LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine,

Slides:



Advertisements
Similar presentations
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
Jean-Claude Guillaume ATOP Days – CERN, 5 March 2009 Review of irradiated cables in the SPS Part I – Present strategy Jean-Claude Guillaume Cables and.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Upgrades and Activities of 13kA EE systems during LS1 Bozhidar Panev TE-MPE-EE
ATC / ABOC Days – Session 4 – January D. Smekens AT-MCS-MNC 1 MAGNETS FOR SPS & BEAM LINES MTTR & Spare Policy for the LHC Injectors & Exp.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
SPS RESTARTING AFTER LS1 05/03/2015 Stéphane Cettour Cavé.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Davide Tommasini Status and prospects of the PS magnet consolidation program ATOP Days March 4 th – 6 th 2009 Status and prospects of PS magnets programs.
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
CMS Proposal for a Maintenance & Operation agreement with EN/CV/DC for fluorocarbon detector cooling circuits v.2 P. Tropea For the CMS experiment.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
BA6 Cooling Towers Test Day Process Control Functionality and Performance Tests TCR – PCR Monitoring.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
1 Feedback on Warm Magnet Activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section With contributions from: P. Catherine, M. Dumas, P. Fessia,
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
Extraction and beamline progress B.Goddard TE/ABT.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
18, 19, 20 February 2002 Power Converters for magnets (PBS 1.2.3) R. GENAND SL/PO 1 Power Converters for Magnets –Introduction –Specification Magnet characteristics.
TE-CRG Activities D. Delikaris, TE-CRG.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
Insertion of 2 MBB with new coated vacuum chambers during technical stop week 35 J. Bauche for the SPSU study group, 24 June 2010.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
S A Griffiths CM42 June 2015 Electrical & Control.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Mikhail Ovsienko TE-MPE-EE
Magnet activities in SPS during EYETS
TE-MSC activities in SPS during LS2
Ongoing consolidation of magnets
ELENA installation and commissioning status
AD consolidation activities in LS2
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
SPS EN-CV Planning LS (initial draft)
EN-STI activities in LHC during EYETS
the CERN Electrical network protection system
TE-MSC activities in SPS during YETS
Magnet electrical and hydraulic (dis)connections for coating
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Experimental Areas – LS2 planning
Hardware Commissioning
Presentation transcript:

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine, K. Cunnington, M. Dumas

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 2 Outline MNC maintenance program Inspections, tests and outcome Magnet activities during LS1 Summary and acknowledgments

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 3 MNC maintenance program  MNC magnet maintenance program in IEF Beam operation: intervention 24h/24 (piquet + experts) Short technical stops: systematic visual inspections; corrective maintenance Short shutdowns: previous + audio-visual inspection in pulsed mode; electrical tests; preventive maintenance; small consolidations Long shutdowns: previous + thermal inspections; large consolidations; major activities in highly radioactive areas  Associated with suitable spare policy Continuous refurbishment of large magnet families with few spares Certification program to prepare spares “ready to install” for all magnet types with (in progress, prioritized with magnet risk score for beam operation)  Ultimate goal: mitigate MTTR and MTBF Nota: Operation mode with ~monthly TS, yearly SD and ~ 5-yearly LS convenient to magnet maintenance rhythm !

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 4  Conditions required: All technical services, infrastructure, power converters available Support from BE/OP and other equipment groups Safety: access restricted to magnet experts; consignations; EIS out of chains  Planning Coordination of several non-MNC activities during inspection campaign: lift maintenance, TT10 geodesic survey, IT works in BA’s, VIC’s Inspections and Tests Campaign

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 5  To detect coil movements or mechanical degradation  Magnets concerned Main dipoles and quadrupoles (960) Transfer line quadrupoles type QTL/QNL/QWL (~200)  Test process Removal of magnet covers Audio-visual inspection in pulsed mode  Cure actions Typically, replacements of most critical elements (early detection!) Shimming in situ often possible for transfer line quadrupoles  Occurrences in LS1 inspections In average with previous years 8 main dipoles, 5 main quadrupoles and 1 transfer line quadrupole will be exchanged in 2013  already started, should be completed in June Audio-visual inspection in pulsed mode Inspections, Tests and Outcome

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 6 Inspections, Tests and Outcome  Example of coil movement on QNL magnet

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 7  To detect weaknesses in coil ground insulation  Magnets concerned Main dipoles and quadrupoles (960) (Other magnets in case of failure in operation)  Test process Machine closed, in dedicated configuration (CIS system of EPC) Separation of power converters from load Test +/- 6kV on dipole and +/- 4 kV on quadrupole circuits  To be noted Busbars and water cooled cables are tested together with magnets!  Outcome of LS1 test No failure High voltage tests Inspections, Tests and Outcome

