What? Deployment of the first full KM3NeT string, a.k.a Detection Unit. Thanks to Aart Heijboer for the nice drawings!

Slides:



Advertisements
Similar presentations
Good Morning! Today is ____________________. I get out of bed when ______. After I wake up, I must _______ I got to bed when _______. Before I sleep, I.
Advertisements

The Race is On! Putting Words in Alphabetical Order.
FPSO Mooring Monitoring & In-service Inspection FPSO Research Forum Richard Leeuwenburgh College Station – May 1 st 2003.
A Kind Dolphin Saves The Day. One sunny morning I went to the beach. When I arrived, I found a spot where I put up my umbrella. I settled my things and.
2 nd Day of Let’s Go Home Activity Complete #5 -#10 in class today 9 ft 2 = 1 yd Draw Remnants! Show ft 2 and yd 2.
Seasons of the year Monika Strąk. Information about the year There are four seasons in the year. We can see winter, spring, summer and autumn; twelve.
Comic Strips in MS Word Or Powerpoint.
366,84 m2 114,09 m2 220,84 m262,34 m2 Renaissance Premium have 2 underground parking floors which let 66 cars to park safely. 1 st Floor Bank Cafe Renaissance.
Revision Revision classes are continuing at lunchtime, after school and occasional Saturdays until half term Check with your subject teachers what sessions.
Jan 2009 U. Katz: Astroparticle Physics 1 What is KM3NeT – the Vision  Future cubic-kilometre sized neutrino telescope in the Mediterranean Sea  Exceeds.
A.Margiotta, SNOW 2006, Stockholm, 6 May 2006 Status Report of the NEMO Project (NEutrino Mediterranean Observatory) Towards a km 3 Neutrino Telescope.
Start Game. The crime begins  The queen was mysteriously was murdered while you were on guard. The others blame you for the crime. You get put in the.
KM3NeT-IT The Capo Passero Infrastructure M.Anghinolfi –INFN-Genova.
Status of the KM3NeT Project  What happened so far  The KM3NeT Conceptual Design Report  The Preparatory Phase: Towards Implementation 3rd Workshop.
What is a Computer Network? Two or more computers which are connected together.
Introduction to future synergy options Uli Katz ECAP, Univ. Erlangen Deep Ocean Cabled Observatories Amsterdam, May 2012.
Thumb doesn’t count!!! 3 3.
Barton St Peter’s Advent Calendar.
Colin Pritchard Driving School Customer Satisfaction Survey Results Last Updated 1 st January 2014.
Current Electricity Parallel Circuit Notes Rule #1: In a parallel circuit electrons have more than 1 path to follow.
INFN Bari, Bologna, Catania, Genova, LNF, LNS, Napoli, Pisa, Roma Università Bari, Bologna, Catania, Genova, Napoli, Pisa, Roma “La Sapienza” CNR Istituto.
Fronted adverbials Li: I can identify and begin to use fronted adverbials in sentence structure A fronted adverbial goes at the beginning of a sentence.
25 km E offshore Catania 2000 m depth TSS Frame Buoy Junction Box e.o. connection e.o. cable from shore Shore laboratory, Port of Catania e.o. cable.
This is both the Beatles and the Isley Brothers.
Calibration Methods and Tools for KM3NeT V. Kulikovskiy on behalf of the KM3NeT collaboration.
Best race Ever [10K,]5K & 1 Mile Course Overview [Location – City, GA] [ ] Connect Race | 1431 Capital Ave Suite 123 Watkinsville GA |
Antares Slow Control Status 2007 International Conference on Accelerator and Large Experimental Physics Control Systems - Knoxville, Tennessee - October.
My weekend ByAsun In the morning... I got up at 9:30 I had breakfast at 10:00 I went to the park at Saturday 22nd February.
Multiplication with Arrays and Boxes – A Visual Model.
It was Friday night… I stayed working till late in the night, I was the last one to left the building, I was completely alone…
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
SundayMondayTuesdayWednesdayThursdayFridaySaturday Instructions For every day in December 2014, draw and label the phases of the moon. 6th = full moon.
ROV for telescope construction: possible use of Cougar Joint meeting WP2, WP3, WP4, WP5 Paris February 2009 Jean Roux, AIM for CPPM Joint meeting.
PPM DU Sea Qualification Tests 1.General constraints & requirements 2.Preliminary tests 3.Full mechanical test.
J-W Schmelling Nikhef Amsterdam Electronics- Technology of January PPM-DU optics for KM3NeT Collaboration meeting Marseille PPM-DU: A three.
KM3NeT-Toulon Infrastructure 22/06/121 NB: focus on latest developments, see February presentation in Catania for details KM3NeT meeting Erlangen,
The KM3NeT-IT sea bed infrastructure Collaboration meeting in Ischia, May 19th sea operations (see talk from Klaus) The new Cable Termination Frame Integration.
Seafloor Network KM3NeT Italia Strategy, Milestones and Cost R. Papaleo 22 june 2012.
Rosanna Cocimano Amsterdam, 5-6 July 2010KM3NeT WPF/L General Meeting Rosanna Cocimano INFN LNS Power plan for detector layout Presented in TDR.
SEA operations – June 2012 Short summary report R. Papaleo 22 june 2012.
KM3NeT WPF/L NIKHEF- MECABAR 1 A.Cosquer on behalf of the KM3NeT consortium MECABAR PROJECT PLAN 1- Context 2- 3D views and responsibilities 3-
Site for the PPM-DU String Layout Possible Site / Properties Power / Communication Contribution / Planning R.Papaleo, P.Lamare, E.Heine Bologna.
Deployment Test Program P.Kooijman. Goal of tests Validation of the LOM deployment – Has had three previous tests – First included rudimentary cable –
WP F/L Detection Unit Mechanical Structure and Deployment R. Papaleo 130/03/2011.
Marseille 30 Dec ’13 KM3NET Marine Operations Catania - Status Klaus Leismüller.
Seafloor Network Km3Net phase1 meeting R. Papaleo 30 jan 2013.
PPM-DU (WORKING DOCUMENT, DO NOT PUBLISH) A three DOM Detection Unit in place of an Antares string. Nikhef for KM3NeT: PPM-DU optical network DRAFT!, designed.
WP F/L Seafloor network, deployment vessels and ROVs for PPM P. Lamare – CEA Irfu 1WPF/L- PPM DU site- P. Lamare30/03/2011.
CLB/DAQ meeting, Paris APC, 05 September DAQ in infrastructure and DU foot P. Lamare (CPPM)
Pre-Production Models for KM3NeT
PPM 30/10/2012. In-situ validation programme Oct/Nov 2012: VEOC prototype in Atlantic (monitor fibres, pressure) Dec(?) 2012: multi-PMT.
Status Optical System KM3NeT
Back to School Night Parents to-do list: Sign in Sign up for 1 party
Concluding remarks E. Migneco
Belgium 6/3/ /3/2017
White Rabbit in KM3NeT Mieke Bouwhuis NIKHEF 9th White Rabbit Workshop
Catania Jan ’14 KM3NET Italy Marine Operations CTF change out
Els de Wolf 20 February 2012, Catania
(NEutrino Mediterranean Observatory): Toward a km3 Neutrino Telescope
Junction Boxes for KM3NeT
Catania 20 Feb ’13 KM3NET Marine Operations Catania - Status
Parallel Circuit Notes
THE ANTARES SITE SECONDARY JUNCTION BOX
HOW TO CHECK YOUR PROGRESS
1-4 Quartiles, Percentiles and Box Plots
A film starts at 13:45 and lasts for 1 hour and 35 minutes
Daily Agenda for Rules & Expectations Our website Review Mitosis
Graphic Design Semester 1 Final Exam
<name of your famous author>
Drill of the Flight COLUMN LEFT
Presentation transcript:

