Purchase Module Implementation 28/11/2002 Initiation & Briefing
Purchase Module Implementation Road Map for Implementation Schedule for Implementation Master Data
Mfg/Pro - Purchasing Road Map Study Modeling Customization Data Identification/ Preparation CRP Training Go-Live Data Validation Data Charging Initiation
Mfg/Pro - Purchasing Listing of all the activities/transactions carried out by the Purchase Department under the respective Unit Conduct As-Process Study as per the activities identified Activity List * Cover All Units
Mfg/Pro - Purchasing Study of the existing process with the Process Owners Controls/Checks in the Current Process & System Understand flow of documents within / outside PEC Current Reporting & Report requirements Study * Cover All Units
Mfg/Pro - Purchasing Map existing/new process to MFG/PRO Map Report requirements to MFG/PRO Map Master Data Supplier Master Credit Terms Item Master Price List Taxes & Add-on charges To-Be Model Review with the Process owners Identification of Users Modeling * As per the Go-Live Plan
Mfg/Pro - Purchasing User Training on the General Flow of Purchase Module in MFG/PRO Would cover all the options in MFG/PRO related to Purchase / Related Modules Masters Transactions Reporting Linkages (Accounts Payable, Inventory control) Training
Mfg/Pro - Purchasing Conference Room Pilot on the To-Be Model Prepare Business Cases Prepare data for CRP Execute Transaction & Verify Review results of CRP CRP
Mfg/Pro - Purchasing Go-Live Preparation Readiness of the System User Training Address CRP issues Complete data charging/validation Pre-Migration Activity Transfer Open Purchase Orders Transfer Opening Stock Go-Live & Support Go-Live
Mfg/Pro - Purchasing Masters & Control Files
Mfg/Pro - Purchasing System/Account Control File Purchase Control File Inventory Control File Control Files * As per the Go-Live Plan
Mfg/Pro - Purchasing Inventory Status Code Maintenance Inventory Status Product Line Maintenance Item Master Site Master Location Master Supplier Master Credit Terms Tax Structure Add-on Cost Data Requirement * As per the Go-Live Plan
Mfg/Pro - Purchasing Go-Live Schedule Unit 1A & 1BFebruary Unit 2A, 2B, 5April – 2003 Unit 3May
Mfg/Pro - Purchasing Stage wise Schedule Study Modeling Customization Data Identification/ Preparation CRP TrainingGo-Live Data validationData charging Initiation 02/12/02 07/01/03 08/01/03 18/01/03 10/01/03 01/02/03 20/12/02 16/01/03 to 20/01/03 03/02/03 to 04/02/03 05/02/03 10/01/03
Mfg/Pro - Purchasing Questions? Thank You