 th
2/27/ Safety and Security
2/27/
2/27/ Where To Find PHENIX Engineering Info Run 14 Continues! RIP GHOSTBUSTER Egon Spengler
2/27/ Crane Mishap Crane Failure Accident Important safety tip