What? Deployment of the first full KM3NeT string, a.k.a Detection Unit. Thanks to Aart Heijboer for the nice drawings!

Where?

Timeline 1st of December 17h30: Ambrosius tide left Malta. My Arrival in Portopalo di Capo Passero

Timeline 2nd of December. 6h00: Ambrosius tide started operation on site. – Interlink Cable laying – ROV inspection of Junction boxes – Mark deployment position for Detection unit DU connection expected 2nd of December at 23h00.

Timeline 2nd of December. 17h00: previous operations finished. – Deployment of DU postponed to 3rd of December early morning> better sea conditions. – Time to run test with Junction boxes, – finish shore station infrastructure

Timeline 3rd of December. 02h08: DU2 splash

Timeline 3rd of December. 02h08: DU2 splash

Waiting (a.k.a. trying to sleep)

Timeline 3rd of December. 01:00 bed time, awaiting the deployment. Whatsapp for updates through the night. Finally at 6:34 show time!

Timeline 3rd of December. 09:00 DU2 on spot S1009

Timeline 3rd of December. 09:32 DU2 interlink connected to Junction box and DU.

Timeline 3rd of December. 09:33 Showtime! Switch on procedure started

Timeline 3rd of December. 9:54 Succes with DU still on LOM

Timeline 3rd of December. Switch off all offshore equipment. Start unfurl procedure with ROV Make visual survey of DU with ROV after unfurling.

Timeline 3rd of December. 18:55 ROV starts inspection of DU

Timeline 3rd of December. 21h00 ROV inspection finished. ROV parked in safe position. All system GO!

Timeline 3rd of December. 21h55 Succes!!

Timeline 4th of December. 13h34 First KM3NeT data is taken!

Timeline 4th of December. 16h51 Full DU running with 18 DOM’s !

Timeline 5th of December. 10h00 Trying to fly home