SPS BEAM DUMP UPGRADE FUTURE CABLING CAMPAIGNS Georgi Minchev Georgiev EN-EL-FC.

Slides:



Advertisements
Similar presentations
“LHC Controls for Sector Test” Planning SPS Extraction Kicker and Septa LHC Injection Kicker and other equipment (beam stoppers, dumps,...) Etienne CARLIER.
Advertisements

Backwards Compatibility L4 – L2 W. Weterings LBCC - 14.
LIU CABLING & OPTICAL FIBRES STRATEGY Georgi Minchev Georgiev EN-EL-CF.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
LIU-IONS Linac3 meeting LIU Project – Planning and Installation Julie Coupard EN/MEF-OSS.
TS, Length of YETS EYETS LIU & CONS Project
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Additional Lift to Access ECA5 Etienne Carlier, Jean-Louis Grenard, Damien Lafarge SPS Dump Upgrade Meeting 09/07/2015.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
SPS re-commissioning with beam K. Cornelis PS-SPS days.
Plan. 12/05/ Who are we? PM (Project Management and Resource Planning) – APT – IMPACT – PPTEU2 – Plan LS1 – 2012 –…–… Plan V2 – From LS1 to LS2.
STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011.
Injector De-cabling Project Enlarged project meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
SPS Dump relocation Radioactive Dump storage alternatives JL GRENARD EN-HE
Extraction and beamline progress B.Goddard TE/ABT.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
SPS Beam Dump in LSS5 Etienne Carlier on behalf of LIU-SPS LSS5 Dump Working Group. IEFC –
POTENTIAL EN-MME DESIGN JOBS IDENTIFIED BUT CURRENTLY NO REQUEST FROM EQUIPMENT OWNERS TO EN-MME EDMS B.RIFFAUD On behalf of EN-MME design team.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 17 th December 2013.
Christophe Martin TE-MPE-EP 02/06/ The BIS and SMP activities during LS1 MPE Group Review, 2 June 2015 Christophe Martin, Stephane Gabourin & Nicolas.
TE-CRG Activities D. Delikaris, TE-CRG.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Status of the LSS5 beam dump and proposed relocation of LSS5 systems Etienne Carlier on behalf of LIU-SPS LSS5 Dump Working Group LIU-SPS Coordination.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
LSS1 post LS2 F.M. Velotti, B. Goddard. Q-Dogleg in LSS1 The quadrupole misalignment in LSS1 was needed to dump horizontally wide beams (e.g. FT beam.
LSS1 Space Reservation Etienne Carlier
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Planned activities during (E)YETS… up to LS2 for PSB-PS equipment Etienne CARLIER On behalf of TE/ABT/EC.
Reminder of upcoming milestones For all machines: Nov. 2012:Table of performance parameters Jan. 2013: Baseline activities defined Feb. 2013: Update APT/EVM.
LIU-SPS T. Kramer, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 20 th November /11/2015 LIU-ABT Review - SPS2.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
LIU–PLI report LIU Project Team meeting. Follow-up on the Engineering Change Requests Engineering Change Requests for the YETS PSB PS.
Electrical Group Inputs for LIU-Ions J. Devine, on behalf of EN/EL.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Linac4-PSB 160 MeV connection readiness review
BE-ICS activities for LIU Project
YETS & LS2 Reminder P. Lelong / G. Georgiev / JM Lassausse
BE-ICS Activities during the LS2 Period (15 min)
TE-MSC activities in SPS during LS2
Injector De-cabling Project
Impact of TIDVG problem on LSS5 dump design schedule
LIU – EVM status and next steps
SPS - EYETS 2016/17 Vacuum systems planning
Design of TIDVG#4 A. Perillo-Marcone (EN-STI).
EC Activities Status for the LIU
LIU–PLI report LIU SPS meeting.
YETS & LS2 Reminder G. Girardot 20 juin 2017.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
TE-ABT Activities for LS2
EN-HE SPS works during EYETS
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Status with crucial LSS5 kicker transmission line cables
Georgi Minchev Georgiev EN-EL-FC
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Insert Presentation Title Here Insert Presentation Summary Here
LIU-SPS review for BI (no BWS)
SPS Planning meeting for LS2 #26 Vacuum sectors status
SPS Injection BIS - Draft requirements
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

SPS BEAM DUMP UPGRADE FUTURE CABLING CAMPAIGNS Georgi Minchev Georgiev EN-EL-FC

Summary 25/02/2016 Georgi Minchev Georgiev EN-EL-FC 1.Declaration in PLAN 2.FC demands

25/02/2016Georgi Minchev Georgiev EN-EL-FC 1.Declaration in PLAN 1/2 PLANUpgradeAction Equipment or System impacted LocationGroupContact New Beam Dump New beam dump system in LSS5, with full shielding and remote handling, plus modified kicker system New Beam Dump Located in LSS5 / ECA5 / BA5 TE-ABT Etienne Carlier New Beam Dump Relocation of present LSS5 systems due to new beam dump system in LSS5 UA9 experiment eCloud experiment Beam instrumentation experiments LSS5TE-ABT Etienne Carlier Relocation of present LSS5 systems due to new beam dump system in LSS5 UA9 experimentsLSS Relocation of present LSS5 systems due to new beam dump system in LSS5 Beam instrumentation LSS5 Relocation of present LSS5 systems due to new beam dump system in LSS5 CollimatorsLSS5EN-STI Relocation of present LSS5 systems due to new beam dump system in LSS5 e-CloudLSS5

25/02/2016Georgi Minchev Georgiev EN-EL-FC 1.Declaration in PLAN 2/2 PLANUpgradeActionEquipment or System impactedLocationGroupContact New Beam Dump Removal of present beam dump system from LSS1 and rearrangement of remaining LSS1 systems Removal of TIDH & TIDV dumps Removal of MKDV & MKDH kickers Removal of TFDH, BGSH, TFDV & BSGV monitorsl Replacement of QDA117 by QD117 Replacement of QFA118 by QF118 Modification vacuum sectorisation LSS1 / BA1 TE-ABT Etienne Carlier Removal of present beam dump system from LSS1 and rearrangement of remaining LSS1 systems Remove the Scraper BSHV LSS1 Removal of present beam dump system from LSS1 and rearrangement of remaining LSS1 systems Move the beam instrumentation LSS1 Removal of present beam dump system from LSS1 and rearrangement of remaining LSS1 systems Remove the beam dumpLSS1

2. FC demands -LIU shall ensure correct insertion of all activities in PLAN tool – works & projects with sub works LIU shall provide before end of March 2016 the expected work volume (No of cables, average length) needed for FTEs estimation Long Shutdown Commissioning Operation Technical Stop YETS 2015 EYETS 2016 * YETS 2017 LS2 *Be ready by end of 2016 in the event of possible full linac4 connection Today we are here LIU shall provide before end of September 2016 LS2 pre-requests for budget envelopes estimation All definitive LS2 requests (DIF, DIC, DIR, DEC) shall be submitted before 21/12/ /02/2016Georgi Minchev Georgiev EN-EL-FC Work anticipation before LS2 - All definitive requests (DIF, DIC, DIR, DEC) shall be submitted before 30/06/2016

Thank you!