WBS: Lowest level OBS: Lowest level
Advertisements

Chapter 7 Project Management
Chapter 17 Project Management McGraw-Hill/Irwin
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Chapter 3 Project Management.
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J Operations Management Project Management Chapter 3 - Heizer.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
Chapter 9 Project Management.
PERT/CPM Models for Project Management
2 Project Management  Management of work to develop and implement an innovation or change in an existing organization Examples: –New buildings –Weapon.
Operations and Supply Chain Management, 8th Edition
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Project Management OPIM 310-Lecture.
Chapter 16 – Project Management
Project Management. Introduction What – Project Management Where – Where the success or failure of a project will have major consequences for the company.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Roberta Russell & Bernard W. Taylor, III
Project Time Management
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Project Management © Wiley 2007.
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Operations Management Project Management
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Network Planning Methods Example PERT & CPM
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Lean Project Management
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 6 th Edition Chapter.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 17 Project Management.
Project Management (專案管理)
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
Project Management Chapter 16. MGMT 326 Foundations of Operations Introduction Strategy Managing Projects Quality Assurance Facilities Products & Processes.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Chapter 3 Managing the Information Systems Project
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Management - CPM/PERT. darla/smbs/vit2 Characteristic of a project A project is a temporary endeavour involving a connected sequence of activities.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Beni Asllani University of Tennessee at Chattanooga
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management Chapter 8.
Project Management.
Project Management Chapter Topics
Project Management: PERT/CPM
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Learning Objectives When you complete this chapter, you should be able to : Identify or Define: Work breakdown structure Critical path AOA and AON Networks.
Project Planning & Scheduling
Project Planning and Budgeting
Stevenson 17 Project Management.
Project Time Management
Presentation transcript:

Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter 9 Roberta Russell & Bernard W. Taylor, III

Copyright 2006 John Wiley & Sons, Inc.9-2 Lecture Outline   Project Planning   Project Scheduling   Project Control   CPM/PERT   Probabilistic Activity Times   Project Crashing and Time-Cost Trade-off

Copyright 2006 John Wiley & Sons, Inc.9-3 Characteristics of Projects  A unique, one-time activity or effort  Defined end product or result, with specific performance requirements, budget, and completion date  Usually require cross-functional teams, composed of people with different skills  Often involve uncertainty and risk

Copyright 2006 John Wiley & Sons, Inc.9-4 Examples of Projects  Construction or major renovations  Creating new computer software  Starting a new business  Designing and launching a new product or model  Evaluating a merger or acquisition  Designing new equipment  Selecting and installing new equipment or software  Writing a new human resources manual

Copyright 2006 John Wiley & Sons, Inc.9-5 Project Elements  Objective  Scope  Contract requirements  Schedules  Resources: equipment, materials, people  Managing people  Control  Risk and problem analysis

Copyright 2006 John Wiley & Sons, Inc.9-6 Project Manager  Leader of project team  Responsible for satisfactory completion of project Goals accomplished Goals accomplished Completed on time Completed on time Completed within budget Completed within budget Conformance quality Conformance quality

Copyright 2006 John Wiley & Sons, Inc.9-7 Project Team Organizations  Matrix organization: each team member reports to functional manager and to project manager. Team members work part-time on the project and spend the remaining time on their regular job.  Project management organization: Each team member works full-time on the project and reports to the project manager.

Copyright 2006 John Wiley & Sons, Inc.9-8 Project Management Process  Project planning  Project scheduling  Project control

Copyright 2006 John Wiley & Sons, Inc.9-9 Project Planning  Scope statement: specifies project objectives and expected results  Statement of work: describes the project in enough detail so that suppliers and contractors can submit bids May be divided into work packages for different project tasks May be divided into work packages for different project tasks Statements of work can also be prepared for team members or company departments Statements of work can also be prepared for team members or company departments

Copyright 2006 John Wiley & Sons, Inc.9-10 Project Planning (2)  Work breakdown structure (WBS) breaks down a project into components, subcomponents, activities, and tasks breaks down a project into components, subcomponents, activities, and tasks  Responsibility assignment matrix: shows who is responsible for various tasks in a project

Copyright 2006 John Wiley & Sons, Inc.9-11 Work Breakdown Structure for Computer Order Processing System Project

Copyright 2006 John Wiley & Sons, Inc.9-12 Work Breakdown Structure Details  Lowest level component for any branch is called a work package.  A work package should be defined so that it can be accomplished by an individual, department, team, contractor, supplier  Clear criteria for completion of each work package.

Copyright 2006 John Wiley & Sons, Inc.9-13  Organizational Breakdown Structure a chart that shows which organizational units are responsible for work items a chart that shows which organizational units are responsible for work items  Responsibility Assignment Matrix shows who is responsible for work in a project shows who is responsible for work in a project

Copyright 2006 John Wiley & Sons, Inc.9-14 Project Scheduling  Steps Define activities Define activities Sequence activities Sequence activities Estimate time Estimate time Develop schedule Develop schedule  Techniques Gantt chart Gantt chart CPM CPM PERT PERT Microsoft Project Microsoft Project

Copyright 2006 John Wiley & Sons, Inc.9-15 Gantt Chart   Graph or bar chart with a bar for each project activity that shows passage of time  Provides visual display of project schedule   Slack amount of time an activity can be delayed without delaying the project