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 8  To detect weaknesses in coil inter-turn insulation  Magnets concerned Main dipoles (3 x 248) (Other magnets in case of failure in operation)  Test process Physical fencing and marking of sector (or machine closed) Separation of load from power converters 1.5 kV discharge on individual magnets (no busbar disconnection)  Campaign organization Started in SD 2010/ sectors/year, first round finished this year  Occurrence in LS1 inspections 1 MBB in position  beam orbit perturbations detected in last months of 2012 operation! Capacitive discharge tests Inspections, Tests and Outcome

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 9 Inspections, Tests and Outcome  Inter-turn short circuit response to capacitive discharge MBB SD 2011/2012 MBB LS1

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 10  To detect clogged cooling circuits in coils and loose electrical connections  Magnets concerned All magnets (~3000!)  Test process Removal of all magnet covers Machine closed, magnets pulsing with maximum RMS Inspection of coil surfaces and electrical terminals with thermal camera  Campaign organization ~2 weeks needed to remove / reinstall all magnet covers!  only during LS  Findings in LS1 campaign Cooling circuit restriction on MBB  magnet has already been removed for manifold inspection in workshop Several minor problems of loose connections, but one major… Thermal inspections Inspections, Tests and Outcome

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 11  Smoldering connection on LSF interconnection box Inspections, Tests and Outcome

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 12 Inspections, Tests and Outcome  Smoldering connection on LSF interconnection box

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 13 Inspections, Tests and Outcome  Examples of other minor issues of loose connections Untightened power cabling connection to MBBT magnet in TT20 MBI interconnection copper strands in TI8

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 14  Replacement of 20 magnets 8 main dipoles, 5 main quadrupoles and 1 TL quadrupoles for coil movements 1 main dipole with flow restriction on cooling circuit 1 main dipoles with inter-turn short circuit 4 main dipoles with loose pole shim temporarily repairs during the last 3 years  Organization 2 main dipoles and 2 main quadrupoles already exchanged this month 16 remaining will be exchanged in June, in between the cabling replacement campaigns Corrective / preventive maintenance Magnet activities during LS1 Main dipole exchange in the SPS

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 15  Coating of 16 dipoles and 4 quadrupoles from QF to QD Required for further studies of electron cloud mitigation with aC coating during next beam run  Organization All magnets have already been removed in one go from machine last week Refurbishment and certification of magnets before coating in situ Reinstallation of all magnets in one go at the end of LS1 to avoid multiple venting of vacuum sector LIU-SPS Hollow cathode coating equipment for SPS main dipoles (courtesy of P.Costa Pinto – TE/VSC) Magnet activities during LS1

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 16 Magnet activities during LS1  Replacement of all EPDM-Kevlar hoses in SPS complex 2000 hoses procured since 2010, were waiting for appropriate time slot Cleaning of all filters and inspection of busbars to take place in parallel  Organization Collaboration with NCBJ Institute (Poland) for additional manpower from September to December 2013 (to be approved) Transparent for other SPS activities (in the shadow of EN/CV works) Consolidation of magnet cooling supply Delaminated cooling hose Cleaning of cooling water filters

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 17  Suppression of weak electrical contacts of water pressure and water temperature interlocks False triggering of interlock system  important part of piquet interventions Shunt of redundant security signals with versatile solution  On all magnets in the NEA  Transparent for other NEA activities North Experimental Area kg/cm² Interlock circuit Manometer with gold tip contacts corroding due to water pressure oscillations Magnet activities during LS1

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 18  Improvements to magnet supply circuits Upgrade of hoses interconnections with full metallic sealing Replacement of obsolete electro-valves and check valves by manual valves Proper sleeving of power cable interconnections  In the frame of the TDC2 / TCC2 consolidation project North Experimental Area – TCC2 Quick connector gaskets degraded by irradiation Improper electrical connections to be sealed with appropriate sleeves Magnet activities during LS1

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 19  EN/EL – Irradiated cable replacement campaign in SPS LSS1+ Requires removal / reinstallation of some 20 magnets  Magnet work package in preparation for ALARA committee Requests from other groups Layout of LSS1 dumping region  GS/SE – Civil engineering works in TT10 and TDC2 tunnels Requires removal / reinstallation of ~8 quads in TT10 and 3 splitters in TDC2  In the frame of the TDC2 / TCC2 consolidation project Magnet activities during LS1

LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 20 Summary and Acknowledgements  New operation mode of accelerators with ~monthly TS, yearly SD and ~ 5-yearly LS convenient to magnet maintenance rhythm  Inspections and tests campaign –Stable situation of known issues, but ambitious magnet replacement program –Inspections in highly radioactive areas to be performed later in LS1 –Regular electrical connection tightening campaign should be restarted  SPS magnet activities during LS1 –Major activities: TDC2-TCC2 and LSS1, magnet replacements for maintenance and LIU e-cloud, cooling hoses consolidation –Magnet activities generating co-activity interferences already mostly planned  We acknowledge our colleagues for: –Their support to our activity… and their understanding! –Having ensured the availability of all systems during our inspections