Fermilab Project Overview Michael Lindgren 2014 EVMS Surveillance Review 10-Dec-2014.

Slides:



Advertisements
Similar presentations
DOE Office of Science Budget Overview
Advertisements

Global Congress Global Leadership Vision for Project Management.
Director’s Welcome Jonathan Dorfan 32 nd Annual SSRL Users Meeting October 17, 2005.
Management’s preliminary comments to the ERC Report.
Beyond the ALCPG David B. MacFarlane Associate Laboratory Director for PPA.
IT Project Management Office
Department of Energy Office of Science Report from DOE Office of High Energy Physics Report from DOE Office of High Energy Physics Dr. Robin Staffin Associate.
A Possible Strategy Towards a Future Lepton Collider Tor Raubenheimer SLUO Annual Meeting September 17, 2009.
By Saurabh Sardesai October 2014.
Planning, Goals and Desired Outcomes Jack Anderson Fermilab Winter 2013 Operations Workshop February 20, 2013.
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
HEPAP and P5 Report DIET Federation Roundtable JSPS, Washington, DC; April 29, 2015 Andrew J. Lankford HEPAP Chair University of California, Irvine.
American Neutrino Strategy: Consequences of P5 Report Jim Strait, LBNE Project Director NuFact August 2014.
Long Range Planning Pier Oddone September 24, 2007.
1 Project Management Introduction. 2 Chap 1 What is the impact? 1994: 16% of IT projects completed “On-Time” 2004 : 29% of IT projects “On- Time” 53%
21 August 2006P Dornan - After ISS1 Discussion  NuFact Talks Comments  Report 1 st Draft Oct – 60 Pages per WG Finalise before end of the year.
Physics Priorities S. Dawson July 11, 2007 Fermilab Steering Committee Meeting.
Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
Cost and Engineering Working Group Introduction Jim Strait Fermilab LBNE Project Manager Deputy Chair, Cost and Engineering Working Group LBNE Reconfiguration.
All Hands Meeting FY 2008 Budget Pier Oddone Fermilab December 20, 2007.
11 Welcome to All! October 26-28, 2009 Washington, D.C. Welcome to All! Accelerators for America’s Future Symposium and Workshop October 26-28, 2009 Washington,
Challenges & Issues for SBNE Nigel S. Lockyer 4/4/14.
11 DOE Office of Science High Energy Physics Program AAAC Meeting October 15, 2009 National Science Foundation Dennis Kovar Associate Director of the Office.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
Summary Comments and Discussion Pier Oddone 40 th Anniversary Users’ Meeting June 8, 2007.
PIP-II: Why a new accelerator? Paul Derwent Fermilab Community Advisory Board 23 July 2015.
LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session.
Management’s preliminary comments to the ERC Report FINANCE COMMITTEE June 19, 2002.
News Y2K June 25, Summary of June 12 Face-to-Face Meeting.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
Management February 20, Annual Review of the Muon Accelerator Program (MAP) Subcommittee members: Ron Prwivo, Ron Lutha, and Jim Kerby.
Fermilab: Present and Future Young-Kee Kim Data Preservation Workshop May 16, 2011.
Budget Outlook Glen Crawford P5 Meeting Sep
Anthony Indelicato DOE-Princeton Site Office February 2014 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Fermilab Introduction, Strategy and News Stuart Henderson Fermilab Science & Technology Review November
Nigel Lockyer Fermilab Operations Review 16 th -18 th May 2016 Fermilab in the Context of the DOE Mission.
Connecting executives to meet America’s challenges January 2012 INFORMATIONAL BRIEFING Leading EDGE Program Overview.
DUNE Collaboration Meeting September 4, 2015 Glen Crawford Research and Technology Division Director Office of High Energy Physics Office of Science, U.S.
Nigel Lockyer Fermilab Operations Review 16 th -18 th May 2016 Fermilab in the Context of the DOE Mission.
Project Management Update Jack Anderson Interim Laboratory Director/ Chief Operating Officer for Earned Value Management System Review Team August 19,
CMS Crosscut Operations and Research, Theory, Computing, University Involvement C. Young and B. Zhou.
CPAD Instrumentation Frontier Meeting October 5-7, 2015 Glen Crawford, Helmut Marsiske Office of Science, U.S. Department of Energy DOE Office of High.
FRA Earned Value Management System Implementation Project October 9, 2008 Dean Hoffer / Elaine McCluskey.
Workshop Goals and Project Management “120A ” – FY15 Budget Request Steve Holmes PIP-II Budget Retreat July 22, 2014.
Computing All Hands Meeting Rob Roser 20 February 2015.
HEPAP Facilities Subpanel and the Cosmic Frontier SLAC Snowmass Cosmic Frontiers Meeting March 6, 2013 Josh Frieman Fermilab and University of Chicago.
CPM 2012, Fermilab D. MacFarlane & N. Holtkamp The Snowmass process and SLAC plans for HEP.
PROTON ECONOMICS: Program Planning Steve Geer Institutional Review 11 February 2015.
Strategic Planning Process Erik Gottschalk Fermilab Physics Advisory Committee Meeting – June 22-25, June 2015.
Jim Siegrist, Associate Director of Science for High Energy Physics 13 June 2012 Fermilab User’s Meeting or Program Development in HEP: DOE Perspective.
DUNE-UK Mark Thomson University of Cambridge DUNE-UK Meeting, UCL May 15, 2015.
A Post P5 Planning Exercise at Fermilab Greg Bock Fermilab PAC July 24, 2014.
Fermilab Budget Briefing FY 2014 Intensity Frontier Proton Research KA Breakout February 28, 2013 Office of High Energy Physics Germantown, MD.
Accelerator Division View Sergei Nagaitsev DOE Independent Project Review of PIP-II 16 June 2015.
1 CF lab review ; September 16-19, 2013, H.Weerts Budget and Activity Summary Slides with budget numbers and FTE summaries/activity for FY14 through FY16.
Welcome! Robert Zwaska 23 November 2015 Workshop on Booster Performance and Enhancements.
Particle Physics Sector Young-Kee Kim / Greg Bock Leadership Team Strategic Planning Winter Workshop January 29, 2013.
Head, Office of Project Management Oversight (OPMO)
An Executive View of the PMO
LHC Science Goals & Objectives
Capital Asset Projects executed by the
One ODOT: Positioned for the Future
Snowmass on the Mississippi
Employee engagement Delivery guide
Organization Design Project support overview Presenter's Name
Growth and innovation Project support overview.
Preliminary Project Execution Plan
Engaging Senior Executives
Presentation transcript:

Fermilab Project Overview Michael Lindgren 2014 EVMS Surveillance Review 10-Dec-2014

Overview Landscape for Particle Physics has changed since last review –Effective Project management more imperative than ever Decadal effort in HEP through Snowmass and P5 process –Process brought clarity to direction for US Particle Physics Drives what projects the DOE will invest in –Clear roadmap to follow for the next decade New lab director renewed focus on Projects –Chief Project Officer position created Lab Technical Resource Coordinator position created –Integrated Planning and Performance Management (IPPM) –Project Support Services (OPSS) strengthened 12/10/14Mike Lindgren | EVMS Surveillance Review2 Fermilab is committed to excellence in project management so we can deliver the science

12/10/14Mike Lindgren | EVMS Surveillance Review3 P5 guidance for US HEP

Projects - Since last year Excellent progress on NOvA and MicroBooNE: –NOvA complete - on budget and on schedule. –MicroBooNE CD-4 review tomorrow –3rd and 4th projects after MINERvA and DES delivered on budget and on schedule LCLS-II – BES accelerator project, pre-CD-2 PIP-II (accelerator replacement) not yet at CD-0 LBNF – (Neutrino’s), international project –Intense focus on redefining from LBNE over past year Mu2e, Muon g-2 – (Muon experiments) Have CD-1 –Expect Baseline+ in FY15 SLI Utility Upgrade – Baseline review this week CMS Phase One upgrade (LHC) has CD-2/3 12/10/14Mike Lindgren | EVMS Surveillance Review4

Executing the Strategy The Chief Project Officer is accountable for the successful execution of our project portfolio in concert with successful operation of the scientific program Projects/Programs are located within Divisions –PIP-II: Accelerator Division –LARP, LCLS-II: Technical Division –CMS upgrades, Mu2e, Muon g-2, Cosmic Frontier: PPD –All neutrino projects: Neutrino Division To succeed on this slate of big projects requires –Increased focus on resource management Dedicated person with authority to span Divisions/Sections –Outstanding project management systems Processes, Tools and People EVM System is critical PM tool 12/10/14Mike Lindgren | EVMS Surveillance Review5

Earned Value We have a built in motivation to complete these projects on cost and schedule –The people building them get to participate in the scientific research done by the product, but –Without oversight help and tools they will not succeed –Hope to demonstrate projects and lab commitment to EV It is now a standard tool for all CD projects Used by more than CD projects – AIP’s and GPP’s using also EV is critical component of projects management of toolkit, and also for oversight groups to measure progress –Have taken recommendations seriously –Hope to demonstrate that we have done so 12/10/14Mike Lindgren | EVMS Surveillance Review6

Getting to Success Recent delivery of multiple projects on time and budget, but –Every one could have been better managed in one area or another (or multiple areas) –Impacts SC confidence of ability to deliver OPA workshop at ANL – summer 2014 –Terrific opportunity to learn from each other –Many common PM issues across labs Steps at Fermilab –Strengthened OPSS Multiple new people – Marc and Rich talk next –Created IPPM – Erik Gottschalk –Several initiatives to identify improvement opportunities External – embracing suggestions and criticisms Internal – New people, new ideas 12/10/14Mike Lindgren | EVMS Surveillance Review7

Lab engagement with Projects Lab has a critical role in project management and construction –Work closely with DOE Program Managers and FSO PD’s DOE attend most lab oversight/management meetings Oversight/engagement through –Project Management Group (PMG) Monthly for each project –Performance Oversight Group (POG) Monthly for all projects together –Cost and schedule (EV) performance reviewed at both –Valuable for Lab, DOE, and Project CPO, OPSS, IPPM, focused on project success –We are here to help projects succeed –Re-thinking approaches and tools 12/10/14Mike Lindgren | EVMS Surveillance Review8

In Closing Our future depends greatly upon our performance in project management. –Last four projects delivered on time and budget –Must continue improvements to succeed on larger scale Lab committed to continue to build an integrated system that supports our Projects and Project Managers. –We have learned from our experience and have taken advice from the review committees seriously. –Improvement initiatives take time, patience and persistence. Projects and lab management recognize the importance of EV as a management tool. 12/10/14Mike Lindgren | EVMS Surveillance Review9 Thanks for being here and taking the time to help. We welcome your questions, insights and recommendations