Copyright 2006 John Wiley & Sons, Inc.9-16 |||||||||| Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work MonthMonth Example of Gantt Chart

Copyright 2006 John Wiley & Sons, Inc.9-17 Critical Path Method (CPM)  Critical path method (CPM) - inputs Activities from work breakdown structure Activities from work breakdown structure Precedence relationships among activities Precedence relationships among activities (what activities must be completed before other activities can be started) One time estimate for each activity (how long does it take to do the activity?) One time estimate for each activity (how long does it take to do the activity?)  Use CPM when activity times can be estimated accurately

Copyright 2006 John Wiley & Sons, Inc.9-18 Critical Path Method (2)  Critical path method (CPM) – outputs Project completion time Project completion time Start and end times for each activity Start and end times for each activity Critical path: activities that must be finished on time so that the project will be completed on time Critical path: activities that must be finished on time so that the project will be completed on time

Copyright 2006 John Wiley & Sons, Inc.9-19 Project Evaluation and Review Technique (PERT)  Project evaluation and review technique (PERT) – inputs Activities from work breakdown structure Activities from work breakdown structure Precedence relationships among activities Precedence relationships among activities 3 time estimates for each activity 3 time estimates for each activity  Use PERT when activity times are hard to estimate (example: new technology)

Copyright 2006 John Wiley & Sons, Inc.9-20 Project Evaluation and Review Technique (2)  Project evaluation and review technique (PERT) – outputs Estimated start and end dates for each activity Estimated start and end dates for each activity Normal distribution for project completion date Normal distribution for project completion date Probability of finishing the project by the mean date = 50% Probability of finishing the project by the mean date = 50% Standard deviation Standard deviation Can compute probability of finishing project by the due date Can compute probability of finishing project by the due date

Copyright 2006 John Wiley & Sons, Inc.9-21 Project Control  Time management: keeping the project on schedule by shifting resources to critical activities If it is necessary to pay overtime or use a more expensive resource, then project costs will increase. If it is necessary to pay overtime or use a more expensive resource, then project costs will increase.  Cost management  Quality management

Copyright 2006 John Wiley & Sons, Inc.9-22 Project Control  Performance measurement Earned Value Analysis Earned Value Analysis a standard procedure for numerically measuring a project’s progress, forecasting its completion date and cost and measuring schedule and budget variation a standard procedure for numerically measuring a project’s progress, forecasting its completion date and cost and measuring schedule and budget variation  Communication  Enterprise project management: simultaneous management of multiple projects and required resources

Copyright 2006 John Wiley & Sons, Inc.9-23 Project Network   Activity-on-node (AON) nodes represent activities, and arrows show precedence relationships Branch Node

Copyright 2006 John Wiley & Sons, Inc.9-24 AON Network for House Building Project Start Design house and obtain financing Order and receive materials Select paint Select carpet Lay foundations Build house Finish work

Copyright 2006 John Wiley & Sons, Inc.9-25 Paths  A path is a route through a network that begins at the first activity and ends at the last activity.  The length of a path is the sum of times for the activities on the path.  The critical path is the longest path in a network (path with highest length) There may be more than one critical path. There may be more than one critical path.  In PERT and CPM, the greatest amount of management attention is focused on activities on the critical path.

Copyright 2006 John Wiley & Sons, Inc Start Critical Path  Critical path Longest path through a network Longest path through a network Minimum project completion time Minimum project completion time A: = 9 months B: = 8 months C: = 8 months D: = 7 months

Copyright 2006 John Wiley & Sons, Inc.9-27 |||||||||| Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work MonthMonth Early Finish Schedule

Copyright 2006 John Wiley & Sons, Inc.9-28 Node Configuration Activity number Activity duration Earliest start Latest start Earliest finish Latest finish

Copyright 2006 John Wiley & Sons, Inc.9-29 Forward Pass   Start at the beginning of CPM/PERT network to determine the earliest activity times   Earliest Start Time (ES) earliest time an activity can start ES = maximum EF of immediate predecessors   Earliest finish time (EF) earliest time an activity can finish earliest start time plus activity time EF= ES + t

Copyright 2006 John Wiley & Sons, Inc.9-30 Earliest Activity Start and Finish Times Start Design house and obtain financing Select paint Lay foundations Select carpet Build house Finish work Order and receive materials

Copyright 2006 John Wiley & Sons, Inc.9-31 Backward Pass   Determines latest activity times by starting at the end of CPM/PERT network and working forward   Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t   Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors

Copyright 2006 John Wiley & Sons, Inc.9-32 Latest Activity Start and Finish Times Start Design house and obtain financing Select paint Lay foundations Select carpet Build house Finish work Order and receive materials

Copyright 2006 John Wiley & Sons, Inc.9-33 Slack  Slack = EF – ES = LF – LS  Activities on the critical path have zero slack.  Non-critical activities have positive slack.

Copyright 2006 John Wiley & Sons, Inc.9-34 * Critical Path *7* *4* *2* *1*1 Slack S EF LF ES LS Activity Activity Slack

Copyright 2006 John Wiley & Sons, Inc.9-35 Schedules  Early start schedule: each activity is scheduled to start on its ES date.  Late start schedule: each activity is scheduled to start on LS date.  Scheduling for non-critical activities may depend on when resources are needed for other projects.