Normanton/Karumba WTP Upgrade Matt Fanning Director TBG Pty Ltd
Normanton/Karumba Shire pop: 2100 (Wet season) Karumba residents: 600 Karumba tourists: 2,000 Industry: Mining, tourism fishing
Existing Scheme Normanton/Karumba Water Treatment Plant –1963 – Normanton Water Supply Established –1982 – New 300mm rising main and Clear water storage, 23km rising main – Karumba connected 42km rising main –1999 – capacity upgrade (copied existing clarifiers), new storages both Normanton and Karumba –Capacity of 3.5 ML/day, –Storage Capacity 2.36ML Normanton, 5ML Karumba
Project Summary Normanton/Karumba Water Treatment Plant –2000 – Planning report – $1.68M –2003 – SCAP funding awarded - $3M grant –2004 – Glenore Weir raising investigation –2006 – Telemetry system implemented (basic automation, but mainly alarms and reporting) – further investigations little traction –October 2009 – Peer Review Hyder Consulting –2009 – Advised by State that SCAP Funding Withdrawn loss of $1M back to Government –November 2009 – Design Awarded to BTO –December 2010 – Works commenced –June 2011 – Works completed
Scheme Issues High Operator costs – Manual processes Difficult to operate – SCADA not full automation High risk of water quality failure Changing water quality guidelines Building required renewal Equipment out dated and high maintenance Upgrade could only occur during the wet season
Scheme Vision To implement a cost effective and reliable Water Treatment System for the towns of Normanton and Karumba.
Basic Principles of WTP Pump water from source location
Basic Principles of WTP Remove large particles in clarifier Coagulant
Basic Principles of WTP Remove fine particles in gravity filter
Basic Principles of WTP Apply disinfection – generally chlorine TO SUPPLY
Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Clarifier 2 Filter 1 Clarifier 1 Washwater Air Scour Raw Water Existing Building Res. #1 Res. #3Res. #2 Dosing Points Existing Plant Overview
State of WTP in 2009 WTP review (2009) 1. Catchment management issues leading to raw water contamination; 2. Extremes of turbidity in the raw water difficult to treat; 3. High filtered water turbidity leading to risk of pathogen shielding and breakthrough; 4. Elevated iron levels leading to oxidant consumption and discoloured treated water; 5. Compromised disinfection efficiency; 6. Presence of Hydrogen Sulphide in Supply Sources; 7. Tastes and odours in the treated water.
State of WTP in 2009 Existing chemical systems Did not meet Workplace H&S standards Chemical make-up labour intensive Chemical quality open to human error Chemical dosing set by operator Dosing not proportional with flow
Dosing System
State of WTP in 2009 Existing Clarifiers Poor performance at high flows Poor performance when high turbidity Problems de-sludging Odour problems Solids carry-over to filter
Clarifiers
State of WTP in 2009 Existing Filters Poor filtration (poor water quality) Manual washing; Labour intensive Damage to filter media
Poor filter Performance
Old Backwash system (used to clean filters) Flow too low (poor washing of media) No standby pump Difficult to prime Labour intensive No NRV fitted to pump State of WTP in 2009
Backwash Pump Air Blower Poor Backwash System
State of WTP in 2009 Old Air Scour (used to help wash filters) Air flow too low (poor agitation of media) No standby blower Labour intensive
Poor Air Scour System
State of WTP in 2009 Chlorine dosing Not proportional to flow No gas detection & alarm Labour intensive
Poor Chlorine Dosing System
State of WTP in 2009 General state of building Not cyclone rated Termite damage Leaking Possible asbestos
Risk? Risk Assessment Risk CategoryRisk ItemPROBCON Risk ScoreRisk Rating Water Quality Protozoa Very High Bacteriological470280Very High Disinfection By-Products31030Moderate Aesthetics (Taste, Staining)51050High Water Supply Short Term Loss of Supply450200Very High Extended Loss of Supply370210Very High Health & Safety Building & Stairways470280Very High Chemical Handling350150High
Why Automate? Main reasons to automate the WTP –Reduce labour costs ($200k/yr) –Improve quality of water –Optimise chemical use (save $$$) –Improve reliability of plant –Accurate reporting and alarming
First Step? Options study –1 – Refurbish existing plant –2 – New clarifier & refurbish existing filters –3 – New clarifier & membrane filtration –4 – Membrane filtration only Include –New intake at Glenore Weir
Which Option? CAPEX Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only $ 2,401,000$ 3,046,000$ 4,346,000$ 4,355,000 OPEX Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only $ 277,000$ 253,000$ 369,000$ 359,000
Which Option? Estimated NPV Year Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only 15$ 4,595,000$ 4,986,000$ 7,183,000$ 7,106,000 20$ 4,943,000$ 5,305,000$ 7,647,000$ 7,558,000 25$ 5,181,000$ 5,522,000$ 7,964,000$ 7,865,000 30$ 5,315,000$ 5,644,000$ 8,142,000$ 8,039,000
Preferred Option New clarifier & refurbish existing filters –New air scour system –New washwater system –New chemical dosing –New buildings –Complete automation
Actiflo Clarifier
Implementation Construction issues –Operational plant (Normanton & Karumba) –Remote location (Materials & skilled labour) –Procurement (Australian & New Zealand) –WEATHER! –4 phase construction
Construction Sequence 1 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 ACTIFLO
Temp chemical dosing systems
Demolition
Construction Sequence 2 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
Fabrication
Staff Induction Training!
Construction Sequence 3 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
New pipe work and control valves
New Clarifier
Construction Sequence 4 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
New MCC Building
Filter Refurbishment
Filter Control
New chemical Dosing System
New WTP Building
WTP Performance Old Performance –Raw water quality Turbidity = 50 NTU –Old clarifiers Turbidity = 3 NTU –After refurbished filtersTurbidity = 1 NTU –Maximum flow (3 filters)= 36l/s! New Performance –Raw water quality Turbidity = 50 NTU –After Actiflo clarifier Turbidity = 1 NTU –After refurbished filtersTurbidity = NTU –Maximum flow (3 filters)= 50l/s!
WTP Performance
What Else? Additions to main contract –Norman River PS –Karumba chlorination system upgrade –Telemetry system upgrade –Procurement –Construction management –Commissioning
Lessons Learnt? Keep it simple Appreciation of location –Supply of materials –Available labour/contractors –Weather Build as much off site as possible Good working relationship with client
Why Use BTO? Excellence in Water & Wastewater Engineering They delivered on their promises: –on time –with clear reports & designs –with staff / resources promised –on budget BTO don’t just write reports – they get things done and deliver!
QUESTIONS???